EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/14.

Slides:



Advertisements
Similar presentations
Engineering Department EN Cooling and Ventilation issues 1 FUTURE EXPLOITATION OF THE EAST AREA EN-CV Michel OBRECHT.
Advertisements

MARINE HVAC SYSTEMS MAR-IX IS A PRODUCT OF MAVÉ B.V. THE NETHERLANDS
The students: Mohammad Shabaro ( ) Mahmoud Mousa ( ) Yosri Asfour ( ) Supervisor: Dr. Iyad Assaf 1.
CURRENT STATUS OF CV INSTALLATIONS, WORKS DURING LS1 AND PROBLEMS ENCOUNTERED DURING START-UP NORTH AREA Bill Bannister / Jani Lehtinen EATM – 7 th October.
Paolo Guglielmini TS / CV / DC08th April 2005 BIDDERS’ CONFERENCE Invitation to Tender 3307 Supply and Installation of water cooling equipment for the.
Point 5 - Cooling Network - Key Primary Water Chilled Water Mixed Water Eau Bruite Standard Power Diesel Backup Comp Air Primary Water at 20-25C – Produced.
EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06.
ISOLDE: Status report building th ISCC meeting CERN, 31 March 2014 Erwin Siesling, Magda Kowalska.
Bulding 245 schedule update LIU Booster Meeting Fulvio Boattini & Michel Obrecht TE-EPC / EN-CV TEEPC.
VENTILATION PRINCIPLE FOR THE DRIVE BEAM TUNNEL M Nonis – EN/CV – 28/7/2009 Already presented by C. Martel/ J Inigo Golfin on15 th October 2008 CLIC WORKSHOP.
Claudio Bortolin. 1 st June: PT100 electrical connection failure (Temp Chiller water In&Out) 1) it required an access to the cavern to be fixed 2) access.
N-TOF review HVAC and cooling systems YB-JIG 15/06/07.
D. Gasser ST/CV 1 Fluid distribution from UW85 Fully available now.
Cooling of NA62 vacuum system November 11 th, 2014 E. Harrouch, EN-MEF, on behalf of the NA62 Vacuum Team.
Budget specification EHN1 Extension: Infrastructure (WG2) Mats Wilhelmsson 17 September 2015.
SM18 INFRASTRUCTURE Crab Cavity CryoModule – Conceptual Design Meeting
2 IMPACT - THE FIRE PERMIT = Hot Work Permit 3 Welcome ! This course is linked to the use of IMPACT, so it is assumed that: You know how to use IMPACT.
EHN1 North Wall Dismantling Schedule Bastien Rae.
CENF – Civil Engineering Extension B887 Status – 02 October 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed.
COOLING & VENTILATION FOR THE DRIVE BEAM TUNNEL M Nonis – EN/CV – 16/9/2009 CLIC TWO BEAM MODULES REVIEW
Computing Facilities CERN IT Department CH-1211 Geneva 23 Switzerland t CF CERN Computer Centre Consolidation Project Vincent Doré IT Technical.
The Building 180 Cryogenic infrastructure water cooling system Stefano Moccia, EN-CV Coordination meeting 26/09/14.
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
Functional/Budget specification EHN1 Extension: Infrastructure (WG2) Mats Wilhelmsson EN/MEF 4 November 2015.
CMS consolidation activities of detector cooling system Detector cooling project P. Tropea.
Restarting Cooling, Ventilation for PS and SPS. PS /SPS days 2006.
Building 180 NORMATEF TEST FACILITY Demineralized cooling water station upgrade R. Bozzi / EN-CV.
IT-4014/EN/NA62 Technical Specification Dismantling, Design, Supply and Installation of a Ventilation and Air Conditioning System for ECN3, TCC8 and GHN300.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/21.
EHN1 – EN/EL Progress update J. Devine G. Gross 11/02/16.
EHN1 – EN/EL Planning Lighting _ Containment_ Cabling J. Devine G. Gross 11/02/16.
Each converter 3 racks (fighting for 2?) Access from front and rear of each rack! 56 racks total + 6 racks Ethernet/control Existing RF equipment to be.
COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.
Technical Review EHN1 Extension Cooling Systems and Pipework Jérôme Rodary / EN-CV.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
A. Perin, TE/CRG, Page 2 CERN-GSI FAIR Project integration/coordination meeting 5 14 th October 2015 A. Perin, H. Derking, L. Stewart, M. Chesi,
R2E Report – P5 Safe-Room Update 20 th LSC Meeting, September 13 th 2013 CERN Radiation 2 Electronics (R2E) Project 20 th LSC Meeting September 13 th 2013.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/02/04.
S A Griffiths CM42 June 2015 Electrical & Control.
Update on the PSB Cooling and Ventilation Systems
Demineralised water cooling system
EN-CV activities for LHC during LS2
SR1 extension follow up 27-Mar-17 Marco Ciapetti.
EHN1 Cryogenics Integration
Neutrino Platform Proximity Cryogenics 62th EHN1 Cryogenics Integration Redouan Abdennour, Johan Bremer, Michel Chalifour, Joaquim Creus, Aurelien Diaz,
Design of the thermosiphon Test Facilities 2nd Thermosiphon Workshop
ARAC/H/F Air-cooled water chillers, free-cooling chillers and heat pumps Range: kW.
CBETA Technical Review
IT-4189 Supply and installation of a cryogenic distribution system
1.3-GHz Cavity Vacuum Furnace at IB4
EHN1 Extension North Side wall (Removal of Existing services & platforms) Michael Jeckel & Bastien Rae.
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
Budget specification EHN1 Extension: Infrastructure (WG2)
SPS cryogenic proximity equipment and SM18 validation
EN-CV Progress EHN1 Extension Project
David Montanari / Johan Bremer Jun 11, 2015 Rev. 1
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS EN-CV Planning LS (initial draft)
HVAC SYSTEM DESIGN ALMAQASED HOSPITAL
CV maintenance works during YETS
Cooling systems for HL-LHC (WP17.3)
CEDAR Detector Ventilation System Review
COOLING & VENTILATION INFRASTRUCTURE
Status of the cryogenic system for B180
EN-CV: P8 systems and Detector Cooling
TEST PLANS for HL LHC IT STRING
Maintenance at ALBA facility: Strategy for the conventional services
Aziz AMAMOU EACM – 21th May 2019
Presentation transcript:

EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/14

Contents 1. Works for cold boxes 2. North wall dismantling 3. Integration status 4. Future design activities

1. Works in progress Cold boxes works All CB are still stopped: switch from drinking water to raw water to be performed TE-CRG is performing some works on CB during YETS  Dates to be scheduled between TE-CRG & EN-CV: TE-CRG will confirm intervention dates to EN-CV (no critical regarding NW dismantling !)

2. North wall dismantling Works completed : (already discussed) firefighting network interception chilled water disconnected barrack HNA 910 mixed water station removed (north wall) old fan coil removed from barrack HNA 494 raw water network interception (several places) Dismantling status updated (13 January 2016) : Completed Scheduled Not possible : access issue Completed Technical visit done with contractor – Works scheduled for week 3 Completed

3. Integration status GAr extraction system & hall ventilation : ~ 90 % Piping networks & cooling systems : ~ 80 % Some integration issues to be discussed : See slides in appendix

4. Future design activities Preliminary design data for EN-EL ( given by EN-CV the 19 October 2015 )

4. Future design activities Chilled Water (CW): Extension of the network in the future galleries Hypothesis for the design - confirmed by EN-MEF on 05 November 2015 : Additional flowrate: ~ 18 m3/h (for n.8 barracks fan coils) Additional cooling power (for n.8 barracks 6.3 kW fan coils): ~ 50 kW Other : NO CW network extension proposal inside EHN1 extension area

4. Future design activities Raw Water (RW): Extension of the network in the future galleries – confirmed on 17 December 2015 Hypothesis for the design – not confirmed (urgent !) : Additional flowrate (for n. 40 ? racks) : ? m3/h (to be confirmed) Additional cooling power (for racks) : ? kW (to be confirmed) Additional cooling power for (n. 3 ?) cold boxes : NO (confirmed by Johan Bremer on 03 November 2015) Water cooling requirements for racks to be given: Racks locations (barrack ?) Thermal load Inlet temperature, ∆T Max allowable pressure ∆P Nominal diameters of connection Any relevant information,…

4. Future design activities Compressed Air (CA): Extension of the network in the future technical gallerie Hypothesis for the design – given by Johan Bremer on 03 November 2015 : ‘Cryo’ users (for cryostats valves & instrumentation) : 10 9 bar Additional users (for tools,…) : NO

4. Future design activities Demineralized Water (DW): Extension of the network in the future technical gallerie Hypothesis for the design - given by Philip Schwarz on 02 November 2015: Additional flowrate (for new magnets) : 64 m3/h - to be updated by Philip & Ilias Additional cooling power (for new magnets) : kW - to be updated by Philip & Ilias Additional cooling power (for power converters) : 0 kW Other : NO Currently : DW network pumping capacity is not sufficient to ensure these requirements !

4. Future design activities Domestic Water (DoW): No extension will be performed in the extension area (confirmed on 15 October 2015) Note : Only DoW piping removal will be done to free the EHN1 north wall. CV will take care to not leave ‘dead branches’ once the works realized. Fire Fighting (FF): Extension of the network in the future area Hypothesis for the design : According the ‘EHN1 extension safety meeting’ held on 09 October 2015 (see MoM) Number of RIAs to be installed: n.6

4. Future design activities Heated water for 2 new AHUs: Hypothesis for the design : Existing hot water substation will be re-used Hot water piping network will be extended

4. Future design activities User Requirements missing  some data have been collected but not all ! EN-CV needs technical data & requirements for designing the future extended networks as listed below  UR shall be confirmed as soon as possible for pre sizing all fluid networks and checking pumping capacities ! chilled water (for HVAC purposes) chilled water (for cooling down other some equipments) compressed air raw water ! demineralized water ! fire fighting system gas extraction (other gases except GAr ?) REMINDER: Deadline to collect all the User Requirements was : 12 November 2015 !

Thank you for your attention