0 0 Mainframe Legacy Access Migration (MLAM) Version 5 Municipality Meeting 3/5/2015 & 3/10/2015
2
MLAM Introduction Topics Introduction of VITA/NG Personnel Project Overview Necessary Actions Project Timeline Questions/Contacts 1
3
Introduction of VITA/NG Personnel 2 Hal Hughey (VITA) – Customer Account Manager Mike Shaffer (VITA) – Service Delivery Manager Jonathan Botts (NG) – Project Manager Other(s)
4
Project Overview 3 VITA/NG project to retire end-of-life devices –Channel interface Processor (CIP) router –Data Link Switching (DLSw) router Objectives: –Move all users off of CIP/DLSw –Utilize secure communications for all mainframe access
5
Project Overview 4 CIP Router DIT DLSw Router To User Organizations Open Systems Adapter To User Organizations Legacy ConnectionsTransformed Connection IBM Mainframe Applications Compensation Board/RESQ users are not part of this project
6
Project Overview Which device am I using? –DLSw router : User report included names of users –From a list of dedicated connections –CIP router: User report included names of users AND transactions counts per month The migration solution is the same… 5
7
Action Plan 1.Define single point of contact (POC) for entire municipality to: –Coordinate flow of information between municipal departments (if applicable) –Communicate to end users –Submit request for FW rules –Reporting status to VITA/NG team 6 With more than 150 municipalities, state agencies, and non-state agencies involved, a SINGLE POC for each is essential
8
Action Plan 2.Review list of identified users Report any discrepancies to VITA/NG team 3.Procure/obtain TN3270 emulator that can support TLS encryption If current emulator cannot 4.Complete firewall rule request form and send to VCCC@vita.virginia.govVCCC@vita.virginia.gov 7
9
Action Plan 5.Test connectivity Reply to completion notice with any issues If 2+ weeks after completion, contact VCCC 6.Notify VITA/NG of successful connection 7.Implement changes for all 8 VITA/NG executes request and provides new address/port information
10
Proven Migration Procedures Several municipalities have finished migrations Numerous FW rule requests processed using form 9
11
Clean-Up Activities Municipality: –Submit TSR Form Only if local circuit can be eliminated VITA/NG: –Block legacy access route To prevent users from reverting 10
12
End User Impact Emulator software may alter look and feel of connection (display changes) Application accessed and data presented should not change –Several municipalities have finished migrations –Numerous FW rule requests processed Encryption process is transparent to user 11
13
Project Timeline Target for migration – 90 days (6/8/15) Requested feedback from POC: –Milestone updates: Selected TN3270 emulator Submitted FW rule request ticket –Status update every two weeks –Notification of any schedule constraints 12
14
Questions/Contacts/Resources Please direct all questions and updates to: –VITAMainframeAccess@vita.virginia.govVITAMainframeAccess@vita.virginia.gov –Shared mailbox for MLAM project FAQs and other information –Includes links to TSR & firewall rule request Submit firewall rule request form to: –VCCC@vita.virginia.govVCCC@vita.virginia.gov 13