Presentation is loading. Please wait.

Presentation is loading. Please wait.

CITY OF FORT COLLINS NEW FACILITIES KEN MANNON, KEN MANNON, Operations Services Director Operations Services Director.

Similar presentations


Presentation on theme: "CITY OF FORT COLLINS NEW FACILITIES KEN MANNON, KEN MANNON, Operations Services Director Operations Services Director."— Presentation transcript:

1 CITY OF FORT COLLINS NEW FACILITIES KEN MANNON, KEN MANNON, Operations Services Director Operations Services Director

2 CITY PARK POOL REPLACEMENT $ 1.75M - SCD: MAY 2003

3 COLLINDALE CLUBHOUSE -14,660 SF $2.6 M – SCD: DEC 2002

4 CSU TRANSIT CENTER – 11 DROP/ PICKUP SITES $2.37M – PHASE I COMPLETED SEPT 2002

5 CSU TRANSIT CENTER SITE LAYOUT

6 EPIC / TWICE THE ICE - 36,400 SF $ 3.93M – SCD: MARCH 2003

7 FIRE STATION # 14 - 10,800 SF $ 2.4M - SCD: APRIL 2003

8 FOSSIL CREEK MAINT. BUILDING – 6,550 SF $ 700K – SCD: MARCH 2003

9 GARDENS ON SPRING CREEK - 4,000 SF + 10 ACRES GARDENS - $ 2.05M - SCD: SEPT 2003

10 GARDENS ON SPRING CREEK – LONG RANGE MASTER PLAN

11 NEW METER SHOP SITE - 8,500 SF $ 2.03M - SCD: DEC 2003

12 NEW N S A C - 52,000 SF CONCEPTUAL PHASE: $100,000 YR 2004 FUNDING: $8 M

13 NIX SITE MAINTENANCE FACILITY - 6,000 SF $ 2.05M - 27.48 AC COMPLETED: JUNE 2002

14 NIX SITE – FARM HOUSE – 6,500 SF $ 2.4M - SCD: OCT. 2002

15 SOUTHRIDGE GOLF CART STG – 3,250 SF $ 200,000 - SCD: EARLY 2003

16 TRAFFIC OPS BUILDING - 9,300 SF $ 2.17M - SCD: NOV. 2002

17 UTIL’S WH YD IMPRVMNT SITE – EAST SIDE $ 3.25M - SCD: SUMMER 2003