Atlas Upgrade week - November 15 th, 2011M. Raymond – CERN/PH-ADO-PO 1 Introduction Many activities are planned to be performed during the shut down 2013-2014.

Slides:



Advertisements
Similar presentations
Status of Sensor and Hybrid Production LHCb Zurich Week T. Bowcock.
Advertisements

ATLAS LHCC 28/11/00 A. Henriques/CERN 1 H8 : Pixel, SCT, TRT, Tiles, LAr em barrel, Muons SPS H6: EMEC, HEC, FCAL, Background studies GIF: Muons (MDT,
ATLAS DBM a Diamond based luminosity and Beam spot Monitor Marko Mikuž For the DBM project IBL GM, CERN, October 19 th, 2011.
Status of the ATLAS MM project
UK – quad module. Experience with FE-I4 UK groups relatively new to ATLAS pixel Have 5 USBPix systems up and running now – Glasgow, Edinburgh, Manchester,
LHCC referees meeting, 10 October 2005Børge Svane Nielsen, NBI1 Status of the FMD LHCC referees meeting, 10 October 2005 Børge Svane Nielsen Niels Bohr.
ATLAS detector upgrades ATLAS off to a good start – the detector is performing very well. This talk is about the changes needed in ATLAS during the next.
WP2: Detector development Summary G. Pugliese INFN - Politecnico of Bari.
The BTeV Tracking Systems David Christian Fermilab f January 11, 2001.
March 20, 2001M. Garcia-Sciveres - US ATLAS DOE/NSF Review1 M. Garcia-Sciveres LBNL & Module Assembly & Module Assembly WBS Hybrids Hybrids WBS.
Summary of CMS 3D pixel sensors R&D Enver Alagoz 1 On behalf of CMS 3D collaboration 1 Physics Department, Purdue University, West Lafayette, IN
Pixel Support Tube Requirements and Interfaces M.Olcese PST CDR: CERN Oct. 17th 2001.
ATLAS Upgrade ID Barrel: Services around ‘outer cylinder’ TJF updated According to the drawing ‘Preparation outer cylinder volume reservation’
Activities Status and Plan for the week D. Giugni / INFN Milano D. Giugni Monday Meeting
WP2: Detector development Summary G. Pugliese INFN - Politecnico of Bari.
The ATLAS Insertable B-Layer (IBL) Project C. Gemme, INFN Genova On behalf of the ATLAS IBL COllaboration RD11 Firenze July 2011.
M. Gilchriese ATLAS Upgrade Introduction January 2008.
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
November 18, 2008 John Haggerty 1 PHENIX In Run 9 John Haggerty Brookhaven National Laboratory.
Pixel/IBL status and plans A.Rozanov A.Rozanov ATLAS-France
09/03/2010 ADO-PO section meeting Beam Pipe Extraction/Insertion R. Vuillermet.
CERN, Main challenges for the ATLAS upgrade project in the coming year.
1 H. Pernegger/CERNVertex 2011 ATLAS Insertable B-Layer Overview Vertex 2011 Rust, Austria H. Pernegger / CERN on behalf of the ATLAS IBL collaboration.
Summary of CMS 3D pixel sensors R&D Enver Alagoz 1 On behalf of CMS 3D collaboration 1 Physics Department, Purdue University, West Lafayette, IN
1 H. Pernegger/CERNIBL cooling review 15/5/2012 IBL Cooling Requirements H. Pernegger.
M&O status and program for ATLAS LAr calorimeter R Stroynowski (on vacations)
Technical Support Activities in PH-ADO-PO
Planar Pixels Sensors Activities in France. Phase-2 and core R&D activities in France -Development of sensor simulations models -Sensor technology Edgeless/active.
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
G. Carboni – Muon Meeting – April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to
ATLAS PIXEL SYSTEM OVERVIEW M. Gilchriese Lawrence Berkeley National Laboratory March 11, 1999.
Communications G. Darbo – INFN / Genova IBL MB#15, 5 October 2009 o Bump Bonding Selex / INFN Roma, October, 30 th 2009 G. Darbo - INFN / Genova.
Michel RAYMOND – April 14 th, 2011 Technical Support Activities in PH-ADO-PO Goals for 2011.
ATLAS micromegas activities (MAMMA)
UCSC August 12, 2008 U.S. Upgrade R&D Meeting: Strip Detector  Seiden.
Report on CMS 3D sensor tests Enver Alagoz 1 On behalf of CMS 3D collaboration 1 Physics Department, Purdue University, West Lafayette, IN
October RRB G. Darbo & H. Pernegger RRB – October 2010 o October RRB Slides for Marzio’s RRB talk CERN, October, 11 th 2010 G. Darbo & H. Pernegger.
G. Carboni - Muon Meeting – Muon Meeting 12/ Agenda IntroductionGiovanni (30’) GEM and TDR AddendumWalter (20’) Update on M1 ratesAlessia.
3D sensors for tracking detectors: present and future applications C. Gemme (INFN Genova) Vertex 2013, Lake Starnberg, Germany, September 2013 Outline:
15/09/20111 ATLAS IBL sensor qualification Jens Weingarten for the ATLAS IBL Collaboration (2 nd Institute Of Physics, Georg-August-Universität Göttingen)
Transition to cables Staves Services IP Underside of stave: IBL modules IBL Design.
ATLAS closing scenario  Where we are  What is still be done before closing (ADO-PO support)  Closing scenario / Procedure / Schedule Prepared by Michel.
General Muon Meeting, 03-March-2014 Jay Hauser “Update on Phase 2 muon Technical Proposal”  Recent developments:  ME0 inserted into HGCAL as for other.
ATLAS Upgrade Report ATLAS Upgrade Report (20/03/12) Planning Assumptions Phase-0 Plans Phase-I Plans - Letter of Intent Phase-II - LoI Planning Conclusions.
Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities.
1 G. Aielli for the RPC community. General information  BOE to be delivered in September  Detector design is over  Production facility reviewd and.
Upgrade PO M. Tyndel, MIWG Review plans p1 Nov 1 st, CERN Module integration Review – Decision process  Information will be gathered for each concept.
Activité LPNHE en 2012 et 2013 G.Calderini Tracker upgrade.
Joerg Dubert’s Questions as you all aware we currently do not yet know how the final mechanical design of the new Small Wheel will look like. Nevertheless,
Giulio Pellegrini 27th RD50 Workshop (CERN) 2-4 December 2015 Centro Nacional de MicroelectrónicaInstituto de Microelectrónica de Barcelona 1 Status of.
Eric Vigeolas, July the 3 rd Status The IBL detector construction already started and the components assembly (flex, modules, stave loagin) will.
Steinar Stapnes, LHCC June The ATLAS inner detector TRT endcap A+B TRT endcap C TRT barrel SCT barrel SCT endcap Pixels uWhole ID sits inside bore.
Giulio Pellegrini Actividades 3D G. Pellegrini, C. Fleta, D. Quirion, JP Balbuena, D. Bassignana.
Atlas status report. LHC Cooldown Status LHC is proceeding with the cooldown and the hardware commissioning L.Evans is asking the experiments to close.
ATLAS Upgrade Report to the LHCC ATLAS Upgrade Report to the LHCC Phil Allport 25/09/12 Schedule Assumptions Phase-0 –IBL –Consolidation of Many Systems.
ATLAS Italia – IBL G. Darbo – INFN / Genova CERN, 2 March 2011 o IBL ATLAS Italia / Referee CERN, March 2 nd 2010 G. Darbo – C. Meroni INFN / GE – MI Agenda:
RD42 Status Report W. Trischuk for the RD42 Collaboration LHCC Meeting – June 12, 2013 Development of CVD Diamond Tracking Detectors for Experiments at.
Upgrade Intro 10 Jan 2010 Norman Gee. N. Gee – Upgrade Introduction 2 LHC Peak Luminosity Lumi curve from F.Zimmermann : Nov Upgrade Week ? ?
ATLAS Pixel Upgrade G. Darbo - INFN / Genova LHCC- CERN 1/76/2008 o Pixel/B-layer Developments LHCC Upgrade Session CERN, 1 / 7 / 2008 G. Darbo - INFN.
22/09/2011 ADO-PO section meeting ADO : Atlas Detector Operation PO : Project Office R. Vuillermet.
SVT – SuperB Workshop – Annecy March 2010
IBL Technical Aspects H. Pernegger / CERN.
FBK / INFN Roma, November , 17th 2009 G. Darbo - INFN / Genova
SVT – SuperB Workshop – SLAC 6-9 Oct 2009
IBL Overview Darren Leung ~ 8/15/2013 ~ UW B305.
Hybrid Pixel R&D and Interconnect Technologies
Francesco Forti University and INFN, Pisa
L H C A T L A S International Collaboration on the LHC Project
Update on ATLAS insertable B-layer
Perugia SuperB Workshop June 16-19, 2009
Presentation transcript:

Atlas Upgrade week - November 15 th, 2011M. Raymond – CERN/PH-ADO-PO 1 Introduction Many activities are planned to be performed during the shut down The sequence of opening/closing and the configuration chosen for the Detector area are guided by the priorities in between these activities. Known activities that require a specific configuration of UX15 Replacement of beam pipes (VA, VT, VI) IBL installation nSQP/Pixels Removal of MB scintillators New LVPS for Tiles New LVPS for LAr Tile drawers repair Completion of EE chambers installation MDT + RPC chambers in sector 13 Replacement of few TGC chambers in Big Wheels New neutron shielding on the toroid end cap Probably the most constraining Standard opening is suitable (more or less)

Atlas Upgrade week - November 15 th, 2011M. Raymond – CERN/PH-ADO-PO 2  Side C needs to be moved to a Large Opening configuration  Side A is in Standard Opening configuration (like in 2010 and 2011) Although VA and VT beam pipes are replaced with Aluminum ones The opening will be as efficient as possible No planned stop for any intervention on detectors Shut down starts on Dec. 03 rd, 2012 / ends July. 31 st, 2014 Pixels extraction/insertion ≈ 1-2 weeks (based on installation) Pixels connection and commissioning ≈ 14 weeks (based on installation) Main assumptions used in the schedule The shutdown in a nutshell Two options are still under consideration : 1.To insert IBL in situ 2.To extract the Pixels and install both NSQP and IBL at surface (SR1) In both options, the opening scenario is nearly the same. Configuration for Pixels / IBL extraction is completed by January 25 th, 2013 In order to be closed on July 31 st 2014 Pixels/IBL insertion must be completed by mid-February 2014 About 1 year is available for the integration work in SR1

 A framework of the time schedule and scenario is prepared and will be soon on ATLAS dedicated page

IBL FEI4 B FEI4 B design has been closed and finished during September – Design includes only fixes and things necessary for the IBL Final design was signed off – See Chip was submitted to IBM Sept wafers were ordered, with 16 of them on “fast track” (44 days instead of normal 73 days) Expect first wafers end of November. Submitted !

Sensor technology Planar Slim Edge Sensors (CiS) oxygenated n-in-n silicon; 200 µm thick minimize inactive edge by shifting guard-ring underneath pixels  215 µm inactive edge achieved 3D Slim Edge Sensors (FBK and CNM) partial 3D: electrodes etched from both sides p-type substrate; 230 µm thick no active edge  ~200 µm inactive edge achieved (drawing outdate: columns penetrate full sensor)

Hit Efficiency in testbeam SCC61: Planar 6x10 15 n eq cm -2 SCC97: 3D CNM 6x10 15 n eq cm % 97.4% punch- through bias dot solder bump A number of pixels don’t work after proton irradiation (TID ~ 3x IBL lifetime) Same behaviour for both sensor types  FE-I4 “feature” (Pixels masked during analysis) Data taken at Φ =15 ° incidence  smearing of electrode structure

Sensors for IBL: 3D and Planar ATLAS Pixel extended Institute Board endorsed the recommendation of the review panel: produce enough Planar sensors to build 100% of the IBL continue current 3D sensor production to build 25% of the IBL 3D slim edge (FBK,CNM) Planar n-n Slim Edge Design (CiS) Target 25% IBL 6 batches in production: and the first 3 batches will go to IZM for bumpbonding Delivery dates agreed with manufacturers for Sept, Nov, (first 3 batches) + early 2012 (next 3 batches) 1 st batch now at IZM for BB Target 100% IBL 6 batches in production at CIS Delivery dates agreed with manufacturers for Aug Sept, Oct, Dec and Jan, to complete order 3 batches at IZM for BB

Stave Flex circuits 2 Designs: multi-layer flex and Al-kapton flex have been reviewed during September Recommendation received from reviewers: – Multi-Layer Cu/Al flex adopted as baseline – A backup solution based on pure Cu (standard technology) is developed in parallel Based mainly on schedule constraints, risk evaluation, manufacturer’s track record and the seemingly modest physics gain resulting from the mass difference between the two options the Review unanimously decided to recommend to the IBL Management to accept the multilayer design as baseline for the IBL stave. We are, however, concerned with the potential risk associated with the Al/Cu via technology, which lacks maturity. As insurance against a possible fatal flaw in the via technology revealed by more comprehensive QA/QC tests yet to be carried out, a backup should be developed and manufactured in parallel, based entirely on standard technology. We strongly recommend embarking on such a comprehensive qualification programme.

DBM modules: Lab and Testbeam Results Four DBM modules built at IZM – 21x18 mm 2 pCVD from DDL – FE-I4 ATLAS IBL pixel chip – 336x80 = channels, 50x250 μm 2 Testbeam and labtests very encouraging Four more DBM modules with final specs currently in process at IZM Diamond + I4 I4 only Module on test board 4 modules after flip-chipping First noise map of a DBM module X-ray perfect Noise map uniform – Indication of success  HV issue due to IZM metallization up to edge

DBM integration and support: Definded interfaces in cooperation with nSQP. No showstoppers, agreed to work sharing: – Services routing done, big thanks to nSQP team – DBM is treated as (half)stave 15 of IBL DBM now also included in IBL MoU DBM should be included in next presentation to LHCC to get approval

Focus over the last 12 months Understanding design & connectivity Imported CAD model from PE to CATIA Design changes: e-readout, mechanics, reliability Procurement, prototyping Setting up infrastructure in B180 cleanroom Assembly & QC procedures Assembly trials 15/11/2011 F. Dittus nSQP Project Status ATLAS Upgrade Week 11 PP1 PP0 As-built Mock-up, April 2011 OSP ISP

Phase-II (installation ) 1. New ID (strips and pixels) (Very substantial progress in many areas, 27 sessions out of total of 55 ID related) 2. New LAr front-end and back-end electronics 3. New Tiles front-end and back-end electronics 4. LAr new FCAL ? 5. LAr HEC cold electronics consolidation ? 6. Muon Barrel and Large Wheel system upgrade ? 7. TDAQ upgrade 8. L1 track trigger (possible role of gas detectors)? 9. TAS and shielding upgrade 10. LUCID upgrade ? 11. Various infrastructures upgrade 12. Common activities (installation, safety, …)