NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade Team Princeton Plasma Physics Laboratory NSTX Upgrade Project Office of Science.

Similar presentations


Presentation on theme: "NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade Team Princeton Plasma Physics Laboratory NSTX Upgrade Project Office of Science."— Presentation transcript:

1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade Team Princeton Plasma Physics Laboratory NSTX Upgrade Project Office of Science Review LSB B318 December 11-12, 2012 NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U Kyushu Tokai U NIFS Niigata U U Tokyo JAEA Inst for Nucl Res, Kiev Ioffe Inst TRINITI Chonbuk Natl U NFRI KAIST POSTECH Seoul Natl U ASIPP CIEMAT FOM Inst DIFFER ENEA, Frascati CEA, Cadarache IPP, Jülich IPP, Garching ASCR, Czech Rep Coll of Wm & Mary Columbia U CompX General Atomics FIU INL Johns Hopkins U LANL LLNL Lodestar MIT Lehigh U Nova Photonics Old Dominion ORNL PPPL Princeton U Purdue U SNL Think Tank, Inc. UC Davis UC Irvine UCLA UCSD U Colorado U Illinois U Maryland U Rochester U Tennessee U Tulsa U Washington U Wisconsin X Science LLC

2 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 2 Progress Since Last Review A great deal of work and accomplishments have been achieved since the last review. –TF Conductor Sub-assembly procurement is proceeding smoothly –Soldering of cooling tubes in TF conductor (Full TF Bundle) is nearly complete –Centerstack Casing fabrication is nearly complete –Coil manufacturing area for Centerstack is in full operation –Final tooling fabrication and procurement for OH is underway –OH and PF conductor has been completed –Completed testing of the Aquapour –Outer TF Coils procurement has been awarded –Inner PF coil contract requisition has been submitted –Delivery of Centerstack Assembly is scheduled for February 2014

3 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 3 General Arrangement 3 TF Flex Bus and Support Structure Centerstack Assembly Outer TF Coils Major Centerstack Components Umbrella Structure Vacuum Vessel

4 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 4 Critical Path Schedule

5 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 5 TF Conductor Assembly Major Tool and Edison Welding Institute are manufacturing the TF conductor assemblies. Initially a slow start due to the final development of the Friction Stir Welding (FSW) procedures and the necessary NDT testing, but production is now moving smoothly. 36 conductors required for the full TF bundle have been delivered Quadrant #5 conductors in January Quadrant #6 conductors in February.

6 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 6 TF Solder Operations From Solder Trials to Operations: –Solder trials were successfully completed at PPPL with assistance of a Solder Consultant –Solder operations are now moving along smoothly –29 conductors have already been soldered Materials: –Solder paste- 96.5 Sn /3.5 Ag w/ GMS based “R” flux [Glyceryl Mono-stearate, Terigitol (a detergent) and Cyclohexlamine Hydro-bromide] Solder Temperatures: –Liquidus ~221º C (430º F) –Soludus~ 246º C (475ºF) –TF solder temperature~ 270-300 degrees C to ensure wetting

7 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 7 Area Setup- TF Fabrication VPI Station

8 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 8 Safety Involvement The fabrication & assembly of the Centerstack is being performed by PPPL personnel at the laboratory. Safety is an important part of the PPPL culture Safety is incorporated in all aspects of the development program- carryover to production Industrial Hygiene (IH) has participated in the planning and setup of the coil area Job Hazard Analysis (JHA’s) are being developed for each procedure Procedures: Clearly identify safety precautions for specific operations Personnel protective equipment (PPE’s) being used Involvement of all safety groups

9 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 9 Tooling Fabrication and Procurement Inner TF Bundle- Tooling and Fabrication –Operations are moving ahead smoothly –All stations are in full operation Post solder bake √ Sandblast √ Priming and cure √ Application of turn insulation √ Install conductors in mold √ Align conductors and complete assembly of mold- In process –Awaiting lid for Quadrant mold Vacuum Pressure Impregnation of TF Quadrant- January 2013 –Full TF bundle mold has been awarded to Reno Machining- delivery in late January

10 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 10 TF Conductor Preparation Sandblasting Priming Turn Insulation Post Solder Bake

11 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 11 TF Quadrant Assembly Install conductors into mold

12 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 12 VPI Operations Developed procedures and tooling for VPI operations Trial VPI was successful

13 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 13 VPI Process Cycle

14 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 14 J.H. Chrzanowski 9/7/12 NSTX-U Center Stack Coils VPI Cycle [CTD-425] 30 24 45 75 6252 0 Coil Fill Period [Fill/soak & remove lines] Cure Time Ramp down Period Ramp up period Post Cure Time Ramp up period 15 hours 24 hours 10 hours Ramp up 6 hours @ 10 ° C / hour Ramp down 13 hours @ 10 ° C per hour Hours Temperature degrees C 10 20 30 40 60 50 70 80 90 130 100 110 140 0 120 150 160 170 10 20 30 40 60 50 70 80 90 130 100 11 0 14 0 0 120 15 0 16 0 170 Ramp up 7 hours @ 10 ° C per hour Temperature degrees C

15 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 15 Full TF Mold The full TF mold is being manufactured by Reno Machine (Conn.) – –PPPL is planning a visit in December –Scheduled for February delivery

16 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 16 Tooling Fabrication and Procurement OH Solenoid- tooling –OH copper conductor has been received –OH conductor sandblasting & priming requisition in system –Induction braze station OH braze joints- is being commissioned OH joint braze qualification program will begin in January –Tension unit & taping machines are in fabrication –OH Mold will be out for bids in January

17 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 17 OH Solenoid Winding Facility

18 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 18 OH Winding Station Tension unit being fabricated in house Taping machines complete OH winding support tooling complete Turning fixture delivered Induction braze station (Complete)

19 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 19 Rolled Aluminum Cylinder wrapped with epoxy/glass insulation represents TF Bundle Maintains true TF OD and clearance space at top and bottom Will use actual mold segments and alignment pins Tested: 1. Filling of Aquapour √ 2. Curing of Aquapour with heating blankets √ 3. Washing Out of Aquapour √ T ESTING OF A QUAPOUR FOR C ENTER S TACK F ABRICATION

20 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 20 Centerstack Casing The Centerstack Inconel casing is being manufactured by Martinez & Turek located in California. They have been making good progress –PPPL visited facility in November just prior to final welding Delivery is scheduled for December 2012

21 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 21 Centerstack Casing Upon arrival of the casing 500 Inconel studs will added to the outside surfaces (original casing shown below) 696 Tiles with diagnostics will then be mounted 3.4 5. 8

22 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 22 Plans Forward for Centerstack Components Inner TF Bundle –VPI first Quadrant- January 2013 –VPI Full Bundle- May 2013 OH Solenoid –Begin winding OH solenoid- July 2013 –VPI OH Solenoid- October 2013 Centerstack Casing –Delivery is scheduled for December 2012 Centerstack Assembly- –Final assembly will occur between November 2013 to February 2014 –Developing Assembly procedures

23 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 23 Plans Forward- continued Inner Poloidal Field Coils –Requisition has been submitted to procurement- RFQ –Delivery summer 2013 TF buss and support components –Purchase Order has been placed with Zenox Corp. (TF Flexes) –Super-nuts in procurement February 2013 –OTF Lead extensions (January procurement) Deliver completed Centerstack Assembly - February 2014 MT Torque-nut™ Flex-Bus (Cu-Cr-Zr)

24 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 24 Outer TF Coils The contract for fabricating (2) Outer TF coils was awarded to Everson- Tesla. –Soldering of the cooling tubes has started –February 2013 delivery

25 NSTX-U NSTX Upgrade Project – Office of Science Review – December 11-12, 2012 25 Conclusion The risks associated with the production of the TF conductors have been addressed (Major Tool/Edison Welding) The soldering trials have been completed and production nearly complete (Retired risk) The TF bundle manufacturing facility is in full operation –Awaiting delivery of molds and completion of procedures The R&D and procedures for VPI are complete & first VPI is scheduled for January The Aquapour trials are complete Tooling for the OH solenoid is being fabricated The OH conductor sandblast/priming contract is awaiting bids The Inconel casing is scheduled for delivery in December Contract for the OTF has been awarded Requisition for Inner PF coils is in procurement The production of the Centerstack Assembly has begin


Download ppt "NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade Team Princeton Plasma Physics Laboratory NSTX Upgrade Project Office of Science."