Lab-Wide Earned Value Management System Project Oversight Committee Meeting September 11, 2008 Dean. Hoffer / Elaine McCluskey.

Slides:



Advertisements
Similar presentations
A Short Course in Project Management
Advertisements

Program Management Office (PMO) Design
1 ICD10 Project Status January 31, Current Timelines and Status - ICD10 Detailed Project Planning is progressing Key internal project milestones.
Module 8: Government Required Reports
PAGE Quick Guide to the FedRAMP Readiness Process 1 August 2014 Presented by: FedRAMP PMO
Why revisit the SA? Now you are in post, your view of your personal skills, needs and knowledge levels may have changed. Your mentor will probably not.
Project Bidding Procedures Enhancing Data and Presentation Skills for Engineers EDASPE Writing the RFP Training Courses – July 2004.
FRA’s Earned Value Management System Corrective Action Plan Implementation January12, 2010 Dean Hoffer and Mike Rhoades.
IS 421 Information Systems Management James Nowotarski 16 September 2002.
Project Plan The Development Plan The project plan is one of the first formal documents produced by the project team. It describes  How the project will.
10.5 Report Performance The process of collecting and distributing performance information, including status reports, progress measurements and forecasts.
19/20 May 2015, Riga “From Gaps to Caps – Risk Management Capability Based on Gaps Identification in the BSR” TASK D COMPARISON OF EVALUATIONS OF EMERGENCIES.
FRA’s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011 Dean Hoffer Head, Office of Project Management Oversight.
CS & ECE Senior Design Project Winter 2008 Karen Davis Chia Han Altan Ferendeci.
EVMS Refresher and Update Training
3 Dec 2003Market Operations Standing Committee1 Market Rule and Change Management Consultation Process John MacKenzie / Darren Finkbeiner / Ella Kokotsis,
WELCOME! Elementary Math Building Leads / Coaches Please complete the ORANGE information sheet. Wednesday, September 26, 2012 Kathleen Wilson - Math Program.
Fusion GPS Externalization Pilot Training 1/5/2011 Lydia M. Naylor Research Lead.
1 Part 5: Closing Task 1 Kelvin asked you to help him prepare and present the final project presentation. Prepare a short presentation to summarize result.
DBS to DBSi 5.0 Environment Strategy Quinn March 22, 2011.
Agenda Teams Responsibilities Timeline Homework and next steps.
FRA’s Earned Value Management System Overview for Self Assessment Surveillance March 12-14, 2012 Dean Hoffer Head, Office of Project Management Oversight.
Senior Culminating Project
HFT project Overview and Status October 14, 2010 F.Videbaek BNL.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier Director for Conventional Facilities CD-2 Planning May 8, 2007.
Copyright 2003 Northrop Grumman Corporation 0 To PIID or Not to PIID: Lessons Learned in SCAMPI Evidence Preparation To PIID or Not to PIID: Lessons Learned.
Lab-Wide Earned Value Management System Project Core Team Meeting October 01, 2008 Dean A. Hoffer/Elaine McCluskey.
Elements of the Cohort Review Approach Harvey L. Marx, Jr. Lisa Schutzenhofer TB Program Controller TB Program Manager.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
Lab-Wide Earned Value Management System Project Core Team Kickoff Meeting April 16, 2008 Dean A. Hoffer.
LBNE Working Group Meeting December 20, :00– 5:00 PM Snake Pit.
I n t e g r i t y - S e r v i c e - E x c e l l e n c e Business & Enterprise Systems The Integrated Master Plan (IMP) and the Integrated Master Schedule.
Executive Session Director’s Progress Review of the NOvA Project August 4-5, 2010 Dean A. Hoffer.
Fermilab Presentation Greg Bock, Pepin Carolan, Mike Lindgren, Elaine McCluskey 2014 SC PM Workshop July 2014.
DEX Publication Project OASIS PLCS Telecon 27 November 2007 Trine Hansen.
DUSEL Beamline Working Group Meeting March 09, :00 AM – Snake Pit (WH2NE) By Dean Hoffer - OPMO.
UU Master Class Earned Value 17 July Earned Value Contents What is Earned Value / Earned Value Analysis Why and where is it used A brief history.
Lab-Wide Earned Value Management System Project Core Team Meeting November 12, 2008 Dean A. Hoffer/Elaine McCluskey.
PPPL is Committed to the Success of NCSX Rob Goldston, Director Princeton Plasma Physics Laboratory August 15, 2007.
Lab-Wide Earned Value Management System Project Oversight Committee Meeting December 11, 2008 Dean. Hoffer / Elaine McCluskey.
Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 1 Project Management Cost and Schedule Nadine Kurita ANSI/EIA-748-A Standard.
Lab-Wide Earned Value Management System Project Core Team Meeting May 28, 2008 Dean A. Hoffer.
Lab-Wide Earned Value Management System Project Core Team Meeting September 17, 2008 Dean A. Hoffer/Elaine McCluskey.
DOE Review of LARP – Feb 17-18, 2014 DOE Critical Decision Process Ruben Carcagno February 17,
Courtesy Reminders: During the webinar, you may select *7 on your phone to speak, and use *6 to mute. Please refrain from placing the phone on HOLD during.
FRA Earned Value Management System Implementation Project October 9, 2008 Dean Hoffer / Elaine McCluskey.
Long-Baseline Neutrino Facility LBNF Update: LBNF EVMS Implementation for CD-3a Elaine McCluskey, LBNF Project Manager Bob O’Sullivan, Project Controls.
Lab-Wide Earned Value Management System Project Core Team Meeting September 10, 2008 Dean A. Hoffer/Elaine McCluskey.
K. Long, 25 June, 2016 IDR: structure and overall timeline: Slides are to introduce discussion of how we prepare IDR. Propose to revise slides as we discuss.
Lab-Wide Earned Value Management System Project Core Team Meeting July 10, 2008 Dean. Hoffer / Elaine McCluskey.
IS&T Project Reviews September 9, Project Review Overview Facilitative approach that actively engages a number of key project staff and senior IS&T.
FRA Earned Value Management System January 9, 2009 Dean Hoffer.
Financial System Upgrade Agency Change Champion Deployment Session March 16 th, 2006.
Cornerstone Phase 4 Update for Stakeholders October 19, 2011
Project Management W. J. Foyt
Roller Coaster Overview
Project Kickoff Meeting
Parent Information & Training Session #1
The School Point of View
Project Progress Document Optimization 22 March 2007
IS&T Project Reviews September 9, 2004.
Student Administration and Support Programme and Project Timelines
Cornerstone Phase 4 Update for Stakeholders October 19, 2011
Student Administration and Support Programme and Project Timelines
Ctclink executive leadership committee May 31, 2018
EVMS Status and Overview
Linac Coherent Light Source (LCLS)
Linac Coherent Light Source (LCLS)
Executive Project Kickoff
Presentation transcript:

Lab-Wide Earned Value Management System Project Oversight Committee Meeting September 11, 2008 Dean. Hoffer / Elaine McCluskey

11-Sep-2008Lab-Wide EVMS Project Oversight Committee Meeting 2 Agenda Project Progress [Dean] –Progress on Reviews of System Description Document and Implementing Procedures –Next Steps –Schedule Training [Dean/Elaine] CAM Notebooks FYIs –Customized Cobra CPR5 3 month rolling average report for variance analysis/thresholds [Dean] –How other Lab’s track Contingency/ Management Reserve [Dean/Elaine] –NOvA Project Preparation Meeting 28-Aug [Dean] Next Meeting 9-Oct

11-Sep-2008Lab-Wide EVMS Project Oversight Committee Meeting 3 Project Progress System Description Document/Implementing Procedure Reviews Oversight Committee Review and Comment – due today EG&G Flow Chart Review of Implementing Procedures –Initial review complete –Tasked to generate missing flow diagrams, comment on existing flow diagrams and consistent formatting

11-Sep-2008Lab-Wide EVMS Project Oversight Committee Meeting 4 Next Step System Description Document/Implementing Procedures Core Team Review –Core Team consolidates Oversight Committee comments, EG&G flow diagram draft/comments and update documents (Elaine to track comment resolution in spreadsheet) –EG&G person with DOE EVMS certification experience (outside 3 rd Party) reviews documents after updates complete

11-Sep-2008Lab-Wide EVMS Project Oversight Committee Meeting 5 Review Process

11-Sep-2008Lab-Wide EVMS Project Oversight Committee Meeting 6 Schedule Key Activities/Projected Dates –Documents ready for Readiness Review – 17- Oct-2008 –Readiness Review by OECM – 16-Dec-2008 –OECM On-Site Review – 11-Mar-2009 (still do not have confirmation on suggested Readiness Review and Site Review dates from OECM)

11-Sep-2008Lab-Wide EVMS Project Oversight Committee Meeting 7 SLAC Training Distributed to Core Team for review –LUSI EVMS Training Slides –LCLS EVMS Training Slides –(Slides linked off of meeting webpage)

11-Sep-2008Lab-Wide EVMS Project Oversight Committee Meeting 8 Training Discussion with BNL 2 Day General EVMS Training by Outside Trainer (for CAMs, Project Management and Senior Management) Individual CAM Coaching (Finishing School) – asked example OECM interview questions and coached on appropriate responses and use of CAM Notebook Specific Topic Training – i.e. Variance Analysis, ETC Mock Review – full week review with interviews with feedback on documentation, presentations and interview skills (done by same person as 2 day review) BNL will be sending training vendor contact information

11-Sep-2008Lab-Wide EVMS Project Oversight Committee Meeting 9 CAM Notebooks SLAC –Emphasized importance of having and using CAM Notebooks. Hard Copies updated by Project Controls. Information available electronically in the Hammer. (have content index) BNL –Hardcopy and same information posted monthly by Project Controls (to be sent content index)

11-Sep-2008Lab-Wide EVMS Project Oversight Committee Meeting 10 SLAC CAM Notebook Index 1.Org Charts (Directorate and Project) 2.WBS Structure & Dictionary 3.Responsibility Assignment Matrix (RAM) 4.Milestone Structure & Dictionary 5.Work Authorization Document (WAD) 6.P3 Milestone Chart 7.P3 Detail Schedules 8.Control Account Planning (CAP) sheets 9.Cost Performance Report (CPR) Earned Value reports 10.tbd 11.EIA-748A 32 Criteria / Acronyms 12.misc

11-Sep-2008Lab-Wide EVMS Project Oversight Committee Meeting 11 FYI’s Customized Cobra CPR5 3 month rolling average report for variance analysis/ thresholds How other Lab’s track Contingency/ Management Reserve NOvA Project Preparation Meeting 28- Aug

11-Sep-2008Lab-Wide EVMS Project Oversight Committee Meeting 12 Customized CPR5 3 Month Average Report Report has been written by Deltek Consultant Report will be installed/tested along with Cobra V4.7 Upgrade Installation and testing in DEV environment week of 15-Sep and in PRD week of 22-Sep Projects can run and use for Sept. variance analysis and reporting

11-Sep-2008Lab-Wide EVMS Project Oversight Committee Meeting 13 Tracking Contingency & Management Reserve PNNL –Do not use Cobra. EV done in home grown tool Plan.Net. SLAC –Use Cobra, but track Contingency and MR outside of Cobra, but include in monthly report. MR is for OPC and Contingency is for TEC. BNL –Contingency/Management Reserve is tracked and reported outside of Cobra

11-Sep-2008Lab-Wide EVMS Project Oversight Committee Meeting 14 Agenda from NOvA Project Preparation Meeting (28-Aug) Things for NOvA to working on –Work Authorization –FRA Variance Thresholds –Monthly ETC –$RAM –CAM Notebooks OECM’s Expectations –1 Day Planning/ Readiness Assessment Meeting –Full Week Certification Review

11-Sep-2008Lab-Wide EVMS Project Oversight Committee Meeting 15 Next Meeting Thursday, 9-Oct