AIDA 1 20 Heatsink units, locating pins and washers now on site. Status of Electronics Module.

Slides:



Advertisements
Similar presentations
VELO Status at Liverpool T. Bowcock. Prototype Module(1) Mechanical Design Several different options Reduce complexity Dead reckoning.
Advertisements

1 Liverpool Production Status Week of 23 February 2007.
Status of Sensor and Hybrid Production LHCb Zurich Week T. Bowcock.
1 Liverpool Production Status Week of 9 February 2007.
Source Driver Status CMS Week November 2007 P. Debbins University of Iowa.
Xenon Detector Status Liquid Xenon Group. 1 Outline Cryostat construction –Honeycomb panel test at Pisa –Assembly –Cryogenic test at SIMIC –Leak test.
MICRO VERTEX DETECTOR ZEUS experiment at DESY (HAMBURG) PROJECT SPECIFICATIONS : Design and production of a silicon Micro Vertex Detector (MVD) for the.
Collaboration meeting, RAL, 4 th – 7th November 2009 Andrew Moss ASTeC Collaboration meeting, RAL, 10 th – 13 th november 2009 MICE RF Amplifier Status.
Development of new Mice Target Stator. (or show and tell) Rutherford Lab 13 th December 2011.
GLAST Calorimeter LAT F2F Meeting 17 Mar 2005 Naval Research Lab Washington DC W Neil Johnson 1 Subsystem Mgrs F2F Meeting Calorimeter Subsystem 17 Mar.
Slide 1UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE UCSB 4-Hybrid Thermal Test System Status 4 August 2003 Sam Burke UCSB HEP Group.
Basic Ag Mechanics October 3, 2006.
STARLight PDR 3 Oct ‘01 G.1.1 Rashid STARLight STARLight Thermal Tahir Rashid STARLight Mechanical Engineer (734)
1 MICE Magnets Contents: Background Refurbishment Testing Installation & survey Current status Upstream beamline Open issues & concerns MICE Beamline Review,
Slide 1UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE UCSB 4-Hybrid Thermal Test System Status 21 July 2003 Sam Burke UCSB HEP Group.

RINDEL Emmanuel – IPNO – Detector Dpt. – 19/10/2011APRIME HPS collaboration meeting 1/9 Ecal and vacuum chamber design Unité mixte de recherche CNRS-IN2P3.
FCAL silicon sensors at INP PAN Cracow Current status Our plans Some remarks FCAL Hardware WGArkadiusz Moszczynski INP PAN Cracow1.
AIDA FEE64 production report June 2011 LYCCA tests and MBS Production of FEE64 Preparation for October test. 13th June
Thermo-mechanical infrastructure: Environmental Monitoring with FOS AIDA WP9.3 meeting November 21 th DESY, Hamburg. David Moya Martin Instituto de Física.
R. Rucinski, Fermilab Feb. 9, 2005 Project Status 2 cassette VLPC Cryostat Russ Rucinski - Fermilab This presentation will probably involve audience discussion,
CEDAR Support Structure and PMT Test Peter Sutcliffe 13 th July 2011 CERN via EVO.
1 HBD Construction status Itzhak Tserruya DC meeting, BNL, February, 2006 Plans for Run-6 Box construction GEM assembly and testing Status of urgent items.
Chiho Wang ATLAS TRT Duke University CERN, Feb TRT Barrel assembly status & schedule Feb. 9, 2005.
Dick Loveless 20 January Status of UXC Dick Loveless 20 January 2010.
Thomas Jefferson National Accelerator Facility Page 1 IPR October Independent Project Review of 12 GeV Upgrade Jefferson Lab October 18-20,
WP8.3.3 Status of Cold Boxes & Irradiation of Si sensors Maurice Glaser Frederico Ravotti Michael Moll Graham Beck, Jag Mistry Gianluigi Casse, Paul Dervan.
Low mass carbon based support structures for the HL-LHC ATLAS pixel forward disks R. Bates* a, C. Buttar a, I. Bonad a, F. McEwan a, L. Cunningham a, S.
AIDA 1 Mezzanine board Contacts for underside connectors Thermal contact pads.
WP4 Equipment Bids (Tim). Bids ATLAS – Case for the Purchase of Equipment for the Testing of Cooling Loops (£15k) – Case for the Purchase of Equipment.
Photo-detector Tube Construction Laboratory Considerations Dean Walters Argonne National Laboratory.
CEDAR Support Structure Peter Sutcliffe 24 th January 2011.
Status of NA62 straw electronics Webs Covers Services Readout.
THERMAL ANALYSIS OF ETA=3 REGION EE AND SE I.Wichrowska-Polok ST/CV CMS EE workshop 13th of March The purpose of the analysis. 2. The model description.
DBSP-R Upgrade Progress Review The DBSP-R Team DBSP-R Progress Review.
MFT WG5: ladder disk and global assembly Stéphane BOUVIER & Sébastian HERLANT MFT WG7: Mechanics and Thermal studies Jean-Michel BUHOUR & Emili SCHIBLER.
Development of a Segmented Planar Germanium Imaging Detector
Progress on Hydrogen R&D System
Vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand LHCb Vertex Detector System: Status Report J.F.J. van den Brand.
1 SVT Status Update Yuri Gotra CLAS12 Silicon Vertex Tracker TCB Meeting March 13, 2015.
PACS IBDR MPE 27/28 Feb 2002 AIV 1 PACS IBDR Test Cryostat and OGSE Gerd Jakob MPE.
KTAG Mechanics, Optics and Cooling Progress and Schedule NA62 CEDAR Meeting 3May20121.
MICE RF System Overview Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory Andrew Moss STFC Daresbury Laboratory MICE UK.
Cell Assembly Wafer connected to reinforcing aluminum plate Joined with metal epoxy and silicone thermal grease to ensure good thermal contact A small.
GLAST LAT ProjectCAL Peer Design Review, Mar 17-18, 2003 P. Dizon Naval Research Lab Washington DC GLAST Large Area Telescope Calorimeter Subsystem Gamma-ray.
Georgina Harris 11 th October nd SKADS Workshop – Observatoire de Paris 2-PAD Infrastructure Georgina Harris SKADS System Design and Team Leader.
EMCal Meeting Nantes – July J-F Muraz  Grenoble Status  Assembly and test Hall.
Chiho Wang ATLAS TRT Barrel Duke University U. Penn. Workshop, 2000 Module Thermal Analysis Chiho Wang Duke University.
Peter Kodyš, October 10, 2005, DEPFET workshop, Munich, Laser testy – status in Prague1 Peter Kodyš, Zdeněk Doležal, Pavel Řezníček, Zbyněk Drásal, Jan.
KTAG Mechanics, Optics and Cooling Progress and Schedule NA62 CEDAR Meeting 26March20121.
FEE Electronics progress PCB layout progress VHDL progress in TBU Prototype fixture for software 9th June 2009.
«BE-RF-PM» Updates on thermal tests Fabrizio Rossi.
1 MQXF(S) Magnet Interface Document MQXF(S) magnet interface document will describe electrical connection between the magnet and the header assembly Scope.
AIDA 1 Mezzanine board Resistors and capacitors near the ASiCs have now been relocated to the underside of the PCB. Cooling pads have been extended.
EMC BWE Proto18 - Orsay Meeting 1 PANDA EMC BWE Proto18 Mikel Catania Goikoetxea, Javier Navarro Medrano, David Rodríguez Piñeiro, Yue Ma, Frank.
Progress on Stave assembly tooling Stephanie Yang (Oxford) WP4 meeting at Liverpool University, 13 th November 2014.
News about the WA104 Programme C. Montanari – INFN and CERN technical working group meeting, September 16,
AIDA: introduction Advanced Implantation Detector Array (AIDA) UK collaboration: University of Edinburgh, University of Liverpool, STFC Daresbury Laboratory.
1°C A.S.2015/2016. What’s matter? EVERYTHING IN THE UNIVERSE CONSISTS OF MATTER. IT CAN HAVE DIFFERENT FORMS.IT CAN BE A SOLID, A LIQUID OR A GAS.
Liverpool March 09 Irradiation Meeting. Graham Beck (QMUL) 1 Dissipated Power: Sensor (at -10C, 200V bias, after protons/cm 2 ) ~ 1W (×3 for.
A.Ryazantsev, IHEP-Protvino, RussiaPANDA Russia Workshop at Moscow, May 2015 Status on Barrel Mechanics Andrey Ryazantsev on behalf of the IHEP-Protvino.
P. Sutcliffe Liverpool University
Thermoelectric Modules (TEM)
MICE Target Report Video Conference 29/11/07
Performance of an Automated Water Based Cooling System for CBM MuCh
Date of download: 12/21/2017 Copyright © ASME. All rights reserved.
MicroMegas Mechanical Meeting --- Cern April 2014
AIDA Asic Heatsinks Prototype received, and approved.
Status of Electronics Module
Gattini Detector Installation
Presentation transcript:

AIDA 1 20 Heatsink units, locating pins and washers now on site. Status of Electronics Module

These parts complete, delivered to Liverpool Templates for the cutting of the Dow Corning form to be produced and manufactured. Fasteners to be ordered. AIDA 2 Status of Electronics Module

3

AIDA 4 Status of Detector Mechanics PT100s and a controller have been wired by Paul and are monitoring temperature.

AIDA Thermal tests, N2 insulating volume, with Thermocube providing cooled nitrogen for detectors. Awaiting delivery of bottled Nitrogen to lab Nitrogen insulated 5 Slide is a reminder of proposed tests.

AIDA 6 This is the unit that will be used to cool the nitrogen gas. Unit on site at Daresbury.

AIDA All bought out parts now at Daresbury. Other parts to be made at Liverpool Workshop, delivery expected 13 th Feb Assembly at DL. Note of caution: Pauls expecting to be on paternity leave around end of Feb. Status of Detector Support Cooling plates Jumo Chiller Baseframe 7