Access system and radiation monitors session (session 5) Topics and subjects discussed Main issues Magali Gruwé and Tomasz Ladzinski 5 th February 2010.

Slides:



Advertisements
Similar presentations
Commissioning the access system M. Gruwé Machine checkout workshop November 8 th 2007.
Advertisements

MEF - Machines & Experimental Facilities Technical Stop #4 29 th August - 2 nd September 2011 Summary Julie Coupard Schedule and Coordination LHC-TS4 -
Injection test? Mike Lamont For initial discussion.
LHC Performance Workshop - Chamonix January 2010 Session 4 - Safety for Personnel Underground - He Evacuation What can the Safety Coordination.
Tomasz Ladzinski GS/ASE. LASS Annual Maintenance & Tests General Principles Each winter shutdown preventive maintenance of EIS takes place. It is followed.
Technical review on UPS power distribution of the LHC Beam Dumping System (LBDS) Anastasia PATSOULI TE-ABT-EC Proposals for LBDS Powering Improvement 1.
GIF++ ACCESS SYSTEM Dorothea Pfeiffer GIF++ Project Meeting Thanks to: V. Martins De Sousa Dos Rios, D. Vaxelaire, D. Haasler.
LHC machine Schedule, coordination & WAT K. Foraz March 22 nd, 2011 IMWG - LHC machine1.
Example STP runs on bridges and switches that are 802.1D-compliant. There are different flavors of STP, but 802.1D is the most popular and widely implemented.
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
LHC ACCESS SYSTEM 1Authors: P, Ninin, S. Grau & LHC access team EDMS: Access System during the LHC Injection tests P. Ninin, S. Grau - TS/CSE Workshop.
How to achieve satisfactory performance of the access system: stability, efficiency, operation, fluidity Timo Hakulinen (GS/ASE) Thanks: LHC access team.
Operational tools Laurette Ponce BE-OP 1. 2 Powering tests and Safety 23 July 2009  After the 19 th September, a re-enforcement of access control during.
Beam Interlock System PR b-CTM, October 7th, 2010 Cesar Torcato de Matos.
LHC Access System August 2006 LHC Access System – Status and Planning August 2006 Elena Manola-Poggioli Eva Sanchez-Corral TS-CSE on behalf of the LHC.
1 User’s perspectives on the management of Elements Important for Safety (EIS) AMMW - CERN Anne Funken, Marc Tavlet / BE-ASR-SU.
TS Workshop, Archamps, May 24 – May 26, 2005 The LHC Access System Status report – May 2005 P. Ninin & the Access project team TS/CSE.
LHC ACCESS SYSTEM 1 Authors: P. Ninin, L. Scibile, T. LadzinskiEDMS: Access Control and Safety System for the LHC Experiments P. Ninin L. Scibile.
2 IMPACT - THE FIRE PERMIT = Hot Work Permit 3 Welcome ! This course is linked to the use of IMPACT, so it is assumed that: You know how to use IMPACT.
Access system M. Gruwé (AB/OP) Thanks to TS/ASE group Extended LTC meeting March 3 rd 2008.
Network design Topic 6 Testing and documentation.
For more info:
Review of Safety Systems for the LHC Experiments & Experimental Areas Emmanuel Tsesmelis / TS-LEA LEMIC 20 March 2007.
NERC Lessons Learned Summary LLs Published in September 2015.
Access System – LASS/LACS L. Ponce On behalf of the OP team.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
LHC ACCESS SYSTEM 1 EDMS: January 2008 Global Tests of the LHC Access system Outcome P. Ninin, T. Petterson, S Grau, T. Ladzinski 18 th January.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
Access system global tests M. Gruwé LHCCWG January 15 th 2007.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
CERN Jan 2006 Specific safety Issues for 2006 compared to 2004 P. Cennini AB Safety Requirement in case the Installation activities are going on.
Training LHC Powering - Markus Zerlauth Powering Interlocks Markus Zerlauth AB/CO/MI.
LHC machine protection close-out 1 Close-out. LHC machine protection close-out 2 Introduction The problem is obvious: –Magnetic field increase only a.
Controls, Safety and Engineering Databases 18 Jan 2006PS & SPS Days Access Safety Systems Modifications & tests in 2006 Presented by Rui Nunes TS-CSE-AAS.
Access system LHC-SPS M. Gruwé and J. Ridewood OP days March 18 th 2008.
Mar 26, 2014 FGClite Power Control TE-EPC-CCE.
Reliability and Performance of the SNS Machine Protection System Doug Curry 2013.
LHC intervention scheduling with the Work Acceptance Tool
(Access system for HWC)
LBDS TSU & AS-I failure report (Sept. 2016)
Computer Network Collection of computers and devices connected by communications channels that facilitates communications among users and allows users.
CENF – Personnel Protection System Preliminary Study
Internal review of IR2 LEP cryostats (WP11/WP5) Close out session
CENF – Personnel Protection System Preliminary Study
Evolution and future of the Access safety and control systems
Packet Switching Datagram Approach Virtual Circuit Approach
RF interlocks for higher intensities (LMC 15 June)
Helium spill in LHC tunnel
LAAWG Status Report – 15th May 2007
The LHC - Status Is COLD Is almost fully commissioned
Computing infrastructure for accelerator controls and security-related aspects BE/CO Day – 22.June.2010 The first part of this talk gives an overview of.
LV Safe Powering from UPS to Clients
Quality Assurance applied to Accelerator Safety
1v0.
the CERN Electrical network protection system
Commissioning and Testing the LHC Beam Interlock System
Storage Virtualization
Collimator Control (SEUs & R2E Outlook)
Remote setting of LHC BLM thresholds?
Interlocking of CNGS (and other high intensity beams) at the SPS
Workshop on Accelerator Operations
Assumption for a given sector
1v1.
TS2 PSS Architecture, Concepts of Operations and Interfaces
Lecture 18: Coherence and Synchronization
TS2 PSS; update on concepts of operation and system's architecture
Operation of Target Safety System (TSS)
Powering and Safety day Underground access during powering tests
Close-out.
Presentation transcript:

Access system and radiation monitors session (session 5) Topics and subjects discussed Main issues Magali Gruwé and Tomasz Ladzinski 5 th February

2 Magali Gruwé and Tomasz Ladzinski  Laurette Ponce (BE/OP): “How did the LHC access system perform in 2009?” “How did the LHC access system perform in 2009?”  Julie Coupard (EN/MEF): “How should the access system be operated while LHC is not in beam operation?” “How should the access system be operated while LHC is not in beam operation?”  Marc Tavlet (BE DSO to be): “Is there a need for re-sectorization and/or additional interlocks?” “Is there a need for re-sectorization and/or additional interlocks?”  Rui Nunes (GS/ASE): “Impact of safety related requirements and evolutions on LASS and LACS” “Impact of safety related requirements and evolutions on LASS and LACS”  Timo Hakulinen (GS/ASE): “How to achieve satisfactory performances of the access system: stability, efficiency, operation, fluidity?” “How to achieve satisfactory performances of the access system: stability, efficiency, operation, fluidity?”  Doris Forkel-Wirth (DGS/RP): “Arcon/Ramses: current status and operational risks” “Arcon/Ramses: current status and operational risks” Program 2 What went wrong with the access system and procedures? What would we wish to change? What are the current issues? How can/will these issues be addressed? What are the consequences for the access system? What else may have an (indirect) impact on availability of LHC? Radiation monitors

3 5 th February 2010 Magali Gruwé and Tomasz Ladzinski  Organizational issues  Sectorization: Justification and implications  Access system performance  How to improve access fluidity  MAD  Radiation monitors Layout 3

4 5 th February 2010 Magali Gruwé and Tomasz Ladzinski Access organization: responsibilities 4 Planning and coordination Safety coordination J. Coupard

5 5 th February 2010 Magali Gruwé and Tomasz Ladzinski  Introduction of the AET (Avis d’Exécution de Travaux): To be put in place before next shutdown To be put in place before next shutdown A streamlined ADI + AOC + … A streamlined ADI + AOC + … One single document including links to VIC, DIMR, locking of equipment, hot work permit, etc… (as needed) One single document including links to VIC, DIMR, locking of equipment, hot work permit, etc… (as needed) Including specific list of people who will intervene, BUT: list that could be edited even after approval of the document Including specific list of people who will intervene, BUT: list that could be edited even after approval of the document Access organization: AET 5 J. Coupard

6 5 th February 2010 Magali Gruwé and Tomasz Ladzinski  BE/OP to give access… Do we need more people qualified/habilitated to give access while not in Operation? Do we need more people qualified/habilitated to give access while not in Operation? Operation of the access system 6 J. Coupard

7 5 th February 2010 Magali Gruwé and Tomasz Ladzinski  Current sectorization fulfills the safety functions for which it has been designed: protect people from ionizing radiation  But: No opening of the inter-site doors when in RESTRICTED access mode No opening of the inter-site doors when in RESTRICTED access mode Heavy constraints for people who need to intervene on siteHeavy constraints for people who need to intervene on site Access sectorization as we know it: Access sectorization as we know it: Does not match the newly discovered needs of hardware commissioning: strong access restrictions during powering Phase IIDoes not match the newly discovered needs of hardware commissioning: strong access restrictions during powering Phase II Access system now also used to protect personnel from the risk of major Helium release without having been redesigned Access system now also used to protect personnel from the risk of major Helium release without having been redesigned Need to re-adjust ventilation sectorization to access sectorizationNeed to re-adjust ventilation sectorization to access sectorization Should it include other interlocks?Should it include other interlocks? Current sectorization: Implications 7 M. Tavlet

8 5 th February 2010 Magali Gruwé and Tomasz Ladzinski  During shutdown and hardware commissioning phase circulation through inter-site doors is an issue:  Solution? Go to general mode? Go to general mode? BUT: BUT: Loose patrol: issue for the localization of peopleLoose patrol: issue for the localization of people Some areas will soon remain in restricted or closed mode (for radiation reasons)Some areas will soon remain in restricted or closed mode (for radiation reasons) Circulation through inter-site doors 8 M. Tavlet and J. Coupard

9 5 th February 2010 Magali Gruwé and Tomasz Ladzinski  Example:  How to address the issue? Add more access points? Any useful/desirable?Add more access points? Any useful/desirable? Long term need?Long term need? Satisfactory for safety? Risk analysis required!Satisfactory for safety? Risk analysis required! Access restrictions in powering Phase II 9 Access to CMS subject to conditions SD4: Conditions for working at height SD6: Conditions for working at height UX45: Solution for access being investigated M. Tavlet

10 5 th February 2010 Magali Gruwé and Tomasz Ladzinski  Need to re-adjust ventilation sectorization to access sectorization Access versus ventilation sectorization Access Point (PAD/MAD) 4. Consequence = Not possible to access US-UA before long air-decay time 2. Cable passages not air tight 3. New “overpressure” door Make cable passages air-tight Add ventilation door next to access point R. Nunes and M. Tavlet

11 5 th February 2010 Magali Gruwé and Tomasz Ladzinski  Should the LASS have a new role, i.e. protect people from other risks than radiation? Interlock cold magnets power converters with LASS? Interlock cold magnets power converters with LASS? Currently software interlock (Laurette’s interlock)Currently software interlock (Laurette’s interlock) Interlocks (I) 11 L. Ponce and M. Tavlet

12 5 th February 2010 Magali Gruwé and Tomasz Ladzinski  Principle: In addition to the existing procedure In addition to the existing procedure Prevents powering above the Phase I current limit when people are in the zone Prevents powering above the Phase I current limit when people are in the zone Stops the Power Converters of the relevant area when people enter a zone Stops the Power Converters of the relevant area when people enter a zone  Implementation: Uses the Software Interlock System Uses the Software Interlock System To generate the logic (between the access conditions and the current read in the Power Converters)To generate the logic (between the access conditions and the current read in the Power Converters) And to send commands to the power converters via the PICAnd to send commands to the power converters via the PIC Action: in case conditions are not met: Action: in case conditions are not met: A global REMOVE Power Converter permit of the relevant sector is sent… causing a Slow Power AbortA global REMOVE Power Converter permit of the relevant sector is sent… causing a Slow Power Abort  Issue: Long chain of different software modules to connect the signals  Question: Move towards a HW link between the LASS signals and the Power Interlock Controller for a long term solution? LASS-Power Converters Interlock 12 L. Ponce

13 5 th February 2010 Magali Gruwé and Tomasz Ladzinski  Should the LASS have a new role, i.e. protect people from other risks than radiation? Interlock cold magnets power converters with LASS? Interlock cold magnets power converters with LASS? Currently software interlock (Laurette’s interlock)Currently software interlock (Laurette’s interlock) Needs further investigationNeeds further investigation Is there a real need for this interlock (in the long term?) Is there a real need for this interlock (in the long term?) Needs risk analysisNeeds risk analysis New interlock for fresh air supply? New interlock for fresh air supply? Interlock ventilation doors (new over pressure doors) with LASS? Interlock ventilation doors (new over pressure doors) with LASS? Interlocks (II) 13 R. Nunes and M. Tavlet

14 5 th February 2010 Magali Gruwé and Tomasz Ladzinski  LACS: Electro-mechanical problems on MAD, PAD, doors: Electro-mechanical problems on MAD, PAD, doors: Impact in 2009:Impact in 2009: Mainly a problem during HWC period, after a long shutdown Mainly a problem during HWC period, after a long shutdown Most problems solvedMost problems solved Key distributors: Key distributors: Impact in 2009:Impact in 2009: Blocking possibility to switch back from access mode to beam mode Blocking possibility to switch back from access mode to beam mode Currently: much improved situation but still some mechanical problemsCurrently: much improved situation but still some mechanical problems Simultaneous opening of both PAD doors: patrol drop Simultaneous opening of both PAD doors: patrol drop New software implemented just on time for beam operationNew software implemented just on time for beam operation But still occasional patrol dropsBut still occasional patrol drops  LASS: Only few changes since 2008, validated by the successful DSO tests Only few changes since 2008, validated by the successful DSO tests Connection with EIS-beam to be revisited to allow testing flexibility Connection with EIS-beam to be revisited to allow testing flexibility Access system performance 14 L. Ponce

15 5 th February 2010 Magali Gruwé and Tomasz Ladzinski  August 1 st, 2009 till January 23 rd, 2010: Total accesses: (average 1033 / day) Total accesses: (average 1033 / day) Accesses in Restricted access mode: (average 191 / day) Accesses in Restricted access mode: (average 191 / day)  Busiest day for operators: January 14 th, 2010: Accesses in Restricted access mode: 670 keys taken Accesses in Restricted access mode: 670 keys taken Access system performance: Statistics (I) 15 T. Hakulinen

16 5 th February 2010 Magali Gruwé and Tomasz Ladzinski  User waiting times from call to operators to access: Subjective estimates based on experienceSubjective estimates based on experience Still needs a proper distribution for analysisStill needs a proper distribution for analysis Best case: < 1 min (no rush, ADI ok, system ok) Best case: < 1 min (no rush, ADI ok, system ok) Normal: 1 – 5 min (normal operator load) Normal: 1 – 5 min (normal operator load) Worst case: 30 min – ∞ (big rush, multiple access points at the same time, technical problems) Worst case: 30 min – ∞ (big rush, multiple access points at the same time, technical problems) Normal procedure: Normal procedure: 1: user calls and gives ADI – 2: operator checks ADI in EDH – 3: operator gives key to user – 4: user enters zone1: user calls and gives ADI – 2: operator checks ADI in EDH – 3: operator gives key to user – 4: user enters zone Repeat until all users passedRepeat until all users passed Experienced operator performance: ~1 min / call Experienced operator performance: ~1 min / call Access system performances: Statistics (II) 16 T. Hakulinen

17 5 th February 2010 Magali Gruwé and Tomasz Ladzinski  Technical improvements and bug fixes: Correction of persistent software bugs and new ergonomics of the console windows Correction of persistent software bugs and new ergonomics of the console windows Solving network problems (IT issue) Solving network problems (IT issue) Biometry on badge (to avoid dependence on network) Biometry on badge (to avoid dependence on network)  Change of RESTRICTED access procedure: Allowing multiple key distribution for a group entering together, i.e. separating the safety token delivery from the PAD entrance cycle. Allowing multiple key distribution for a group entering together, i.e. separating the safety token delivery from the PAD entrance cycle.  Organization and technical change: Additional filter (valid AET) applied on the access requests: Additional filter (valid AET) applied on the access requests: Access request not treated if no valid AETAccess request not treated if no valid AET How to improve access fluidity? 17 T. Hakulinen

18 5 th February 2010 Magali Gruwé and Tomasz Ladzinski  Detection of personnel in Material Access Devices: Ongoing issue since 2008 Ongoing issue since 2008 Improvements in place. BUT: Improvements in place. BUT:  Sensitivity versus rate of false detections is an issue  At the limit of what is possible with the approach taken. Pending actions: Making the personnel detection process fail-safe Making the personnel detection process fail-safe Fine-tuning (but is it really possible any further?) and acceptance Fine-tuning (but is it really possible any further?) and acceptance Technological redundancy… Technological redundancy…  Change strategy? Remote human video control on demand / compensatory measures (guards on sites) Remote human video control on demand / compensatory measures (guards on sites) Explore different areas of technology (redundant system) Explore different areas of technology (redundant system) MAD 18 L. Ponce and R. Nunes

19 5 th February 2010 Magali Gruwé and Tomasz Ladzinski  RAMSES system for LHC: proven reliable Decentralized system and autonomous (internal battery) Decentralized system and autonomous (internal battery) Detector-alarm units operate autonomously: continues to operate even if the rest of RAMSES failsDetector-alarm units operate autonomously: continues to operate even if the rest of RAMSES fails Areas well covered with monitor stations Areas well covered with monitor stations In case of failure: single channel fails: radiation monitoring ensured by remaining channelsIn case of failure: single channel fails: radiation monitoring ensured by remaining channels  ARCON system for LHC injectors: In case of failure: several channels fail: whole area without radiation monitoring! In case of failure: several channels fail: whole area without radiation monitoring! Major issue: spares missing! Major issue: spares missing! Operational risk: faulty ARCON equipment: beam stop for 1-3 days Operational risk: faulty ARCON equipment: beam stop for 1-3 days To be phased out and replaced by RAMSES: To be phased out and replaced by RAMSES: First phase (RAMSES-light, for the LHC injectors) before end of next shutdownFirst phase (RAMSES-light, for the LHC injectors) before end of next shutdown Radiation monitors 19 D. Forkel-Wirth

20 5 th February 2010 Magali Gruwé and Tomasz Ladzinski No problem* with personnel safety but issues with availability of the LHC  LACS: Ongoing issues Ongoing issues Improvements expected (for fluidity) Improvements expected (for fluidity)  Safety issues: *Ongoing (never ending?) MAD issue *Ongoing (never ending?) MAD issue Working group to be started to address: Working group to be started to address: Possible new sectorization (needs and risk analysis)Possible new sectorization (needs and risk analysis) Possible additional interlocks (needs and risk analysis)Possible additional interlocks (needs and risk analysis)  Operational risks: ARCON to be phased out ARCON to be phased out Conclusions (summary of summary) 20