1 Our goals for today’s meeting  Confirm FNAL role –a complete review of all cryogenics and gas handling –  We would like an above ground review only.

Slides:



Advertisements
Similar presentations
1 Procuring a Design Project engineers perspective on starting the design process and establishing the A/E scope of work Frank C. Quigley General Engineer.
Advertisements

Safety Driven Performance 2013
PLANT DESIGN (I) Prof. Dr. Hasan farag.
Camera Cooling with Pumped Liquid Nitrogen Richard Schmitt 8/7/06.
1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
Trip Report on the visit to ICST of HIT, Harbin, China Derun Li Mike Green Steve Virostek Mike Zisman Lawrence Berkeley National Laboratory (from December.
Spectrometer Solenoid Design and Procurement Review Steve Virostek Mike Green Mike Zisman Lawrence Berkeley National Lab MICE Collaboration Meeting October.
MICE Collaboration meeting at CERN March 28 – April 1, 2004 MICE Cooling Channel --- AFC Module work group report Wing Lau – Oxford.
1 New baseline for the magnet cooling system Yury Ivanyushenkov Engineering and Instrumentation Department, Rutherford Appleton Laboratory.
March 14, 2003 MICE Absorber/Coil Integration MICE LH2 Absorber 1.Assembly 2.Safety 3.Staging 4.Instrumentation.
MC and Commissioning Preparation
Mucool cryo-design Christine Darve Fermilab/Beams Division/ Cryogenic Department 8/12/02.
PROJECT AND STUDY DRAWINGS & DIAGRAMS
Objective : To understand the fabrication, design, installation welding, inspection and testing for new construction in oil and gas industry After followed.
-P&ID- Piping & Instrument Diagram
Process Engineer’s Role in Project Management Dr Abdullah Malik.
The MICE vacuum system Presented by Mark Tucker at CM-39, 26 June 2014.
Engineering and Design Group Fermi National Accelerator Laboratory Cryogenic Department AAC Review, May , 2005 Jay Theilacker HPTFCRYOGENICS.
Given a P&ID, the learner will be able to identify the purpose of that P&ID according to their student guide. – Given a P&ID, locate the title block and.
Process Safety Management
Water System Design - The Role of O&M Staff Cheryl Capron Seattle Public Utilities.
ISO OPERATIONAL CONTROL
MTA Cryogenics: Where We Are The Work of Fermilab AD/Cryo Barry Norris, Christine Darve and a host of wonderfully talented Cryogenic Personnel John Thompson,
Fermilab requirements and recent FEA Analyses PH-DT Engineering Office, CERN 06/05/2015 Page 1 CERN, May 6th 2015.
23 rd World Gas Conference 5 – 9 June 2006 Amsterdam Full Scale Qualification Trials and Certification of the AMPLITUDE-LNG LOADING SYSTEM Phillip COX.
Helium Spill Test in LHC tunnel to define length of restricted working areas  Actual situation  Evolution  How to continue  Set-up of the spilling.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Collaboration Meeting #28 Sofia, Bulgaria.
Exhaust to atmosphere G1 V1 V2 V3 LN2 Storage Vessel 150 l Dewar Cryostat Exhaust to atmosphere Nitrogen or helium gas bottle LN2 Circuit for MIT Test,
New compressor station Second stage of nitrogen system (N2 refrigerator, cryogenic tank, pipe lines) Cryogenic equipment required to run NICA Third stage.
LH2 Safety Issues for MICE 1.O2/LH2 separation 2.No Ignition sources near LH2 3.Adequate ventilation 4.Affects: Windows: absorbers and vacuum Primary and.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Progress on Hydrogen R&D System
Johan Bremer, 22th-26th September 2008 Cryogenics Operations 2008, CERN, Geneva, Switzerland 1 CRYOGENICS OPERATIONS 2008 Organized by CERN Safety aspects.
To TT10 Nitrogen or helium gas LN2 Storage vessel buffer storage vessel G1G2 Magnet cryostat VALVE BOX Schematic diagram of the cryogenic system.
HL-LHC Crab Cavity Review Debriefing Comments from LARP June 30, 2014.
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
A JSJ Business APQP/PSO. A JSJ Business Purpose: To understand key concepts of the GHSP APQP and PSO process by reviewing the.
Linda Bagby - SBN Program Electrical Coordinator ICARUS Electronics Meeting 27 January 2016 SBN Program Operational Readiness Clearance.
Linda Bagby - SBN Program Electrical Coordinator T600 Installation 8 February 2016 SBN Program Operational Readiness Clearance.
Installation of the T600 at Fermilab CSN2, September 22,
Cryogenics Fabrication Plans & Constraints David Montanari (on behalf of the CERN Neutrino Cryogenic Group) ProtoDUNEs Meeting Feb 23, 2016.
SPHENIX MECHANICAL D. Lynch August 21, /15/2014sPHENIX Mechanical Design.
PIP-II Cryogenics Arkadiy Klebaner and Jay Theilacker PIP-II Collaboration Meeting 9 November 2015.
C. Darve / Technical Board – December 13 th, 2012Preliminary pressure vessel code requirements Preliminary pressure vessel code requirements Technical.
ESS Cryomodule Status Meeting – Elements of Safety | | Christine Darve Elements of Safety Applicable to the ESS 2013 January, 9 th Christine.
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
Failure Modes, Effects and Criticality Analysis
Process Safety Management Soft Skills Programme Nexus Alliance Ltd.
V Thermo-siphon Workshop Test protocol Jan Godlewski PH/DT-PO On behalf of thermo-siphon working group
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
Cryomodule Safety Approvals Jay Theilacker LCLS-II Production Cryomodule Final Design Review May 12-14, 2015.
WBS 1-7 System Assembly & Installation John Voirin August 10-11, 2011.
Crab Cavity Technical Coordination meeting:
Six Sigma Greenbelt Training
Accelerator Readiness Review October 31, 2006
Magnet cryogenic system update.
2K Cold Box PDR Introduction
IT-4189 Supply and installation of a cryogenic distribution system
Proximity Cryogenics P&IDs Meeting
Proximity Cryogenics P&IDs meeting
Welcome! Drafting 2323: Pipe Drafting
David Montanari / Johan Bremer Jun 11, 2015 Rev. 1
LN2 Circuit for MIT Test, September 2005
Documentation Chris Scanlon and Ritendra Bhattacharya
Overarching Commissioning Plan
Piping and Instrumentation for Process Industries
Schematic diagram of the cryogenic system
as a prototype for Super c-tau factory
Columbia Astrophysics Laboratory
Presentation transcript:

1 Our goals for today’s meeting  Confirm FNAL role –a complete review of all cryogenics and gas handling –  We would like an above ground review only in order to start work  Review the documentation LUX has assembled based on the Theilacker memo– identify any missing pieces  Confirm committee members know how to access review documentation on LUX web site  Establish a timeline for completion of the review – we have a tentative date for a readiness review  Once the review is complete, it should constitute a signoff element for the overall LUX readiness review Lawrence Livermore National Laboratory

2

3 Starting point for the cryogenics review Lawrence Livermore National Laboratory

Review elements from Theilacker memo 1. piping & instrumentation diagram (P&ID) LN system P&IDs xenon system P&IDs 2. valve and instrumentation list 3. list of plausible failure modes 4. Calculate maximum flow rates for each item in the failure mode list 5. ODH analysis per FESHM 5064 based on items 3 and engineering notes for any pressure vessels per FESHM engineering notes for pressure piping systems per FESHM a Failure Modes and Effect Analysis (FMEA). 9. a What-If Analysis. 10. any required written cryogenic LOTO procedures. 11. any required written startup procedures (verification checklists, etc.). 12. any required written operational or maintenance procedures.

5 1. P&ID Lawrence Livermore National Laboratory LN system P&IDsLN system schematic contained in LN ODH document. P&ID will be generated shortly xenon system P&IDsFull xenon system schematic Detector subsystem Circulation subsystem storage subsystem

6 2 Valve and Instrumentation List Lawrence Livermore National Laboratory All valves and instrumentation are numbered according to a standard numbering scheme and tabulated at the link below

7 3. Plausible failure modes Lawrence Livermore National Laboratory Failure modes are in the ODH documents and in the FMEA

8 4. Calculate maximum flow rates for each item in the failure mode list Lawrence Livermore National Laboratory Maximum flow rates are in the ODH documents and in the FMEA

9 5. Prepare an ODH analysis per FESHM 5064 based on items 3 and 4. Lawrence Livermore National Laboratory ODH analyses have been made available to this committee for xenon and nitrogen – updates as necessary on LUX web Near term the underground OH analysis by Alonso is not needed

10 6.,7. Prepare engineering notes for any pressure vessels and piping systems per FESHM Lawrence Livermore National Laboratory Vessel: cryostat vessel requirements, drawings and manufacturer certifications are on the the LUX Web Piping: Most LUX piping falls below the FESHM standard for safety notes – for the parts that do need an engineering note we have assembled partial documentation

11 8. Prepare a Failure Modes and Effect Analysis (FMEA). 9. Prepare a What-If Analysis. Lawrence Livermore National Laboratory Draft FMEA including What If analysis on TWiki uxSafety/CryogenicSystems/LUXFMEACryogeni cs_r3.pdf Guidance: What is a What If Analysis

Prepare any required written cryogenic LOTO procedures. 11. Prepare any required written startup procedures (verification checklists, etc.). 12. Prepare any required written operational or maintenance procedures. draft gas handling startup, operations and maintenance procedure Mature draft, needs updating draft cryogen handling startup operations and maintenance procedure early draft, needs updating LOTO procedure - not yet determined to be necessary Lawrence Livermore National Laboratory

13 Is anything missing ?  Interim review of test using a ‘small amount’ of nitrogen to cool the detector - no xenon in this test  Recap Theilacker memo for interim review – including:  Mike D.: Describe actual configuration - one dewar connected to thermosyphon system.  Mike D.: Create P&ID for this and for full system  Adam Bradley: Add mechanical drawings for thermosyphon system –  Mike D.: create procedures for LN supply of the thermosyphon dewar  Adam Bradley: Engineering note for thermosyphon dewar with associated relief valves  Adam Bradley: procedure for running thermosyphons  List maximum pressures for the Lawrence Livermore National Laboratory