1 EN-CV activities for LHC during LS2

2 Maintenance

3 Impact of the maintenance on the CV services
2019 2 months(*) 2020 3 weeks (*) 2019 1 month 2020 3 weeks 2019 1 month 2020 3 weeks 2019 1 week 2020 1 day (*) except for the cryo if needed

4 Maintenance Mechanical and/or chemical cleaning of heat exchangers
Safety requirements (vessels,..) Mechanical revision of valves, pumps, ..replacement of piping component (flexible sleeves) Maintenance of busbar for power cubicles. Instrumentation calibrations Bugs fixing and functionnal tests.

5 Projects and consolidation

6 Chilled water production consolidation at SU4 and SU6
What Removal of existing chillers and installation of new ones, modification of the piping network Handling of the chillers New slabs New power supplies When SU4 : January-March 2019 SU6 : October-Novembre 2019 Impact on process No chilled water available

7 New HVAC system for SR1 What Removal of the exisitng AHUs
Installation of the new ones New power supplies Handling of AHUs Co-activities during the dismantling and installation phase in the surrounding area When Decembre 2019-March 2020 Impact on process No HVAC (installation of a provisionnal heating system) No smoke extraction Possible compensatory measures (based on past experience) Avoid unecessary storage of flammable material Notify the firebrigade Install a mobile CO2 fire extinguisher (optional)

8 Projects and consolidation
New control system for SPS loop (bldg. 863) providing water to cryo point 18 (4 weeks); SIG pumping stations (WSNET, WSSPS and WSLHC): replacement of control system; New control system for for SEQ cooling plants (2 months); HL LHC: Installation of 4 airlocks ventilation in Pt 1 and 5- Planning TBD with HL works; Modificiation in point 4 – TBC; New control system for ATLAS and CMS ventilation system. For CMS 2019 Q1 and Q2, for ATLAS 2019 Q2 and Q3; Migration of control for USC55 cooling system; New cooling tower in point 18. Stop for 3 months; CMS increase of cooling capacity. Stops to be foreseen; LHCb and ALICE: installation of containers for data acquisition. Stops to be foreseen on demineralised water supply circuit.