Installation of the T600 at Fermilab

Slides:



Advertisements
Similar presentations
Cryomodule Helium Volumes Tom Peterson, Fermilab AWLC14 13 May 2014.
Advertisements

Sputter Stand Safety Specifics Electrical Hazards High Voltage : Electrical power is required for the high voltage supply, gauging, system controller and.
Bellow valve (trap&pump) Inside glove box. (Note: Ar glove box is not necessary, if you work with single crystalline organic materials like rubrene that.
LBNE 35 ton prototype Phase 1 summary Terry Tope Fermi National Accelerator Laboratory All Experimenters’ Meeting – Fermilab – May 19, 2014.
Review of Helium Venting Analyses
Magnet Cooldown Scheme 17 th February 2012 Roy Preece (STFC RAL)
AMS-02 Cryosystem Phase III Flight Safety Review January 12, 2010 Phil Mott.
1 Superconducting Magnets for the MICE Channel Michael A. Green Oxford University Physics Department Oxford OX1-3RH, UK.
LarTPC Electronics Meeting Current Work at MSU Fermilab Dan Edmunds 23-February-2010.
March 14, 2003 MICE Absorber/Coil Integration MICE LH2 Absorber 1.Assembly 2.Safety 3.Staging 4.Instrumentation.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
Fcal upgrade for sLHC: Cryogenics modifications – TE-CRG/ C.Fabre 1 ATLAS FCal Upgrade for sLHC: Modifications to the Calorimeter Cryogenic.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
Assembly Scenarios Draft 1 MODEL simulation based on CXUO-CRY-AP-001.
IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009.
SCU Segmented Cryostat Concept M. Leitner, S. Prestemon, D. Arbelaez, S. Myers September 2 nd, 2014.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
Exhaust to atmosphere G1 V1 V2 V3 LN2 Storage Vessel 150 l Dewar Cryostat Exhaust to atmosphere Nitrogen or helium gas bottle LN2 Circuit for MIT Test,
LH2 Safety Issues for MICE 1.O2/LH2 separation 2.No Ignition sources near LH2 3.Adequate ventilation 4.Affects: Windows: absorbers and vacuum Primary and.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Johan Bremer, 22th-26th September 2008 Cryogenics Operations 2008, CERN, Geneva, Switzerland 1 CRYOGENICS OPERATIONS 2008 Organized by CERN Safety aspects.
Neutrino Cryogenics Requirements Meeting 25/09/2014 Day 1 review.
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
Concept Design for LBNF Far detector (LAr single phase)
Installation of the T600 at Fermilab CSN2, September 22,
Long-Baseline Neutrino Facility LBNF Cryostats Systems Requirements on FSCF Marzio Nessi LBNF/DUNE DOE/SC CD-3a Director’s Review October 27-29, 2015.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
Tracker cooling plant refurbishment Project status Revised plan Financial impact.
AT-ECR/C.FabreMay 31, 2007 Cryogenics for Liquid Argon Calorimeters Caroline Fabre on behalf of the ATLAS Liquid Argon Cryogenics Collaboration.
MICE Coupling Coil Fabrication Steps to Complete Allan DeMello Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
JLAB Cryomodule Assembly Facilities Visit Report Tug Arkan, Yuriy Orlov March 26, 2012.
Installation of the T600 at Fermilab Fermilab, February 15,
Neutrino Platform Proximity Cryogenics Functional Design M.Chalifour 14/04/2016 M. Chalifour - TE/CRG-CI 2.
Single Phase ProtoDUNE TPC CERN The SP TPC Team Jan. 13, 2016.
Status Report of the Review of Vacuum Systems and Procedures Tug Arkan, Allan Rowe 3/7/
Max-Planck-Institut für Plasmaphysik 1 ICEC 26- ICMC 2016 March 7-11, 2016, New Delhi, India Michael Nagel Cryogenic commissioning, cool down and first.
WA105 6x6x6 Cryogenics David Montanari / Johan Bremer Sep 21, 2015 Rev. 1.
S A Griffiths CM42 June 2015 Electrical & Control.
ProtoDUNE Single Phase (NP-04) P&ID David Montanari (on behalf of Mark A, Johan B, Michel C, Joaquim C, Kevin H) CERN Neutrino Platform General Meeting.
WBS 1-7 System Assembly & Installation John Voirin August 10-11, 2011.
Final Design Cryogenic and mechanical configurations
Status CO2 Cooling IBBelle: Reconnection after Belle II Roll in
Teleconf ACS – FREIA 28th March 2017
Design of the thermosiphon Test Facilities 2nd Thermosiphon Workshop
IT-4189 Supply and installation of a cryogenic distribution system
Proximity Cryogenics P&IDs Meeting
protoDUNE – single-phase Instrumentation - Gas Analyzers
1.3-GHz Cavity Vacuum Furnace at IB4
Pre-installation and Functional Tests
Proximity Cryogenics P&IDs meeting
Cryoplant Installation Scope
First tests on the roll-formed field cage.
David Montanari / Johan Bremer Jun 11, 2015 Rev. 1
LARP Vertical Test Facility
1 Connect pumping equipment (group) with leak detector to insulation vacuum 1 or 2 pumping groups? connected to SB or CM or both? Which pumping group?
Aachen Status Report: CO2 Cooling for the CMS Tracker
CRYOGENICS OPERATIONS 2008 Organized by CERN
EHN1 Neutrino Installation Plans
Far Detector Activities Late 2017 – Early 2018
LN2 Circuit for MIT Test, September 2005
IBBelle: Status Commissioning at MPP Transport to KEK
Aachen Status Report: CO2 Cooling for the CMS Tracker
Overarching Commissioning Plan
SNS PPU Cryomodule Instrumentation
Cryomodule Assembly Plan
Teleconference ACS – FREIA 19th June 2017
SNS PPU Cryomodule Instrumentation
J. Fleiter, S. C. Hopkins, A. Ballarino
ICARUS Internal Cryogenic Sensors
Presentation transcript:

Installation of the T600 at Fermilab CERN, November 17, 2016

Installation of components on the roof CERN, November 17, 2016

Installation of the cold vessels After unloading from the truck and placement in the top building, the cold vessels will be inspected both externally and internally for general integrity of the TPCs. The feet under the cold vessels will be then installed prior to install the vessels in the final location inside the pit. Requirements to FNAL: internal and external cranes, unloading/loading personnel, moving docks, surveys, mains, ventilation, heating. CERN, November 17, 2016

Installation of Chimneys and final internal operations Readout cables will be taken from the inside of the cold vessels though the connecting “chimneys”. A survey of the TPCs will be performed. The ceramic resistances that connect the race tracks will be put in place. All other vacuum tight connections crossing the thermal insulation will be installed, including the pipe for LAr filling and recirculation. The manholes will be then definitively sealed. Chimneys LAr Filling line Internal cables LAr Distribution line Requirements to FNAL: cranes, crane drivers, mains, ventilation, heating. Manpower for operations on the detector: 4 mechanical technicians (2 CERN + 2 FNAL) + 1 supervisor Time: 7 days CERN, November 17, 2016

Internal vacuum tests Turbo pumps (2X) Vacuum pumps, valves, and vacuum gauges will be transported to FNAL and installed on the chimneys. All ports of the Argon circuit (“chimneys”, etc.) will be temporarily closed and vacuum pumps will be installed on each container and on the container walls. All installed connections will be tested for helium leak tightness (10-8 mbar x liters / s). Turbo pumps (2X) Roughing pumps (6x) Requirements to FNAL: mains, ventilation, heating, technicians for chimneys and flanges installation and sealing, helium, helium leak detectors, safety and support for tests. Manpower: 4 mechanical technicians (2 CERN + 2 FNAL) + 1 supervisor Time: 5 days for installation + 4 days for vacuum pumping and testing CERN, November 17, 2016

Thermal shield top assembly and test The vacuum equipment will be removed and the top part of the thermal shield will be installed together with the output lines and all the circuit be tested again at 10 bars. Thermal shield top Requirements to FNAL: cranes, crane drivers, mains, ventilation, heating, safety for tests. Manpower: Subcontracted (2 mechanics + 1 welder) + 1 supervisor Time: 3 days for installation + 2 days for test CERN, November 17, 2016

WARM vessels ROOF CERN, November 17, 2016

Step 13 – Installation of electrical feedthroghs Warm vessel roof preparation The warm vessel structure will be prepared at the ground level in 12 subcomponents. The thermal insulation will be installed on each subcomponent. Holes for the chimneys Thermal Insulation (glued and supported by rods) St. Steel external skin (welded) St. Steel structure (bolted) Subcomponents Requirements to FNAL: cranes, crane drivers, mains, ventilation, heating, crane. Manpower: 2 mechanical technicians (1 CERN + 1 FNAL) + 1 supervisor Time: 15 days CERN, November 17, 2016

Step 13 – Installation of electrical feedthroghs Warm vessel roof installation The warm vessel roof subcomponents will be put in position, bolted on the lower structure and welded to the lower structure and between them Bolted connections Continuous TIG weld Top warm vessel roof first sub-component Requirements to FNAL: cranes, crane drivers, mains, ventilation, heating, welders, TIG welding tool, fumes detectors. Manpower: 4 mechanical technicians (2 CERN + 2 INFN) + 2 welders (FNAL) + 2 supervisors. Time: 15 days CERN, November 17, 2016

Installation of flexible joints Rubber (neoprene) joints will be attached between the external stainless steel skin and the “chimneys” to ensure tightness of the insulation volume and allow displacement of the chimneys during cool down. The tightness of the rubber joints and of the entire warm structure will be tested. Rubber Joints Requirements to FNAL: mains, ventilation, heating, helium, leak detector, safety for tests. Manpower: 2 mechanical technicians (1 CERN + 1 INFN) + 1 supervisor Time: 3 days CERN, November 17, 2016

on cryostat electronics installation CERN, November 17, 2016

Installation of external joints Two main activities will be carried on, in parallel, from this point on. Installation of the external joints on the chimneys (crosses); installation of argon and nitrogen external piping. External joints (crosses) Requirements to FNAL: mains, ventilation, heating, crane, crane drivers, support of technicians for mech. assemblies Manpower: external contractors for cryogenics + 4 mechanical technicians (2 INFN + 2 FNAL) + 2 supervisors Time: 3 days CERN, November 17, 2016

Step 13 – Installation of electrical feedthroghs Installation of feedthroghs and electronics baskets The electrical feedthroughs for the wires and PMTs readout and Voltage supply will be installed with the baskets to host the R/O electronic boards. The optical feedthroughs for the PMTs calibration will be installed. Start tests on electronics noise, etc.. Partially occupied Requirements: mains, ventilation, heating, crane, crane drivers, support of technicians for mech. assemblies Manpower: 2 mechanical technicians (FNAL) + 2 electronics technicians (INFN) + 1 supervisor Time: 7 days CERN, November 17, 2016

Step 13 – Installation of electrical feedthroghs Installation of PWR and HV supplies and on detector electronics Install all the LV and HV power supplies, the R/O boards both for the wires and for PMTs and connect all the cables and optical fibers. Make connectivity tests of all the electronic chains. Supply and R/O cables +optical fibers Requirements: mains, ventilation, heating. Manpower: 2 electronics technicians (1 FNAL + 1 INFN) 3 physicists (1 CERN + 1 FNAL + 1 INFN) + 2 supervisors Time: 20 days (in parallel with other activities) CERN, November 17, 2016

Warm and cold commissioning of the T600 at Fermilab CERN, December 8, 2016

Proximity cryogenics CERN, December 8, 2016

Step 13 – Installation of electrical feedthroghs Complete the argon circuit Gas and liquid recirculation systems will be installed together with safety valves, manual valves, pressure and vacuum gauges, until the argon circuit is fully installed and sealed. LAr pump LAr Filters GAr Filters Requirements: mains, ventilation, heating, crane. Manpower: External contractor + 1 technician (FNAL) + 2 supervisors Time: 20 days CERN, December 8, 2016

Step 13 – Installation of electrical feedthroghs Pressure leak test (warm-commissioning – 1) The argon volumes are put to a slight overpressure (≈150 mbar). The absolute pressure will be monitored over few days to search for large leaks. LAr pump LAr Filters GAr Filters Requirements: mains, ventilation, heating, oxygen deficiency sensors, argon gas (100 m3). Manpower: 1 technician (FNAL) + 2 supervisors Time: 7 days CERN, December 8, 2016

Step 13 – Installation of electrical feedthroghs Installation of vacuum pumps and gauges Vacuum pumps and gauges will be installed and tested Roughing pumps (5x) Roughing pumps (5x) Turbo pumps (4X) Turbo Pumps (4X) Requirements: mains, ventilation, heating, crane, compressed air. Manpower: 2 mechanical technicians (1 CERN + + FNAL) + 2 supervisors Time: 7 days CERN, December 8, 2016

Step 13 – Installation of electrical feedthroghs Vacuum and Helium leak tests (warm-commissioning-2) Vacuum will be started. Helium leak tests will be done on all external connections of the argon circuit, the purification filters will be opened as a last part of the leak tests. Vacuum pumping will continue until the final commissioning phases. Turbo pumps (4X) Turbo Pumps (4X) Roughing pumps (5x) Requirements: mains, ventilation, heating, compressed air, helium, helium leak detectors, safety for tests. Manpower: 1 technician (20%) + 2 supervisors Time: > 20 days CERN, December 8, 2016

Step 13 – Installation of electrical feedthroghs Complete the Nitrogen circuit All Nitrogen circuit will be installed, including pumps, valves and gauges and controls LAr pump LAr Filters GAr Filters LN2 pump Phase separator Requirements: mains, ventilation, heating, crane. Manpower: external contractor + 2 supervisors Time: 45 days CERN, December 8, 2016

Step 13 – Installation of electrical feedthroghs Connect the external cryogenics The external cryogenics equipment (storage dewars, transfer lines, controls) will be connected to the apparatus. LAr pump LAr Filters GAr Filters LN2 pump Phase separator LAr Storage Pre-Filter LN2 Storage Requirements: mains, ventilation, heating, crane. Manpower: 2 technicians (FNAL) + 2 supervisors Time: 7 days CERN, December 8, 2016

Step 13 – Installation of electrical feedthroghs Pressure test of the Nitrogen circuit Nitrogen circuits will tested according to the design maximum pressure. LAr pump LAr Filters GAr Filters LN2 pump Phase separator Requirements: mains, ventilation, heating, oxygen deficiency sensors, safety for tests, nitrogen gas (100 m3). Manpower: 1 technician (20% - FNAL) + 2 supervisors Time: 7 days CSN2, September 22, 2015 CERN, December 8, 2016 Slide: 23

Final operations before start cold commissioning Hardware for DAQ and for remote apparatus control (cryogenics, slow controls, etc.) will be procured and installed inside an appropriate space (control room). All connections with the Far Detector building will be done and tested. Software for slow control will be installed and tested. CERN, December 8, 2016

COLD Commissioning CERN, December 8, 2016

Cold Commissioning Warm test of all cryogenic components and controls. Slow controls tests and data logging. Tests of network communications and alarms. Final safety inspection and clearance for start of the operations. Check of liquid argon supply. First supply delivered and local storage full. Break the vacuum inside the argon volumes and take the internal pressure to ≈ 0.15 bar relative with purified argon gas. The argon gas input line remains open and the pressure is regulated during the whole cooling process. Start cooling. Cool down to about 200 K (≈ 3 days). Continuously check the temperature gradients on the wire chambers. Stop cooling if needed to lower the temperature gradients. Start GAr recirculation and continue to cool down. Cool down to about 130 K (≈ 3 days). Continuously check the temperature gradients on the wire chambers. Stop cooling if needed to lower the temperature gradients. If needed, stabilize the gradients to ≤ 40 K. Start filling with LAr through the purifiers. CERN, December 8, 2016

Filling Internal temperature will rapidly go to ≈ 90 K. If needed, pressure will be controlled during the first phase of the filling by manually venting trough dedicated valves. Pressure in the LAr storage dewar has to be regulated to < 3 bar to minimize flash evaporation. Continuously fill at a rate of 1 m3 / module / hour. Progressively close the manual venting valves as the pressure and temperatures stabilize. Continuously check the quality of the argon after the filling filter. Stop the filling when the maximum level is reached. Stabilize the cooling circuit and the GAr recirculation circuits until the pressure is steadily around 0.15 bar and the temperature differences at the output of the cooling shield are within 1 K. This will require ≈ 10 days. Monitor the level. Start the drift field. Turn on the PMTs. Turn on the readout electronics. CERN, December 8, 2016