LHC experience with installation Katy Foraz March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop ***********************************

Slides:



Advertisements
Similar presentations
M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
Advertisements

LHC HARDWARE COMMISSIONING REVIEW May 2005 CRYOGENIC VACUUM SYSTEM Paul Cruikshank for AT/VAC.
A. Perin, CERN, TE-CRG, 26 May Review of the cryogenic by-pass for the LHC DS collimators 26 May 2011 Modifications to the DFBs, DSLC and cryogenic.
Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005.
For more information, please contact 19/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
LHC HARDWARE COMMISSIONING SAFETY TRAINING DAY S. Claudet (AT-ACR-OP) With great help from G. Lindell (Safety commission) CRYOGENICS.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
CRYOGENICS AND POWERING
Acknowledgments: O.Aberle – F.Bertinelli – J.C.Billy - O.Capatina - J.Casas - L.Ceccone - S.Claudet J.Coupard - K.Dahlerup - R.Denz - K.Foraz - J.J.Gras.
Session th January 2010 R.Schmidt TE/MPE Hardware Commissioning 2010 and beyond R.Schmidt.
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
LHC Access System August 2006 LHC Access System – Status and Planning August 2006 Elena Manola-Poggioli Eva Sanchez-Corral TS-CSE on behalf of the LHC.
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
LHC scheduling applied to CLIC and ILC TILC09 & GDE AAP review – Tsukuba April 2009 K. Foraz K. Foraz - CERN TILC09 & GDE AAP review – Tsukuba April 2009.
Global Design Effort - CFS TILC09 and GDE AAP Review Meeting - Tsukuba, Japan 1 GDE ACCELERATOR ADVISORY PANEL REVIEW CONVENTIONAL FACILITIES.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
June 1 rst, Consolidation for E-cloud and High Voltage cards N.Vauthier TE-CRG LS1 projects review:
HC Review, May 2005 Hardware Commissioning Review Hardware Commissioning Review Quality Assurance and Documentation of Results Félix Rodríguez Mateos,
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
MTF – Manufacturing and Test Folder Large Scale Deployment of MTF Sonia Mallón Amérigo Elena Manola-Poggioli on behalf of the EDMS Team, TS-CSE.
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
ILC D RAFT P ROJECT S CHEDULE K LYCLUSTER 500GeV K Foraz & M Gastal ILC Mechanical & Electrical Review and CFS Baseline Technical Review Many thanks to.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
Quality Assurance Overview Ranko Ostojic 12 Nov 2012.
Training LHC Powering - Markus Zerlauth Powering Interlocks Markus Zerlauth AB/CO/MI.
TE-CRG Activities D. Delikaris, TE-CRG.
Roberto Saban TS HC Review bis Outline  Interviews of all the Group Leaders loosely or tightly concerned by hardware commissioning proposing them.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
LMC 1 (Pre Chamonix) DN200 relief valve position DN200 relief valve position On top wherever possible. Open W bellows for MLI protection. On top wherever.
LHC machine integration experience PicoSEC-MCNet System Integration Training 26 th May Julie Coupard.
COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.
February 4 th, Quality assurance plan: production, installation and commissioning N.Vauthier TE-CRG Technical Review on Beam Screen Heater Electronics.
The Large Hadron Collider The 19 th Sep 2008 incident [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] NIKHEF Seminar ( )
Training LHC Powering – Blanca Perea Solano From Individual System Tests to Powering to Nominal Blanca Perea on behalf of Hardware Commissioning Coordination.
Overall planning, consolidation, stops, time line K. Foraz MAC – April 27th 2010 April 27th 20101K. Foraz - Machine Advisory Committee.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
Lessons learnt from CERN experience
CERN Construction Planning and Scheduling (LHC installation)
Status, Schedule and EVM for the test facility project
Installation Global System
IT-4189 Supply and installation of a cryogenic distribution system
Equipment simplified model SMR UR safety
Minimum Hardware Commissioning – Disclaimer
Internal review of IR2 LEP cryostats (WP11/WP5) Close out session
Installation of an Instrument on a CERN machine
CLIC / ILC Collaboration for CFS works
Configuration Management and Layout Database ELENA Project
The LHC - Status Is COLD Is almost fully commissioned
Coordination of Hardware Commissioning
Consequences of warming-up a sector above 80 K
Hollow e- lens, Cryogenic aspects
Accelerator and Experiment Interface Session: LS2, LS3
Renovation of the 45-year old PS magnets
Powering from short circuit tests up to nominal
Status of the BLHC ….work in progress! Mike Lamont CERN/AB 18/01/2008
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
LHC installation status
Commissioning of the LHC superconducting magnets systems: Why an LHC Hardware Commissioning? Specificity and complexity of this machine Roberto Saban.
UPPSALA UNIVERSITY_GERSEMI PROJECT
Review of hardware commissioning
Cryogenic upgrade of B163, B165 & B253 Status Meeting 19th December 2018
Presentation transcript:

LHC experience with installation Katy Foraz March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop *********************************** QAP History Lessons learned

K. Foraz Quality Assurance Plan Based on ISO 9000 (documents distributed to all project engineers, contains all the code definitions, procedures) - EDMS Engineering Specifications: functional and interface specifications and design files Engineering Change Request Engineering Drawings Technical Description for Market Survey Technical Specifications Manufacturing tool management  to follow the prod. & inst. activities: – Components traceability, – follow-up of non conformity – Step sequence of a process. QAP March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop

K. Foraz Unique Reference database : QAP March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop

K. Foraz 5 main phases – Civil engineering – General services – Cryogenics – Machine – Hardware commissioning March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop History

K. Foraz Civil engineering phase Scope Surface buildings Underground: – 2 injection tunnels ~5km – 2 beam dump tunnels – 2 new experimental areas – Other tunnel modifications: RR.. 240’000 cubic meters 4 main contracts March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop TI2TI2 DUMPDUMP CMSCMS ATLASATLAS

K. Foraz Civil engineering phase Main problems encountered From CE side – Modification of scope while contracts were signed  New buildings  Modification of design – Introduction of 35h law in France  Impact on contractors planning and resourcing… – Discussions with contractors  Target cost mechanism – Some geological problems : PM54, Water leaks in UD68 and sector 34 From coordination side – Lots of dust – Endless ends March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop

K. Foraz General services Phase Electrical general services and cabling More than 4’500km of cables 2 Industrial Services Contracts – Benefit: Fast intervention possible – Disadvantage: limited resources Main problems encountered: – For EL At the beginning: integration not fully done Late request from users Availability of cables (other contracts…), and others – From coordination side Lots of delay …. Endless ends March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop

K. Foraz General services Phase Optical fibers – Skilled contractor and very good contract follow-up – Easy coordination – Could we have replace some of the control cables by optical fibers ? Water cooled cables – Supply contract – Hard time for planning – Technical problems….. “Fire brigade” March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop

K. Foraz General services Phase Cooling and ventilation Scope: – Piping: more than 160 km of pipes, ~ 8km of flexible – Cooling and ventilation Lots of work in surface buildings and experimental areas New Cooling and ventilation systems in alcoves (UA, RR), modification in surface (upgrade, controls…) Main problems: – Technical or and commercial March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop

K. Foraz Cryogenic phase Cryo Islands – Upgrade or new installation  « stand-alone » Works Cryogenic Line installation – Started in June 03 – After few months: Serious technical and quality problems – Worksites stopped in July 04, CERN repaired and re-installed all the faulty elements already at CERN – Started again in November 04 – Finished in December 06 March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop

K. Foraz Cryogenic phase Impacts induced by QRL delays – Technical: Skip systematical cold tests on each sector – Logistics: Cryo-magnets storage Cryo-magnets transport in parallel with QRL installation and interconnections works – Organizational Change of the sector sequence Squeeze time dedicated to the machine phase -> change the scope of contracts which were already signed (human and material resources to be added) Squeeze the hardware commissioning phase by almost a factor 2 -> find resources to parallelize March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop

K. Foraz Machine phase Cryo-magnets transport Most of cryo-magnets transported through a unique shaft: PMI2 (+PX65 & PX24) More than 1’700 magnets transported Main problems encountered: – Cross working sites in a narrow areas – Some breakdown at the very beginning teething problems – Delays in magnet’s deliveries: most of the time, no margin between surface readiness and transport Dedicated task force to ease the process (technical and organizational) March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop

K. Foraz Machine phase Interconnections Including: – more than 1’900 interc. – vacuum tests – electrical tests Slow start-up: missing magnets, co-activities Got organized on the 3 rd sector while continuous sequence of magnets were available. March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop

K. Foraz Machine phase Interconnections Major incidents November 06 - Inner Triplets failure: heat exchanger tube Few weeks later after repair : Inner triplets spiders failed ► Sector 78 cooled and power test without IT in order to gain experience. September 07: PIM crisis – Ingenious solution for diagnostic : RF ball February 08: connection cryostat crisis March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop

K. Foraz Hardware Commissioning Phase Short Circuit Tests & Individual System Tests Each system individually commissioned with relevant performance assessment IST Include: – cryogenic line pressure and leak tests, – collimators tests, – Powering Interlock System tests, – Energy Extraction tests, – Beam Instrumentation tests, – Injection and Beam Dump systems tests, – Cryogenics Instrumentation tests, Had to fit within tight constraints of the LHC installation planning March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop

K. Foraz Hardware Commissioning Phase Cool-down Started in January painful beginning, but weak points identified: – Cryogenics Cold compressor tuning Cryo commissioning of stand alone magnets DFB’s : condensation and thus frost – Services Power cuts Faulty relays Network problems CV consolidations March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop

K. Foraz Hardware Commissioning Phase Powering tests Object: power test each sector independently to ensure a safe and efficient machine start-up without being plagued by technical problems. Reminder: in 2003, ~10wks/sector and one sector at a time Beginning of 2007, after QRL and IT crisis, decision was taken to increase the number of sectors being commissioned in parallel from 2 up to 6 ! March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop

K. Foraz Hardware Commissioning Phase Powering tests Started in March 2007: painful beginning due to low Mean Time Before Failure and High Mean Time To Recovery March 2008: Taking into account the recent delays, and in order to meet the target of a beam in LHC before the end of this summer, decision was taken to qualify circuits at least for 5TeV. Situation in May 08: – Sector 45 commissioned partially – Sector 56: commissioned to 5TeV – Sectors 78 & 81: progressing – From mid-June: every 2 weeks, a sector will be available for powering tests March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop

K. Foraz Keep baseline documentation is essential through the lifetime of the project Integration vs. Installation Safety First 25% of installation (2/8 sectors) are longer Gain experience asap for each phase is a benefit Fast Internal Intervention team is crucial March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop Lessons learned