1 Pinole Valley High School (PVHS) Project Status
Facilities Subcommittee Meeting August 18, 2015

2 PVHS Anticipated Timeline
Cost/Budget Evaluation June/July 2015 Cost Efficiency Work Group July 2015 Updated Documents Received August 10, 2015 DSA Back-check/Approval Aug – Oct 2015 Pre-qualification Process July – Oct 2015 Project Bid Period (Target) Oct – Dec 2015 Construction Start (Target) January 2016 Buildings Complete (Construction: 30 mos.) – Bid Alternate Fall 2018 Buildings Complete (Construction: 36 mos.) – Bid Alternate 2019 Facilities Subcommittee – August 18, 2015

3 DSA Approval & WCCUSD Review (Including Cost Efficiencies) Timelines
Coordination Meeting 07/28/15 Back check Pre-Review Meeting Week of 08/24/15* Structural Back check Review Initiated 09/07/15*† Balance of Project Review Initiated 09/14/15*† DSA Approval/Stamp-out Week of 10/02/15* WCCUSD Updated Progress Drawings Received 08/10/15 – 08/24/15* WCCUSD Comments to Architect 09/28/15 – 10/09/15* WCCUSD Comments in Documents 10/12/15 – 10/21/15* [* Target Date] [† DSA will assess review time required at time of submittal] Facilities Subcommittee – August 18, 2015

4 PVHS Budget Considerations
BOE Approved Project Budget $181,900,000 Total (Completed/Current Construction Projects) ($27,370,000) Remaining Phases: Temp Housing Demo, Sports Fields/Courts (Supporting & Hard Costs) ($21,960,000) Remaining Project Budget $132,570,000 Supporting Costs (New Campus) $27,700,000 Construction Cost Available $104,870,000 AOR & District Estimates* (06/11/15 – 07/01/15) $112,563,245 – $122,465,404 Project Balance (Range) ($7,693,000) – ($17,595,000) [* Range may reflect scope discrepancies between documents used] Facilities Subcommittee – August 18, 2015

5 Cost Efficiency Working Group Summary
Participants included: City of Pinole: Debbie Long, Roy Swearingen CBOC: Maureen Toms Pinole Residents: Jeffrey Rubin, Bertha Rohrbach Architect: WLC Architects PVHS Site Representative: Kibby Kleinman, Principal WCCUSD Facilities Staff Program/Design Manager: SGI CM District Chief IOR: PTS (Steve Cayson) Facilities Subcommittee – August 18, 2015

6 Cost Efficiency Working Group Summary
Meetings occurred July 23rd & July 29 Categories reviewed: Operational (Facilities, M & O) Programmatic/Educational Other Opportunities Other Discussion Topics: Potential Additional Construction Costs Construction Schedule(s) Facilities Subcommittee – August 18, 2015

7 Cost Efficiency Working Group Summary
Recommendations Operational – Limit build-out of clinic space Revise classroom lighting Revise insulation/ thermal requirements Revise acoustical performance of mechanical duct and wall systems (still Ed Code compliant) Eliminate automatic shade controller system Reduce classroom floor boxes from 3 to 2 Replace fluorescent lighting with LED Intrusion, Security, POS, IT, LAN/WAN, EMS Programmatic/ Educational – Replacing operable walls with permanent walls (Buildings C & D) Eliminate special drama room features Eliminate stage scrims (backdrop curtains) ($3.5M) + $1.9M = ($1.6M) Facilities Subcommittee – August 18, 2015

8 Cost Efficiency Working Group Summary
Other Considerations Operational Revised Quad Space Revise waterproofing standard compliance requirements Replace central mechanical plant with package A/C systems Programmatic/ Educational Building A: Eliminate video production room, scene shop, drama classroom Building A: Eliminate classroom multi-media space Modify garden area Other Recommendations Replace sun shades at buildings C & D with film on glass Replace porcelain tile with cement plaster Items to consider as alternates Replace terrazzo/epoxy flooring with polished concrete Restore brick veneer in lieu of porcelain tile Facilities Subcommittee – August 18, 2015

9 Potential Issues & Concerns
Potential Cost Savings Up to $6.9M Potential Design Schedule Impact (*some tasks may be completed during DSA back check/bidding) Up to 16 weeks* DSA Review & Approval Timelines may impact desired construction schedule If bids are over allocated budget, adjustments to budgets may be required Facilities Subcommittee – August 18, 2015

10 Facilities Subcommittee – August 18, 2015
Recommendations Incorporate Recommendations for Cost Efficiency Bid with Alternates (two schedule options [30 months, 36 months], brick veneer, polished concrete) Facilities Subcommittee – August 18, 2015