Old car vs. New Car The Choice The Sticker Price $ 5.2M The Cost of the Old Car “We are approaching the practical limit of functionality for that building” -member of the Property Committee
Jim Bettridge Lea Cromwell Scott Hobbs David Kraemer (Head) Stan March Paul Reiss Richard Thomas Gary Yancy Father Peter Walsh Dick DePatie (Parish Administrator) The Property Committee
Mission What Is Our Business? Go and make disciples who live... a deeper life in Christ a more holy communion with one another, and a greater love for the world Vision A church bursting with disciples who are so transformed by the Holy Spirit that they live to give for the love of the Lord.
Poor location Energy “hog” Access issues Digital integrity Inefficient layout Aging infrastructure Worn interior Church House Issues
Ministry of Welcome Center Ministry of Administration Ministry of Teaching/Spiritual Formation Ministry of Prayer Ministry of the Building (4 Elements)
Assess Needs Develop Organized Concepts Evaluate Existing Buildings and Site Examine Resources Empower Implementation Team Commence Gathering Resources Initial Steps Accomplished by July 2015
Views From West-Predesign Concept by Paul Reiss
Views From East-Predesign Concept by Paul Reiss
as Site concept fixed Program Management firm engaged Initial space program identified—7,056 GSF plus 1450 sf renovation Preliminary budget ranges calculated: $3.5M Includes non-construction items Went to leadership for discernment approval
Selected design team: Summer, 2015 Complete schematic design documents including engineering designs: November, ,575 gsf Received professional cost estimate: December, 2015: $ 4.7M Winter : considered reductions; conference room need; office flow; additional drainage work; storage needs Concluded need for “composite scheme”
Approved Schematic Design 8,575 gsf Upper Level Oratory Welcome Center 2 new conference rooms Clergy Offices Lower Level Entry Business Offices Staff Conference Room Mechanical Composite Scheme 9,846 gsf Upper Level Oratory Welcome Center Staff Conference Room Clergy and Business offices Lower Level Entry (Future) 2 new conf. rooms Storage Mechanical
Tai Soo Kim Partners Architects Ministry Center Addition June 7, 2016
Tai Soo Kim Partners Architects Site Plan
Tai Soo Kim Partners Architects South Elevation
Tai Soo Kim Partners Architects West Rendering
Tai Soo Kim Partners Architects East Rendering
Tai Soo Kim Partners Architects East Elevation
Tai Soo Kim Partners Architects First Floor Plan
Tai Soo Kim Partners Architects Lower Level Plan
$ 4.5M Net of Expenses -$ 1.8M Rectory _________________________ = $ 2.7M -$.5M Capital Needs/3 Years _________________________ = $ 2.2M for CFM Empower The Parish
$ 3.8M Construction Cost + $ 1.4M FF&E/Fees/Moving, etc. ____________________________ = $ 5.2M All In - $ 2.2M Empower we have ____________________________ = $ 3M Needed to Build To Build The Center For Ministry
Church House $? Other Needs That Arise $? Other Capital Needs