Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 30/08/2013LSC - S. Baird, M. Bernardini1.

Slides:



Advertisements
Similar presentations
LS1 Status Report – 116 th LHCC Frédérick Bordry 4 th December 2013.
Advertisements

CURRENT STATUS OF CV INSTALLATIONS, WORKS DURING LS1 AND PROBLEMS ENCOUNTERED DURING START-UP NORTH AREA Bill Bannister / Jani Lehtinen EATM – 7 th October.
QRL Leak Tests the story so far………. Paul Cruikshank on behalf of TE-VSC colleagues & AL4030 Consortium (S133) 1 Paul Cruikshank TE/VSC - QRL Leak Tests.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
Beam Vacuum Quality Control Outline  VSC consolidation  VSC support  Organization  Status Cédric Garion on behalf of TE-VSC Cédric Garion TE/VSC Beam.
LS1 Injectors K. Foraz on behalf of N. Gilbert, S. Mataguez, D. Hay & D. McFarlane LSC 24 th May /05/2013LSC – EN-MEF-OSS1.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010.
11/4/2005OLAV 1 Workshop CERNW. Maan Fast Vacuum Valves at CERN -Introduction to fast valves -History of fast valves in use/used at CERN -LEP fast shutters.
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
7 November 2003 Status of CNGS NBI presented by K. Elsener 1 Status of CNGS Konrad Elsener CERN – Accelerators+Beams Division.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
12th February 2010David Mcfarlane EN-MEF-ABA1. History of Booster The accelerator was built in The Proton Synchrotron Booster is the first, in the.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
Special interventions Status of production and QC Nicolas Bourcey TE-MSC-MDT Fourth LHC Splice Review November 2013.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
4 December 2007Sylvain Weisz - LEMIC1 Status of LHC installation.
Planning of Injector Activities for Linac4-to-PSB Connection and LS2 Thanks to all the valuable input from the LIU project leaders and LIU work- package.
Injectors & LHC report K. Foraz on behalf of OSS members 01/11/13LSC - EN-MEF-OSS1.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
Beam Instrumentation during LS1 Ray Veness on behalf of the BE/BI group.
Injectors & LHC report K. Foraz on behalf of OSS members 01/08/2013LSC - K. Foraz1.
D. Delikaris, TE-CRG, LSC 25th Meeting Page 2 October 18 th, 2013 LS1 Committee (LSC)- 25 th Meeting D. Delikaris, TE-CRG Cryogenics activities.
TE-CRG Activities D. Delikaris, TE-CRG.
Proposed integration of cryo BLMs in LHC during LS1 V.Parma, CERN, TE-MSC With contributions/input from: M.Sapinski (BE-BI) Th.Renaglia (EN-MME) N.Bourcey.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
LHC schedule status K. Foraz EN-MEF 12/04/2013LSC - K. Foraz1.
PSB HW Commissioning Meeting 8 February 2016 A. Akroh, B. Mikulec.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
R2E relocation & shielding activities: status report Anne Laure Perrot EN/MEF- LE On behalf of the R2E coordination team LS1 Committee – meeting #48, 27.
Cost and schedule for ELENA Beam Transfer Systems W. Bartmann, J. Borburgh, E. Carlier, L. Ducimetiere, T. Fowler, M. Hourican, R. Ostojic, L. Sermeus.
Warm Magnets - LS1 Feedback J. Bauche, on behalf of the TE-MSC-MNC Team.
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
L. Tavian, TE/CRG, LSC Page 2 February 21 th, 2014 LS1 Committee (LSC) L. Tavian TE-CRG.
Report Technical Director Storage-Ring-Installation Completed
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
K. Foraz on behalf of OSS members
ABT-EC EYETS Activities 2nd reports
BE-BI Activities and Status: LHC and Injectors
TE-MSC activities in SPS during LS2
SMACC Tenth report [15 min] 13/09/2013
EYETS David Hay EN-OSS.
ELENA installation and commissioning status
BA6 – crab cavity activities in EYETS
K. Foraz on behalf of OSS members
LIU – EVM status and next steps
AD consolidation activities in LS2
SPS - EYETS 2016/17 Vacuum systems planning
on behalf of the RF group
Update of cryogenic activities
Long Shutdown for the LHC: Vacuum Beam Pipes
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS EN-CV Planning LS (initial draft)
SPS Planning for the EYETS Meeting 8 (07/12/2016)
SPS Planning for the EYETS Meeting 9 (14/12/2016)
TE-MSC activities in SPS during YETS
K. Foraz on behalf of OSS members
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
LHC installation status
East Hall under construction
Linac4 Connection Broken Line 07/08/19
Presentation transcript:

Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 30/08/2013LSC - S. Baird, M. Bernardini1

AD TE/EPC : removal old power supplies completed in the AD hall. TE/VSC : – UHM3107 and UVM3207 tanks : seals installation next week. – Ion pump change in still progress until early September. TE/MSC : BHN06: new CERN visit to manufacturer for first coil test this week. Waiting for feedback before final decision. An ultimate planning has been prepared, with delivery of the coils mid of October. In case of additional delay, the plan-B would consist in repairing BHN23 or 24. TE/ABT : – Provisional gasket installed for leak test in the workshop (TE/VSC). – Delay for the 2 KFI tanks reinstallation, fixed on 18/10 (compatible with the revised bake-out planning). BE/BI + TE/VSC – Replacement of MTV screen re-scheduled in week 39 and 40. GS/ASE : – Equipment for the new access point being delivered in the AD-hall. – A decision has been recently taken to first install a platform and consequently raise the access point by about 10 cm. So some delay in the planning, but not critical. Girder line 7000: manufacturing of the first 3 vacuum chamber in progress at CERN 30/08/2013 LSC - S. Baird, M. Bernardini 2 Power supplies removed in AD hall Access devices delivered

LEIR BE/BI: – Degasing tests in progress for the MTV screens (by TE/VSC). – Intervention on the 2 BIPM (Beam Ionisation Profile Monitor) on vacuum sector 5 still in preparation (waiting for new MCP cards). TE/MSC : – Repair of DHV12 encounters some difficulties, but could be fixed. – Installation back in the machine on October the 1 st is still expected. GS/ASE : – New access point being tested, on service week /08/2013LSC - S. Baird, M. Bernardini3 Vertical BIPM

PS Done – PS PSS Safety and Access System Installation : Doors from buildings 352 and 353 to the PS tunnel are now operational In Progress – CV Consolidation program: racks delivered, cabling and piping progressing well – The Septum 16 External Shielding program: work of 29 piles installations is on-going – EN-EL cabling campaign in progress – General equipment maintenance is going on: BI, RF cavities 10 MHz, beam stoppers (EN-STI) – Outside PS tunnel, chilled water campaign: Asbestos removal Building 355 Forecast – Access system installation 30/08/2013LSC - S. Baird, M. Bernardini4 Valves installation on chilled water New PS access system Installation of piles

PSB In progress – PSB beam dump replacement project on schedule. The old beam dump has been successfully removed and transported to the ISR radioactive storage facility. Careful extraction of the 5 shielding blocks successfully completed. Restricted access to the PSB Machine during the extraction period. – CV consolidation and maintenance of CV, kickers, Septa, vacuum beam instrumentation, Magnet and Beam stopper, cabling campaign. – Replacement of PSB ring 32A electrical power sockets. – Installation of new cable trays under the false floor. New issue about the new installed BLM cables: non conformities outlined during the test campaign. Solution under study. Completed. – Integration testing of the new PPS (access) system Forecast – Installation of the public address cables & infrastructure – Replacement of the BI.SMH under preparation. Work and dose planning under preparation. 28/08/2013LSC - S. Baird5

SPS BA1 Irradiated cable campaign – The removal of the 2 shielding walls in LSS1 started on Monday of this week. Complete by the end of next week (as planned) – Installation of the new fibre optics systems will start on September 9 th A big thank you to all teams involved! *Identification of the cables has to be done during the coming month. If they are not identified by the equipment owners, then they will be removed and not replaced! TT10 Civil Engineering works The end plates for the new support beams started to arrive Installation of Beams is still scheduled in early September. 30/08/2013LSC - S. Baird, M. Bernardini6 Other works – Cabling works – Installation of the Fibre Optics systems in BA6 have started. – Replacing of the main isolating valves on the cooling water ring-main is going on. Removal shielding wall

LHC - P1  P2 R2E – Pt1: – Left: Cabling progressing well, 3 weeks ahead of schedule. Piping: 1 more week needed. – Right: Piping: 1 week delay, will be recovered LSS1: – 13kA and 600A upgrade completed – Survey HLS maintenance in progress – DFBX: consolidation of current leads in progress – Survey smoothing is finishing Arc 12: – UPS replacement in RE 18 and 22, transport ok! – Cryo-magnets reconnection in progress – SMACC: IC W openings finalised M openings started (2 wks ahead of schedule) 30/08/2013LSC - S. Baird, M. Bernardini7 R2E_Piping in UJ16

LHC - P2  P3 Point 2 – Cooling tower maintenance finished and SU maintenance will start soon – Cryogenic maintenance in progress LSS2 – Cable campaign completed – 13kA and 600A upgrade completed Arc 23 – Preparation for the modification of the HRL valves (UJ32) – Cryogenics and vacuum consolidation in progress – Magnet reconnection in progress – DN200: 60% installed – UPS replacement will start soon LSS3 – Installation of the cable trays ongoing – DFBA: Intervention on the Thermoswitch ongoing – 13kA and 600A upgrade completed 30/08/2013LSC - S. Baird, M. Bernardini8 DN 200 Installation in 23

LHC - P3  P4 Arc 34 – Magnet replacement finished – Vacuum consolidation activities in progress – VSC beam vacuum blowing and endoscopy activities finished  < 1 debris/ magnet – CRG services modules consolidation in progress – SMACC: W bellows openings start in 2 weeks time, due to fast arrival M openings 30/08/2013LSC - S. Baird, M. Bernardini9 Last Quadrupole installed Beam Vacuum Debris - Summary table Courtesy V. Baglin and J. Finelle

LHC – P4  P5 LSS4 & P4 – Flexwell and control cabling campaign completed – Water cooled cables consolidation in progress – RF maintenance and upgrade – New cooling tower installation will start soon. Arc 45 – All magnets replaced! – QRL: QRL X ray campaign finished The new deformed, not leaky compensator, on QRL header C being dismounted – VSC consolidation in progress 30/08/2013LSC - S. Baird, M. Bernardini10

LHC – P5  P6 LSS5: – Modification of the cabling for TOTEM ongoing – Completion of the DFBAJ consolidation – 13kA upgrade completed R2E – P5 – Drilling: activity completed – Civil engineering: 1w ahead of schedule – UPS dismounting in progress Arc 56 – 2 nd Ball test realized – QRL Xray campaign finished: Compensator replacement foreseen in 2 weeks time – SMACC 11/14 vacuum subsectors consolidation completed; Non conformities still opened VSC leak test in progress W closure started LSS6 & P6 – Maintenance & Upgrade of chilled water in progress – MKD-MKB tests on beam1 and upgrade on beam2 – Cabling campaign ongoing – 3 TCDQ installed – 13kA upgrade ongoing 30/08/2013LSC - S. Baird, M. Bernardini11 First W closure M lines VSC test

LHC – P6  P7 Arc 67 – QRL X ray campaign in progress – SMACC in progress: Splices consolidation almost completed Insulation boxes being mounted Welding M in progress Diodes consolidation in progress (60% achieved) W closure will start soon R2E – P7: – Cable trays installed and rack installation done – Fireproof racks some minor delay – UPS dismounting ahead of schedule – Smoke detector installation in progress LSS7 – Consolidation of the DFBA ongoing – 13kA & 600A upgrade ongoing 30/08/2013LSC - S. Baird, M. Bernardini12 R2E_Detection Pipe installation

LHC - P7  P1 Arc 78 – Splices consolidation started – DFBAN and DFBAO ready for consolidation LSS8 &P8 – UPS replacement in progress – Installation of the 1 st MKI within 3 weeks – 13kA and 600A upgrade completed R2E - P8 – UPS waiting for tests – Ventilation control scheduled in October – Cryo and cabling activities ahead of schedule Arc 81 -DFBAP ready for consolidation -M opening finished 3 wks ahead of schedule -VSC beam vacuum non conformity on Nested Bellow 20L1- V2, being tested -QRL compensator  first replacement, beginning Sept 30/08/2013LSC - S. Baird, M. Bernardini13 Nested bellow

General infrastructures 30/08/2013LSC - S. Baird, M. Bernardini14 A maintenance of the 3G services (UMTS) in LHC will be performed on the 5 th and 6 th of September - The 3G services will be migrated to the new infrastructure deployed by Sunrise. - The download/upload capacity will be increased (basically doubled). The preparatory works to introduce 3G services in the injector complex are on-going (no impact mobile services) Project of technical network renewal in progress

Overall progress Injectors: on schedule, but to follow – AD – BHN06 coil manufacturing LHC – to follow – R2E - On schedule – SMACC – some delay – Cabling campaign – On schedule – Consolidation of the Water Cooled Cables – On schedule – Beam vacuum group activities underground in stand by waiting for equipment installation – to follow 30/08/2013LSC - S. Baird, M. Bernardini15

LHC Overall Schedule – broken line 30/08/2013LSC - S. Baird, M. Bernardini16