TF Fabrication Progress is being made on TF bundle fabrication activities but the schedule remains tight. All 24 outer conductors have been machined but.

Slides:



Advertisements
Similar presentations
Engineering Operations Outage Status: Post-run diagnostic calibrations have been completed and in-vessel work can start on PCHERS, FIDA, MPTS, and the.
Advertisements

August NSTX-U Team Meeting. Engineering Operations August 15, 2014 NSTX-U In-Vessel installations and calibrations have concluded, and activities have.
Chubaka Producciones Presenta :.
1 The CNGS Reflector Water distribution system Outer conductor Inner conductor Drain connections  5 Drain tube Support and alignment frame Transport chassis.
J. H. ChrzanowskiNSTX TF Flag Joint Design Review1 NSTX TF Flag Joint Design Review Fabrication and Assembly April 10, 2003 By: James H. Chrzanowski.
Status of the LARP Phase II Secondary Collimator Prototype 30 September 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US.
RF Measurement Plan Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory January 20, 2011 MICE Video Conference Meeting.
2012 JANUARY Sun Mon Tue Wed Thu Fri Sat
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 14, 2009.
MICE Video Meeting, 10 Jan 081 Spectrometer Magnet Progress Michael A. Green Lawrence Berkeley Laboratory.
1S. Virostek - LBNL Spectrometer Solenoid Fabrication Update Vendor still expecting to complete first magnet by the end of November, before X-mas more.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Whole School Attendance Whole School Attendance 94.64% Overall School Absence 5.36%
Fermilab Cavity Refurbishment Status J. Reid M. Slabaugh November 19, 2014 J. Reid 1.
Team Meeting April 25, 2014 NSTX-U Construction Progress NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U.
Sign Up for SAT/ACT Your Easy How To Guide. SAT Registration
Proposed TF Joint Design C Neumeyer 2/26/9 Notes: 1)Several concepts included are based on ideas developed by R Woolley 2)No analysis has yet been performed.
Princeton University Plasma Physics Laboratory EVMS Certification Review NSTX Project Overview Ron Strykowsky October 4-6, 2011.
Machine Installation and Construction Management Erik D. Perry Princeton Plasma Physics Laboratory NSTX Upgrade Project Office of Science Review LSB B318.
NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/ NSTX Upgrade Progress Overview Ron Strykowsky Erik Perry, Tim.
NSTX TF Flag Joint Design Review INTRODUCTION C Neumeyer 8/7/3.
Thoughts about the MQXF development plan P. Fessia Thanks to discussions within the MDT section (P. Ferracin, J. C. Perez, E. Todesco, P. Ferracin), L.
February NSTX-U Team Meeting. Engineering Operations Feb. 11, 2014 NSTX-U In-Vessel installations and Calibrations to conclude in late March (3/28/2014)
Project Overview Ron Strykowsky, J.Chrzanowski, L.Dudek, E.Perry, T.Stevenson LSB B318 January 3, 2013 NSTX-U Supported by Culham Sci Ctr York U Chubu.
1 NSTX Upgrade Progress Report May 7 th, 2013 Ron Strykowsky, Erik Perry, Tim Stevenson, Larry Dudek, Steve Langish, Tom Egebo, Mike Williams and the NSTXU.
April NSTX-U Team Meeting. Engineering Operations April 25, 2014 NSTX-U In-Vessel installations and Calibrations to conclude in mid-June to shift activities.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
Anthony Indelicato DOE-Princeton Site Office May 2012 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the NSTX.
1 Pixel Detector General –July Evidence of galvanic corrosion in EU barrel cooling tubes. Recovery plan implemented, this problem now solved but…..
NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade Team Princeton Plasma Physics Laboratory NSTX Upgrade Project Office of Science.
DATE POWER 2 INCOME JANUARY 100member X 25.00P2, FEBRUARY 200member X 25.00P5, MARCH 400member X 25.00P10, APRIL 800member.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
March 2005, USCMS Trigger video meetingD. Acosta1 Revised Schedule for SP Pre-Production Continued testing of first two pre-production boards over next.
NSTXU Project Update Jim Chrzanowski, Larry Dudek, Erik Perry, Tim Stevenson, Ron Strykowsky and the Project Team October 4th, 2013 NSTX-U Supported by.
2011 Calendar Important Dates/Events/Homework. SunSatFriThursWedTuesMon January
Hi-Lumi Conductor Procurement A.Ballarino, B. Bordini, L. Oberli HL-LHC/LARP International Review of Superconducting Cable for the HL-LHC Inner Triplets.
Engineering Operations Outage Schedule Center Stack casing is scheduled to go back in the vessel today Complete NB armor, Diagnostic calibrations, clean/photo/close,
1 HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 Outline:  Full scale prototype status  Light source test  Construction Schedule.
NSTX Upgrade Test Cell Initial Schedule Vent vacuum vessel by 9/19 No vessel entry at this time Period of removals prior to start of outage: 9/19 – 10/14.
FRESCA2 Technical Meeting 5-Validation of coil winding with Cu coils Françoise Rondeaux 09/06/ CEA-Irfu-SACM-LEAS - 5-Rondeaux- FRESCA2 Technical.
ATLAS Pixel Detector September 2002 N. Hartman LBNL 1 Pixel Support Tube: Cost and Production Schedule September 2002.
Tom Egebo PPPL Review of the NSTX TF Coil Repair Effort September 3 - 4, 2003 Cost & Schedule to Completion Supported by Columbia U Comp-X General Atomics.
11 T Dipole Project CERN Status M. Karppinen 11 T Management meeting 1 July 2013.
NSTX TF Flag Joint Status of Design, Analysis, Test Activities & Design Review Preparations C Neumeyer NSTX Team Meeting 7/24/3.
Anthony Indelicato DOE-Princeton Site Office October 2013 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the.
Engineering Operations Outage Status: New shielding of HHFW/in-vessel components has been completed. Fit-ups of OH bus lead upgrades to reduce error fields.
July 2007 SundayMondayTuesdayWednesdayThursdayFridaySaturday
Engineering Operations Outage Schedule The vessel & beamline are under vacuum. 1st Bake-out complete. Air leaks found and fixed. The OH coil will be installed.
Project Overview Ron Strykowsky Princeton Plasma Physics Laboratory NSTX Upgrade Project Office of Science Review LSB B318 December 11-12th, 2012 NSTX-U.
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
Engineering Operations TF Commissioning Mechanical testing of TF flag/box assemblies complete, inner bundle installed, and all joints made up. Joint resistance.
RF Module Update MICE Collaboration Meeting 44 Andrew Lambert Lawrence Berkeley National Laboratory March 30 th, 2016.
MICE Prototype Coupling Coil Cooling Circuit Design Dan Cheng Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
MICE Coupling Coil Fabrication Steps to Complete Allan DeMello Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
Anthony Indelicato DOE-Princeton Site Office December 2012 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the.
Chiho Wang ATLAS TRT Duke University Dubna, May Barrel integration status May 24, 2005.
QXF Coil Fabrication & Tooling Reaction / Impregnation
BSS Prep work at CERN and Acceptance of Parts
Oversight Board Meeting October 3, 2017 Rob Michnoff
Spectrometer Solenoid Fabrication Status and Schedule
Far Detector Activities Late 2017 – Early 2018
13-block rotation schedule
The SAT will be given at ECHS on the dates below!
As needed for progress monitoring
LARP Rotatable Collimators for LHC Phase II Collimation
Overall time schedule of SRF activities
BOARD MEETINGS Thursday, August 27th TBA NJHS MEETING SCHEDULE
UPPSALA UNIVERSITY_GERSEMI PROJECT
2015 January February March April May June July August September
Presentation transcript:

TF Fabrication Progress is being made on TF bundle fabrication activities but the schedule remains tight. All 24 outer conductors have been machined but the vendor is behind schedule on the 12 inner conductors. Vendor has extended work hours and is considering a 2nd shift. PPPL will take partial delivery to begin prep/insulation on schedule. The curing/soldering oven is in service and a cooling tube has been soldered into the 1st TF bundle outer conductor. Oven is being loaded today to solder a batch of 4 outer conductors The oven will be moved to the NTC high bay area on Aug. 7th to insulate, assemble and mold the 1st quadrant Preparing to hand solder as well as oven solder remaining conductors

TF Fabrication Peer reviews of the TF flags, flag boxes, and hub assembly have been completed. Receiving bids for fabrication with expected deliveries of mid Aug (hub), early Sept (flag boxes), and late Sept (flags). Fit-up/construction of the upper hub assembly and fit-up of the lower hub assembly will begin in late October. The TF inner bundle will be complete and ready to install in the center stack by the beginning of December. Additional time has been allotted for the refit of the flex buses. The installation should be complete and the umbrella lids in place by the end of January.

Prep for Operations Vacuum vessel pump-down is scheduled for early November Date driven by the NB bellows delivery and the need to complete bake-out before test cell activities in December and January. Pre-op testing, machine area scrubs, and the integrated system testing will begin in early February Fully instrumented, high current resting of individual prototype TF joints scheduled for August.