N-1-1 Contingency Analysis & Relay Protection 4 th BTA Presentation Bob Smith Manager Transmission Planning June 6, 2006.

Slides:



Advertisements
Similar presentations
Sequence Data, Power Flow & Transient Stability (PF & TS) MSRATF - July 10, 2013 Joe Seabrook.
Advertisements

1 MSRATF Update to TSS (Modeling SPS and RAS Ad Hoc Task Force) Scope of Work Approval January 25, 2013 Joe Seabrook Puget Sound Energy.
WECC Standards Committee Joint Session
1 MSRATF Update to TSS (Modeling SPS and RAS Ad Hoc Task Force) May 15, 2013 Joe Seabrook Puget Sound Energy.
Doug Tucker Associate Staff Engineer TRD/TADS update and Future reporting.
TRANSMISSION & INTERCONNECTION PLANNING T&D BUSINESS UNIT 1 Distance Relay Specification WECC TSS January 23,2014 Amos Ang.
Goshen Area Bus Reconfiguration
 2005 Pinnacle West Capital Corporation Palo Verde Hub Participant Meeting May 27, 2005 Arizona Public Service Company Tom Glock – Manager Power Operations.
April 15 and May 15, 2003 ERCOT System Disturbances ERCOT TAC Meeting June 4, 2003.
1 U.S. Energy Information Administration, Annual Energy Review All energy input US average = 90.3 MWh per person, per year. Corresponds to 10.3 kW.
Team BUSS Backup Storage Source. Team BUSS Idaho Power Company Backup Storage Source Project Title Extra High Voltage (EHV) Station Second DC Storage.
TRANSMISSION & INTERCONNECTION PLANNING T&D BUSINESS UNIT 1 Current Differential Relay Specification WECC TSS August 20,2014 Amos Ang.
WECC and NERC Protection Criteria and Standards
1 Blackout 2003 See:
August 14 th NE Blackout and Common Roots of Blackouts Damir Novosel, PhD President KEMA Inc., T&D Consulting BLACKOUT AMERICANO E ITALIANO:
1 Local Area Planning Update to TRANSAC – September 18, 2014.
Averting Disaster - Grid Reliability Issues and Standards National Energy Restructuring Conference April 1, 2004 Washington, DC.
Houston Area Dynamic Reactive Project March 11,
Recommendations from 2011 Southwest Outage Heather Polzin, FERC Office of Enforcement Dave Nevius, Senior Vice President, NERC Member Representatives Committee.
Adaptive Protection of Distribution Feeders Alexander Apostolov, Benton Vandiver.
1 Arizona Corporation Commission BTA Workshop Presenter: Steven Cobb May 23, 2008.
December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.
VISUALIZATION WHY WE NEED SYNCHROPHASOR TECHNOLOGY IN OPERATIONS John Ballance – EPG Presented to ERCOT Phasor Technology Workshop – November 16, 2012.
TOS Operating Committee Report Al Badella Technical Operations Subcommittee Chair July 14th, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.
Lyndonville Electric Department Feasibility Analysis Review December 2,
NERC Event Analysis Update Member Representatives Committee Meeting October 28, 2008 Robert W. Cummings NERC Director of Event Analysis & Information Exchange.
Distribution Planning Use of SMART Distribution Automation Control System (DACS) Presented by: Ed Briggs, P.E. Created by: Ed Briggs & Greg Wickliffe
Cigre B5 – 06 Working Group Presentation Protection and Control Asset Program Management John Robertson March 25, 2008.
© Property of ERCOT /06/20041 Overview of SPS in ERCOT February 5, 2004.
ERCOT PUBLIC 4/21/ RTP: Cascade Analysis April 21, 2015.
Lecture 22 Unbalanced Faults and Power System Protection Professor Tom Overbye Department of Electrical and Computer Engineering ECE 476 POWER SYSTEM ANALYSIS.
Reliability Must-Run Analysis 2006 – th BTA Presentation Bob Smith Manager Transmission Planning June 6, 2006.
CIP Version 4 The Basics. CIP Version 4- Background Centers around expanded criteria for Critical Assets – FERC thought Risk Based Methodologies used.
Lecture 22 Unbalanced Faults and Power System Protection Professor Tom Overbye Department of Electrical and Computer Engineering ECE 476 POWER SYSTEM ANALYSIS.
ECE 476 Power System Analysis Lecture 22: System Protection, Transient Stability Prof. Tom Overbye Dept. of Electrical and Computer Engineering University.
Announcements Read Chapters 10 and 11
1 Distributed Generation and Power Quality-Continued.
APS Ten-Year Plans th BTA Presentation
Cheng-Ting Hsu Presenter: Cheng-Ting Hsu Cogeneration System Design for a High-Tech Science-Based Industrial Park Department of Electrical Engineering.
How the Transmission System Works Really William F. Reinke.
NERC Lessons Learned Summary LLs Published in September 2015.
Experiences in Managing Settings Bryan J Gwyn National Grid USA.
Evolution and Prospects of Relay Protection and Automation Systems Evolution and Prospects of Relay Protection and Automation Systems Moderator: Janez.
OPSTF – Issue 7 Long-term unavailability of autotransformers.
THE POWER OF POSSIBILITY AESO current limits for Alberta-BC transfers Jeff Palermo – KEMA/AESO.
ECE 498HZ: Power Distribution System Analysis
April 7, 2015 Washington, D.C. Area Low-Voltage Event Operations Training Seminar 2016 Erik Johnson System Operations Training (ERCOT)
Power System Protective Relaying-Part One
STUDY OF ELEMENTS OF A 220/132/33KV SUBSTATION
Project WECC-0100 Standards Briefing WECC-0100 SDT April 7, 2016 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.
Protection Relay Modeling for Transient Stability Simulation 10/26/2016 CJ Jing, David Franklin, Kevin Moran.
Local Area Planning Update to TRANSAC – September 15, 2016
Compliance Report to ERCOT TAC February 2007
What is an Operation and Misoperation
HARRY ALLEN TRANSFORMER REMEDIAL ACTION SCHEME (RAS)
Removal of Fraser RAS from RAS Databse
Project WECC-0100 Update Load Modeling Task Force
Pacific Power Seismic Preparedness Update
NERC OC Update Greg Park, NWPP (In place of Rich Hydzik)
Local Area Planning Update to TRANSAC – September 26, 2018
Specifications Updates and Approval
Protection Relay Modeling for Transient Stability Simulation 10/26/2016 CJ Jing, David Franklin, Kevin Moran.
Yale Runback Local Area Protection Scheme
Review of Distribution Network Protection
What is an Operation and Misoperation
HARRY ALLEN TRANSFORMER REMEDIAL ACTION SCHEME (RAS)
Removal of Fraser RAS from RAS Databse
NERC OC Update Greg Park, NWPP (In place of Rich Hydzik)
Project WECC-0100 Update Load Modeling Task Force
WECC – NERC Standards Update
Presentation transcript:

N-1-1 Contingency Analysis & Relay Protection 4 th BTA Presentation Bob Smith Manager Transmission Planning June 6, 2006

4th BTA2 Contingency Planning (N-1-1) Westwing Transformer #4 Out of Service Oct 31, May 1st, 2006 West Phoenix – Lincoln St. 230kV Out Of Service March 6 – April 15, 2006

Relay Protection  APS performs relay coordination checks on all relaying schemes both internal to our substations and between substations in our system  Working with Protective Relay Depts in connecting utilities, APS performs relay coordination checks on all intertie points  All additions and changes made on the APS system are checked to make sure that relay coordination exists throughout the APS system and with connecting utilities

Relay Protection  APS’ transmission line relaying schemes are designed in a way that enables faults internal to a line to be tripped instantaneously. relaying schemes on adjacent lines will trip for that same fault with a time delay which provides the needed coordination to trip only those breakers that need to be tripped to isolate the fault  APS is fully compliant with all applicable WECC, FERC, & NERC standards that apply to relay protection and coordination.  There has been an increased emphasis on these standards since the recent East Coast Blackout

Relay Protection  Since the recent WW events, APS has been adding totally redundant relaying schemes on all 230kV and above substations and lines  This will eliminate all known single point of failure to keep cascading events from happening in the future  So far, we have added redundant schemes at our WW, PP, NG, NV, MK, YV, FC, CH, DV, & RC