Presentation is loading. Please wait.

Presentation is loading. Please wait.

Public Consultation A RE YENG REVIEW LINE 2B 13 August 2015.

Similar presentations


Presentation on theme: "Public Consultation A RE YENG REVIEW LINE 2B 13 August 2015."— Presentation transcript:

1 Public Consultation A RE YENG REVIEW LINE 2B 13 August 2015

2 Agenda Meeting facilitator – Dr David de Waal Welcome – Cllr Siobhan Muller Review of Line 2B – Cllr Aaron Maluleka Presentation – Rob Kelly & Mandla Ndlovu Discussion General Closing – Vote of thanks

3 Review of Line 2B Councillor Maluleka Council Resolved: That the proposed revised A Re Yeng Line 2B cross section design (lane acquisition for TRT Option 2) from the intersection of University/Lynnwood Road in Hatfield, along Lynnwood Road and Atterbury Road up to the intersection with January Masilela Drive, be approved.

4 POLICY FRAMEWORK NATIONAL LAND TRANSPORT ACT, 2009 The Act proposes that priority be given to public transport by ensuring the provision of adequate public transport services and applying travel demand management measures to discourage private transport.

5 Gauteng 25-Year Integrated Transport Masterplan States that the GITMP 25 presents a paradigm shift in spatial (Land Use) and Transport Planning.

6 BRT and IRPTN Report “The provision of additional lanes was specified as a last resort, which may require land expropriation if the road reserve is not wide enough. In the assessment a certain level of reduction in the level of service to general traffic was accepted in order to promote public transport. If the traffic impact on the rapid transit route and adjacent routes were severe, mitigation measures such as traffic management and provision of additional lanes could be specified. In cases where only one lane per direction is available, construction of an additional lane per direction was specified to accommodate dedicated lanes for the rapid transit”

7 Scheme extent – 6.9km 5 sections 6 Median Station Stops

8 Option 1 – Lane Addition

9 Option 2 – Lane acquisition

10 Baseline study (2012) Lynnwood and Atterbury Roads No current problems with traffic congestion Exception Lynnwood/University junction

11 2028 future year Level of Service F: Garstfontein / Dely Justice Mahomed/Brooklyn Justice Mahomed/Jan Shoba Justice Mahomed/University

12 Link Flow Differences between 2016 Mixed Lane option (i.e. 1 Mixed Lane Flow Minus 2 Mixed Lane Flow) 500-800 vehicles divert/hr Traffic flow differences between the two mixed lane scenarios are substantial Much higher levels of diversion occur for the single mixed traffic lane option On Lynnwood and Atterbury Roads these differences vary between 500 and 800 vehicles per hour

13 BROOKLYN RD JAN SHOBA JUSTICE MAHOMED DELY RD GARSTFONTEIN RD HAZELWOOD RD DIVERSIONS WITH 1 LANE OF GENERAL TRAFFIC ON LYNNWOOD/ATTERBURY

14 DUXBURY JAN SHOBA

15 Item No.: Consideration FactorsOption 1 – lane additionOption 2 – lane acquisition 1 National Land Transport Act 2009 (Act of 2009) Increase Infrastructure by widening the road to mitigate traffic congestion of private vehicles Remove road capacity to force people to use public transport 2Estimated Cost Implications R576 extra R160m over Option 1 (R80 million/km) – R 416m (R52 million/km) 3 Land acquisition for road widening 38 properties (excluding Council owned land) and portions of 47 residential driveways Approximately 4 properties will be affected 4Construction time18-24 months24 months 5 Traffic Management during Construction Maintain 1 lane of general traffic and one bus lane inbound and outbound Maintain 1 lane of general traffic inbound and outbound 6 Diversion of traffic to other streets Minor impactRelatively severe impact 8 Encouraging use of Public Transport Not as effective as option 2 driver to increase public transport usage by car users 9 Non Motorised Traffic i.e. Cycling and walking Limited space for cycling facilitiesCreates more space for a full NMT 10 Aligns to COT Planning and development policies Yes but not to the extent of option 2Yes to a greater extent than option 1

16 Traffic Impact Mitigation proposal – +1.7km of 4 mixed traffic lanes

17 Proposed new layout – Lynnwood

18

19

20 Proposed new layout – Atterbury/Lynnwood

21 Proposed new layout – Atterbury

22

23

24

25 Traffic Impact Mitigation Measures Retention of capacity between Jan Shoba & Atterbury Retention of capacity between N1 & Atterbury Intersection upgrades Off-trunk upgrades of identified intersections Optimise NMT facilities & landscaping Park & Ride facilities UTC Transfer of 200+ minibus taxis during peak hour to BRT

26 Proposed timelines

27 Notice of Intent – September Comment period – 21 days Report to Council for final decision Tender Process – Last quarter of 2015 Construction commencement – First quarter of 2016 Estimated duration – 18 months

28 For more information Call Centre:(012) 358-4848 Email:areyengenquiries@tshwane.gov.za Website:www.areyengtshwane.co.zawww.areyengtshwane.co.za Twitter: https://twitter.com/A_Re_Yenghttps://twitter.com/A Facebook:www.facebook.com/A Re Yeng

29 Thank You


Download ppt "Public Consultation A RE YENG REVIEW LINE 2B 13 August 2015."

Similar presentations


Ads by Google