LEP cryostat Procurement strategy and plans

Slides:



Advertisements
Similar presentations
Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.
Advertisements

Modifying the interconnection thermal shields during LS1. Graeme Barlow - TE-MSC-CMI1.
1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
MICE Target Status Chris Booth Sheffield 10 th May 2006.
MICE Video Meeting, 10 Jan 081 Spectrometer Magnet Progress Michael A. Green Lawrence Berkeley Laboratory.
Richard F Boyce Injector UpdateL0-1 Accelerator 3 November L0-1 Design, Manufacturing & Testing R. F. Boyce, SLAC.
1 Presented at ColUSM by D. Ramos on behalf of the Cold Collimator Feasibility Study Working Group Longitudinal.
FNAL-SCRF 会議報告 1. Cryomodule, Plug-compatible Interface ( 大 内) 2. High Pressure Code, 5K Shield (Tom Peterson)
K. Alam, CLIC workshop, October 16-18, CLIC workshop, October 2007 Working group “ Two beam hardware and integration” Test module in the two.
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Collaboration Meeting at JLab, Virginia February 28, 2011.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
H. Prin, F. Savary, D. Duarte Ramos, L. Grand- Clement, C. Mucher, A. Temporal.
Engineering Department ENEN Status of TCSP manufacturing Collimation Working Group (CWG) 24 June 2013 A. Dallocchio, A. Bertarelli, F. Carra, L. Gentini,
Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay.
Brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Inner Triplet Review Q1, Q2, and Q3 Mechanics T. Nicol April 24-25, 2007.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM29 at RAL, UK February 17, 2011.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
Summary ( Cryomodule, Plug-compatible Interface) Norihito Ohuchi.
The HCAL barrel absorber structure
Main features of PETS tank J. Calero, D. Carrillo, J.L. Gutiérrez, E. Rodríguez, F. Toral CERN, 17/10/2007 (I will review the present status of the PETS.
LAr Week Feb 2000 M. Lefebvre Milestones and Schedule General Production Readiness Review  Passed in Jan 99 Leak Test Station and Electric Test.
FP420 R&D Project – Brainstorming session on mechanics 28 March 06 1 D. D. INFN To/CERN PH CMM FP420 Integration Environment.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
Enrique Calvo Alamillo Ds DHCAL m 3 modular structure. 2. Basic modular distribution. 3. Guiding and repositioning system. 4. Detector.
The integration of 420 m detectors into the LHC
Matthew Moulson for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 11 December 2012 LAV construction & installation status.
HL-LHC 11 T Dipole for DS Collimation 8 th to10 th December, 2014 D. Duarte Ramos, C. Mucher, L. Gentini, T. Sahner, H. Prin, R. Wawrowski, F. Savary,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
LHC Machine Advisory Committee Meeting no.19 QRL status 16 June 2006 G. Riddone, AT-ACR On behalf of the QRL team.
ColUSM #63 18 th September, 2015 D. Ramos, C. Mucher, L. Gentini, H. Prin, Q. Deliege, A. Bastard, J. Hrivnak.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
EuCARD-WP7-HFM meeting 15 November 2011 Status of construction of FRESCA2 dummy coil assembly Attilio Milanese, Juan Carlos Perez.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
CERN – ENGINEERING DEPARTMENT: A. Dallocchio on behalf of EN-MME
The Super-FRS Multiplet, Magnetic and Cryogenic requirements
Cryostats for superconducting magnets
High energy beam transport.
CERN – ENGINEERING DEPARTMENT: A. Dallocchio on behalf of EN-MME
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973
CERN – Zanon discussions
D. Ramos, H. Prin, M. Moretti, C. Eymin, A. Temporal, V. Parma, S
Cold mass design, assembly plans and QA/QC at CERN
Roadmap for triplet cryostats
11 T Dipole Integration & Plans M. Karppinen
Internal review of IR2 LEP cryostats (WP11/WP5) Close out session
HFM Test Station Main Cryostat
Cryostat procurement, status and plan, QA/QC
F.E.T.S. Mechanical Engineering Update
Status of design and production of LEP connection cryostat
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
Cryo-assembly design D. Ramos, V. Parma, C. Mucher, H. Prin, M. Souchet, J. Hrivnak, M. Moretti, L. Mora, F. Savary, L. Gentini Review of the 11T Dipoles.
Flexible lines production and planning
Status of cryostat integration and conceptual design
LS1 Committee January 24th, 2014
Consolidation and Upgrade of the LHC Experimental Vacuum Systems
EHN1 Neutrino Installation Plans
From Design to Installation courtesy R. Folch S. Atieh TS / MME
Far Detector Activities Late 2017 – Early 2018
Parts exchange for HL-LHC AUP Q1&Q3
The 11T cryo-assembly: summary of design and integration aspects
Design of Distribution Feedbox at LHC P7
Status of the PANDA Solenoid Magnet Production in BINP
MQXF updates P. Ferracin October 9th, 2014.
PANDA The conceptual design of the control Dewar
Ch. Boccard, M. Krupa, G. Schneider, R. Veness, M. Wendt
UPPSALA UNIVERSITY_GERSEMI PROJECT
Production Cryo HL-LHC BPMs
Progress on cryostat design and production
Cryogenic upgrade of B163, B165 & B253 Status Meeting 19th December 2018
Presentation transcript:

LEP cryostat Procurement strategy and plans A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN Internal review of IR2 LEP cryostats (WP11/WP5)– 17 May 2017

Summary Introduction Procurement strategy Main components Plans and Schedule Conclusion A. Vande Craen

First unit to be assembled from November 2017 Introduction LEP composed of > 250 different components for a total of > 1800 pieces Ranging from standard screws to busbars not forgetting large machined plates and pressure vessel First unit to be assembled from November 2017 Series assembled through 2018 A. Vande Craen

Procurement strategy and plans A. Vande Craen

H-beam plates Specific Procured through EN-MME Stainless steel 304L Tight tolerances (flatness <= 0.2 mm/m) Large dimensions < 0.1 % cobalt content Procured through EN-MME Due to tight tolerances, will be manufactured in house Delivery of first unit Mid-October 2017 A. Vande Craen

Shuffling module Specific Procured by TE-MSC-CMI 3 types Magnet side (identical for Type A and B) Type A, LEN side Type B, LEN side Pressure bearing assembly Tight tolerances < 0.1 % cobalt content Procured by TE-MSC-CMI Specification ready, IT will follow Delivery of first unit expected Mid-October 2017 A. Vande Craen

Small machined components Specific Flanges in 316LN, 3D forged (EDMS 790773) Other components in 304L <0.1 % Cobalt content Procured through EN-MME (subcontracting) Drawings finished end of May Delivery of first unit expected October 2017 A. Vande Craen

Follow-up by TE-MSC-CMI From CERN store Pipes Specific 4 different diameters (M, N, X, V’ lines) 3 standards 1 non-standard (X line) According to specification EDMS 1380627 Follow-up by TE-MSC-CMI From CERN store A. Vande Craen

Designed and manufactured by TE-MSC-LMF Busbars Designed and manufactured by TE-MSC-LMF Delivered with supports and insulation First set ready for October 2017 (see R. Principe’s presentation) A. Vande Craen

LHC standard components Type Cold bores Support posts (fixed and sliding) Interconnection flanges Bellows In stock A. Vande Craen

Standard components Type Follow-up by TE-MSC-CMI Screws, nuts, washers Taps O-rings Braids Follow-up by TE-MSC-CMI List finished end of May Procurement in the shadow of other components A. Vande Craen

MLI Specific Contract follow up by TE-MSC-CMI Contract will include design and manufacture According to CERN specification Contract follow up by TE-MSC-CMI Specification ready, IT will follow Delivery of first unit expected October 2017 A. Vande Craen

Vacuum vessel Specific In combination with 11T cryostats 2 types (Type A and Type B) In combination with 11T cryostats Contract follow up by TE-MSC-CMI (M. Struik) Contract placed Delivery of first unit expected end of October 2017 A. Vande Craen

Bottom tray Specific Contract follow up by TE-MSC-CMI First unit machined at CERN DR created for series In combination with 11T bottom trays Contract follow up by TE-MSC-CMI Delivery of first unit expected end of October 2017 A. Vande Craen

Schedule summary A. Vande Craen

Conclusion A. Vande Craen

Conclusion Procurement strategy and roles well defined Follow-up of so many components is challenging Ready for assembly of first unit in November 2017 Ready for series production in January 2018 Last components at CERN in April 2018 A. Vande Craen

Thank you ! A. Vande Craen