1 SPS - EYETS 2016/17 Vacuum systems planning
28/09/2016 TE-VSC SPS planning EYETS2016/17

2 SPS ring general X3101 Magnet exchange campaign
Vacuum support Dates to be determined by TE-MSC after magnet survey General Vacuum maintenance Up to 100 Ion Pump’s to replace, gauge replacements Sector 440 (17 VPIAs) Sector 460 (7 VPIAS (1X QF)) Sector 510 (12 VPIAs (1X QD,MBB) Sectorisation; 2x VPIAs to be install the VVR configuration (18 VPIAs) magnet exchange (~ 15 VPIA’s) Leak detections (TI2 & ACTD cavity#4) Transparent Ion pump grounding Complete ion pump safety grounding of full SPS ring Arc re-sectorisation Installation of up to 9 sector valves, roughing valves and gauges. ECR – second version about to be circulated for approval. X3101 28/09/2016 TE-VSC SPS planning EYETS2016/17

3 BA1 TIDVG_11892 exchange MKP04 Vacuum leak developed during operation
Surface preparation works (+10 days) - to be included in planning Vacuum support, including bake-out in tunnel (~10 days) Replacement of 2x ion pumps Dates to be co-ordinated by EN-STI MKP04 Tank exchange Surface preparation works (+10 days) Vacuum support Dates to be co-ordinated by TE-ABT TIDVG – bake-out in tunnel with water heater MKP04 – to test bake-out in 867 28/09/2016 TE-VSC SPS planning EYETS2016/17

4 BA4 MKE in period 416 MSE in period 418 1 or 2 tanks to be confirmed?
Vacuum support Dates to be co-ordinated by TE-ABT MSE in period 418 Exchange of 6x MSE tanks Surface preparation works (status?) 28/09/2016 TE-VSC SPS planning EYETS2016/17

5 aC Coating BA4 & BA5 activities in EYETS
Start of the Carbon Coating & flange impedance reduction campaign: Coat 10% of the drift tubes (intervention in LSS4); QF up to QF with corresponding SSS; MBB 50530, 50550, 50470, 50490, 50730, 50750, and 50690 QD and with SSS; DS LSS ARC BA4 BA5 existing aC SSS QF works MBB works Drift tube works 9 SSS QF to transport 2 SSS QD to transport 2 QD to transport 10 drifts to transport Vacuum sector valves Extraction septum All magnet removal (& return) via BA3 Support from EN-HE, TE-MSC, EN-SU 28/09/2016 TE-VSC SPS planning EYETS2016/17

6 aC Coating BA4 & BA5 MBB aC coating works - sextant 4-5
16 dipoles & 5 Quads ex-situ aC coated in LS1 Only MBB type dipoles need to be coated following LIU Scrubbing Review EYETS – trial of in-situ aC coating of 8 MBB (ECR: ) Remove QD and sss QD in 2 locations in arc 5- (transport via BA3) Install aC coating equipment in 6m space created and coat 2 x MBB to left and right. aC coat QD and sss QD ex-situ. Further MBB aC coating works in YETS, LS2, LS3. MBB MBA QD + sssQD via BA3 QD Coating train is inserted into MBB chamber 28/09/2016 TE-VSC SPS planning EYETS2016/17

7 Coating train inserted into QF chamber
aC Coating BA4 & BA5 QF coating & impedance reduction works - sextant 4-5 QF and sss QF chambers need to be aC coated following LIU Scrubbing Review sss QF chambers need impedance reduction shielding at circular bellows & flanges for LIU. EYETS – trial of aC coating and impedance reduction at 9 QF & sss QF ECR and Remove sss QF in 9 locations in arc 4+ (transport via BA3) Install aC coating equipment in 2.8 m space and coat QF in-situ. aC coat plus IR shielding on 9 sss QF ex-situ in 867. Complete QF aC coating & IR works in YETS & LS2. Coating train inserted into QF chamber 28/09/2016 TE-VSC SPS planning EYETS2016/17

8 aC Coating BA4 & BA5 Draft Planning Activities fit in 11 week time window starting 9th January 2017 Earlier start (magnet transport) depending on overall EYETS planning. Magnet disconnection and venting will start week 50, 2016. 28/09/2016 TE-VSC SPS planning EYETS2016/17

9 BA5 BWSRA_51740 BSHV_51659 FBCT 51930 Leak on blank flange
Replace seal Transparent, but dates to be confirmed from BA5 planning BSHV_51659 Removal of scraper 2x new vacuum chambers Transparent, but dates to be confirmed with EN-STI FBCT 51930 Installation of new chambers and support Vacuum support Dates to be confirmed with BE-BI BWSRA – wire scanner WCT – fast current transformer 28/09/2016 TE-VSC SPS planning EYETS2016/17

10 BA6 Sectorisation for Crab Cavities
Preparation work ready for Crab Cavity installation YETS2017/18 Open vacuum sectors 632 (pos.616) & 634 (pos.617); reinstall VVFA61695 and VVSB61757 ASAP to start pumpdown of upstream and down stream ECR: Transparent, but dates to be confirmed with BE-RF Moving of fast valve VVFA from to 61659 Installation of new sector valve Installation of new vacuum chambers and supports Downstream MKE Upstream TPSG 28/09/2016 TE-VSC SPS planning EYETS2016/17

11 Component Testing Please inform TE-VSC regarding any components to be installed in the vacuum systems as soon as possible, after ECR approval. All the components need to be submitted for acceptance test to the VSC-BVO section before 01/12/2016. If any component that is due to be installed in the machine during the EYETS is submitted for vacuum acceptance test after this date, the activity has to be taken into account in the general installation planning. In this case our resources will be divided between the machine activities and the lab activities, with possible delays on the installation. 28/09/2016 TE-VSC SPS planning EYETS2016/17

12 Transfer line access Requests for removal of access chambers to the SPS transfer lines (to pass with large equipment, h<90cm)? Access to TT10 from BA1 Access to TT20 from BA2 Access to TI8 from BA6 28/09/2016 TE-VSC SPS planning EYETS2016/17

13 COLDEX EYETS 2016-17 (in order of priority) VACUUM
Installation of a new Beam Screen with LESS laser treatment SPS beam vacuum (sect. 430) + COLDEX (sect. 431) venting and opening Not before Feb/March 2017 (follows fabrication and treatment planning) WAMPAC5 calorimeters installation (a-C and Cu or LESS) replace the WAMPAC4 installed in COLDEX DN100 SS left/right transitions (sector 431) insertion of new liners and preparation is done in surface (b. 867) New instrumentation on COLDEX chimney full coverage of the to 100 mbar measurement range → installation of two gauges DIC/DIF sent On-site fix of malfunctioning experimental equipment TT903 and TT905 sensors (degraded); BS electrode (bad insulation) reduces to TT905 fix if a new BS is installed Consolidation + re-fill of Gas Injection System 1 gauge probably broken (radiation) → installation of PI/PE gauges change of N2 with CH4 (to be confirmed), re-fill of other gases only if required bake-out required if system is vented

14 COLDEX EYETS 2016-17 (in order of priority) CRYOGENICS
Replacement of malfunctioning experimental equipment 1 flowmeter broken (radiation) → replacement with spare General maintenance and check-out OTHERS Installation of Beam Loss Monitors (BLM) follows HL-LHC request to have beam loss indication at COLDEX in collaboration with BE/BI basic setup: one monitor upstream, one on COLDEX ECR required? DIC/DIF sent Installation of protections on sect. 430/431 ground supports follows new design by EN/MME to be validated in a second version of ECR SPS-HJP-EC

15 Temporary storage areas
COLDEX EYETS No space consuming activities implying permanent obstruction of tunnel passage area Some occupancy is foreseen only during BS removal/insertion A temporary underground storage area is requested for storing equipment dismounted, e.g. LSS4 by-pass Y-chambers (2) Sector 430 beam pipe (1) COLDEX cryostat internals Venting equipment, leak detectors, pumping groups etc. Required SPS machine interfacing and coordination AUG test, Access test dates Cabling campaign planning Lift maintenance dates BA4 cooling water stop/restart dates Temporary storage areas info available through EN/ACE