GLAST Large Area Telescope:

Slides:



Advertisements
Similar presentations
J.P. Langston Brake Retrofit
Advertisements

Tracker Subsystem1 GLAST LAT Project FM8/14 PSR, Oct. 5, 2005 GLAST LAT Tracker Towers 8/14 Pre-Ship Review INFN-Pisa.
Power Screw and Springs
GLAST LAT ProjectMarch 24, 2003 HPS Tracker Peer Review, WBS Section 2-D 1 GLAST Large Area Telescope: Tracker Subsystem WBS Structural.
Aerospace Fastener Applications
GLAST LAT ProjectMonthly Review, September 1, Tracker SubsystemR. Johnson 1 GLAST Large Area Telescope: Tracker, W.B.S August Status Meeting.
TKR-Grid I/F Design Options Grid TKR Flexure Shoulder Bolt (close fit) Conical Bushing Grid TKR Flexure Shoulder Bolt Collar/Pin with conical head (pressed.
GLAST LAT ProjectOctober 14, 2002 Tracker, WBS GLAST Large Area Telescope: Tracker Subsystem WBS Engineering Meeting Tracker Engineering-Model.
July GLAST Project Installation Review LATLAT 1 Tracker Tower Installation Review Peter Amnuaypayoat
1 GLAST LAT ProjectMechanical Systems Mechanical Systems Mechanical / Thermal Hardware November 2004 Status Marc Campell, Subsystem Manager.
Tracker Subsystem1 GLAST LAT Project FM7/9 PSR, Sept. 9, 2005 GLAST LAT Tracker Tower7/9 Pre-Ship Review INFN-Pisa.
GLAST LAT Silicon Tracker Marcus ZieglerIEEE The Silicon Tracker Readout Electronics of the Gamma-ray Large Area Space Telescope Marcus Ziegler.
GLAST I&T January T Borden 1 Tracker EM Mechanical Mock-up T Borden I&T Tracker Mock-up.
Tracker Subsystem1 GLAST LAT Project FM-B PSR, 10 Feb, 2005 GLAST LAT Tracker Tower-B Pre-Ship Review Luca Latronico INFN-Pisa
GLAST LAT ProjectSubsystem Managers Meeting May 12, GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager.
Page 1 GLAST LAT ProjectAugust 30, 2004 GLAST Large Area Telescope: LAT Accelerometer and Thermal Instrumentation Review Presented by Leonard Lee John.
Tracker Subsystem1 GLAST LAT Project FM6 PSR, July 21, 2005 GLAST LAT Tracker Tower6 Pre-Ship Review INFN-Pisa.
GLAST LAT ProjectF-to-F, June 15, TrackerR.P. Johnson 1 GLAST Large Area Telescope: Tracker, W.B.S Face-To-Face June Meeting Robert Johnson.
GLAST LAT ProjectDecember 2, 2003 R. Johnson Engineering Meeting 1 GLAST Large Area Telescope: Tracker Subsystem WBS Tracker EM Vibration Test Status.
Please follow in manual AC CHAPTER 7
GLAST Large Area Telescope:
1 GLASTGLAST Pisa GLAST Italia meeting, 18/02/02 A.Brez – INFN Pisa GLAST:Gamma Ray Large Area Telescope Ladders, Trays and Towers Construction A.Brez.
NCSX Vacuum Vessel Joint Design Mike Viola PPPL July 1 st, 2003.
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Section Mechanical Systems X-LAT Assy1 GLAST Large Area Telescope: Mechanical.
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Document: LAT-PR-0XXXX Section 5.1 Grid Box Design 1 GLAST Large Area Telescope:
Tracker Production Overview Readout Cables UCSC, SLAC (Parlex) SSD Procurement, Testing SLAC,Japan, Italy (HPK) Electronics Fabrication, burn-in, & Test.
GLAST LAT ProjectMarch 24, A Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS A: Engineering Model Tower.
GLAST LAT ProjectMarch 24, G Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS G: Tower module assembly A.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems Mechanical / Thermal Hardware December 2004 Status Marc Campell, Subsystem Manager.
GLAST LAT ProjectMarch 24, B Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS B: EM Mini-Tower Robert Johnson.
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Section Mechanical Systems Radiator Assy1 GLAST Large Area Telescope: Mechanical.
GLAST LAT ProjectMarch 24, C Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS C: Electronics Module Testing.
GLAST LAT ProjectPisa 9/1/04 A.Brez 1 GLAST Large Area Telescope: Grid interface proposal Alessandro Brez INFN Pisa Gamma-ray Large Area Space Telescope.
GLAST LAT ProjectMarch 24, B Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS B: Electronic Parts & Materials.
1 FPA Stage 2 Peer Review May 12, 2006 T. Brown. 2 FPA Stage 2 Status Summary of Stage 2 activities Review current design status Review schedule details.
GLAST LAT ProjectCAL Peer Design Review, Mar 17-18, 2003 P. Dizon Naval Research Lab Washington DC GLAST Large Area Telescope Calorimeter Subsystem Gamma-ray.
LAT Design Integration and Analysis1 GLAST LAT Project24 May 2005 LAT Monthly Status Review 24 May 2005 Design Integration and Analysis LAT Monthly Status.
GLAST LAT ProjectDec 17, 2003 Page 1 GPR Design & Requirements Grid Perimeter Ring (GPR) Design –Ring is comprised of four lengths of Aluminum bolted together.
Tracker Subsystem GLAST LAT Project 1 ANNEX 1 to NCR/FM/INFN/PI/372 STATIC TEST TORQUE LOSS OUT OF SPEC’S ON BOTTOM TRAY S/N 005 Andrea Tenze
Annex 5 - Tower and Lock installation
GLAST Large Area Telescope:
GLAST Large Area Telescope:
Open Issues Modification of Cactus Arm bending tool required
GLAST Large Area Telescope:
GLAST Large Area Telescope:
7E: Tower test plans GLAST Large Area Telescope: Tracker Subsystem
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope
1. Introduction and Overview
GLAST Large Area Telescope:
Design Integration and Analysis
Mounting Considerations …
Lessons Learned and Earned Value Management System Assessment
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
TKR and LAT Survey and Alignment Planning
GLAST Large Area Telescope:
GLAST Large Area Telescope:
Introduction and Overview
Gattini Detector Installation
GLAST Large Area Telescope:
Bunker Wall Design Wall ESS
Design Integration and Analysis
GLAST Large Area Telescope: Tracker Subsystem WBS 4.1.4
US-HiLumi – Shipping Post Assembly Status
Tracker to Tracker Clearance Reduction Contributors
Presentation transcript:

GLAST Large Area Telescope: Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Status of Tracker EM Testing Engineering Meeting December 9, 2003 Robert Johnson Santa Cruz Institute for Particle Physics University of California at Santa Cruz Tracker Subsystem Manager rjohnson@scipp.ucsc.edu

Status of Tracker EM Testing Thermal-Vacuum test: Jack has edited the T/V test plan, but it is still riddled with TBDs. Jack Goodman and Tom McCarthy are in Italy this week to firm up the details of the plan and understand the temperature control in the Alenia chamber. Vibration Test—series of engineering working meetings this week Torque loss in the corner flexures was understood qualitatively: The torque spec was low, and no locking feature was used. The design relied upon friction to prevent movement by up to 4 mils within the tolerance between flexure and shoulder bolt, which could have started the loss of preload. Without tight support of the shoulder in the aluminum Grid, there was a potential for excessive bending stress on the bolt, which could have released the preload.

Status of Tracker EM Testing Resolution: Revise the design to ensure that the joint really behaves as a shear pin, as it was modeled, with no reliance on friction to hold the shear. Avoid high tolerance requirements for the Grid and flexure machining, but also avoid preloading stress back into the bottom tray. Introduce a locking feature for the bolts. SLAC concept (see drawings on the next page) Corner flexures: conical bushing self centers in the flexure Requires good precision on those 4 holes, matching TKR & Grid, to avoid preloading stress into the bottom tray. The bushing will fit tight into the flexure and Grid to act as a shear pin. It will be easy to get the bolt started in the threads. Side flexures: use an epoxy bushing (à la the Cal) to hold the shear load with essentially no alignment requirement.

Corner-Flexure-Grid Attachment Concept under study at SLAC, down-selected from 4 different proposals. Steel conical bushing self centers in the flexure and carries the shear load, with a tight fit in the Grid. The bolt just holds it in place. Grid TKR Flexure Shoulder Bolt Collar/Pin with conical head (pressed in) Martin’s first cut at the dimensions:

Corner-Flexure-Grid Attachment Sandro has proposed an extra bracket to be added to fix the flexure to the grid. Some issues to consider with this: Clearance inside the grid (e.g. calorimeter & TKR cables) Precision location of the 4 new holes (a friction mount won’t be accepted, so at least some of those holes will need shear pins). Grid Flexure Proposed Bracket

Other Work in Progress The EM tower was removed from the damaged vibration fixture and mounted on a new one, where it is being tested in Pisa with a very low level acoustic stimulus (ESPI system). No damage was seen to the helicoil inserts in the old fixture. Confirmed that only 2 of the 8 side-flexure bolts lost a slight amount of torque, despite completion of the full-level lateral vibration with all corner flexures disconnected. Work is under way at SLAC to procure and test 120-degree countersink screws to spread the load on the sidewalls and allow higher torque to be used there without damage to the carbon fiber. This is only a potential issue–none of these screws lost torque in the test. Other possibilities being considered to resolve this issue: Shimming the closeout inserts during assembly. Using inserts on all sidewall holes.

Prognosis MRB by Friday or Monday. Complete all design work before the holiday. CAD design of interface by Dec 11. Incorporate into the Tracker flight drawings and IDD by Dec 15. Retrofit the existing bottom-tray flexures and the vibration fixture in early January. Get back on the vibration tester at Alenia as early as January 19. The thermal vacuum test should follow the vibration, as we cannot run the vibration test with the thermocouples installed between trays.