Presentation is loading. Please wait.

Presentation is loading. Please wait.

Windsor Park & Ride (Overview & Scrutiny Panel – 29 th October 2007)

Similar presentations


Presentation on theme: "Windsor Park & Ride (Overview & Scrutiny Panel – 29 th October 2007)"— Presentation transcript:

1 Windsor Park & Ride (Overview & Scrutiny Panel – 29 th October 2007)

2 Objectives -Reduce congestion and impact of traffic in Windsor / Eton -Manage future transport growth / demands -Maximise efficiency of transport network (walking, cycling and public transport) -Air Quality improvements -Support town centre development -Support and enhance the visitor market -Regional benefits (eg. Crossrail / 2012 Olympics) Are there parking issues in Windsor to be addressed ??? Is Park & Ride the best solution ???? -Reduce congestion and impact of traffic in Windsor / Eton -Manage future transport growth / demands -Maximise efficiency of transport network (walking, cycling and public transport) -Air Quality improvements -Support town centre development -Support and enhance the visitor market -Regional benefits (eg. Crossrail / 2012 Olympics) Are there parking issues in Windsor to be addressed ??? Is Park & Ride the best solution ????

3 Strategic Layout

4 Scheme Design Strategic Link adjacent to M4 (junction 6) Scheme Design (Drawing no. 14276/500/003(B) refers) –New junction from Windsor & Eton Relief Road –New station on Windsor – Slough rail link –New link road to Eton wick –Capacity for circa. 900 cars / 25 coaches –Eton Wick residents car park / Eton P&R (circa. 300 spaces) –Potential to increase capacity to circa. 1800 spaces Strategic Link adjacent to M4 (junction 6) Scheme Design (Drawing no. 14276/500/003(B) refers) –New junction from Windsor & Eton Relief Road –New station on Windsor – Slough rail link –New link road to Eton wick –Capacity for circa. 900 cars / 25 coaches –Eton Wick residents car park / Eton P&R (circa. 300 spaces) –Potential to increase capacity to circa. 1800 spaces

5 de Layout

6 Transport Mode – Rail (preferred solution) Existing Slough – Windsor rail link Dedicated heavy rail option Frequency of service (6 per hour) Capacity (minimum of three carriages) New station at Park & Ride Existing station at Windsor Central Various track-work options Future operating arrangements Existing Slough – Windsor rail link Dedicated heavy rail option Frequency of service (6 per hour) Capacity (minimum of three carriages) New station at Park & Ride Existing station at Windsor Central Various track-work options Future operating arrangements

7 Transport Mode – Bus (alternative solution) Fleet of dedicated Park & Ride buses 7 no. buses – Approx. Frequency of service (every 15 minutes) Limited Scope for bus priority measures Fleet of dedicated Park & Ride buses 7 no. buses – Approx. Frequency of service (every 15 minutes) Limited Scope for bus priority measures

8 Finance – Capital Total Project cost – circa. £19m (Capital Outlay) -Car park / access / highway works – circa £8m -Rail / station works – circa. £6m -Fees / direct RBWM costs – circa. £5m (Note: costs based on construction in 2010/11) Funding sources –SEERA (Regional Transport funding from DfT):£7m –Olympic development Agency: To Be confirmed –RBWM Corporate funding:£1m –Developer contributions Subject to appropriate development –Other agencies / partners Negotiations not commenced CAPITAL DEFICIT: £11m Total Project cost – circa. £19m (Capital Outlay) -Car park / access / highway works – circa £8m -Rail / station works – circa. £6m -Fees / direct RBWM costs – circa. £5m (Note: costs based on construction in 2010/11) Funding sources –SEERA (Regional Transport funding from DfT):£7m –Olympic development Agency: To Be confirmed –RBWM Corporate funding:£1m –Developer contributions Subject to appropriate development –Other agencies / partners Negotiations not commenced CAPITAL DEFICIT: £11m

9 Finance – Revenue Potential Demand -Currently 300 – 400 spaces (based on review / projection of car park usage patterns) -Circa. 800 spaces (based on typical interception rate of between 2.9 – 6%) -Future growth and additional capacity required for Windsor Revenue Costs –Rail or bus based facility:£1m per annum Revenue Generation -Parking income: increase by raising tariffs and generating demand OPERATING DEFICIT: £275K (PER ANNUM) Experience of Park & Ride facilities elsewhere is that direct positive financial returns are rare and Break Even is often the best case. Subsidies are common. Significant non-cashable benefits are realised Potential Demand -Currently 300 – 400 spaces (based on review / projection of car park usage patterns) -Circa. 800 spaces (based on typical interception rate of between 2.9 – 6%) -Future growth and additional capacity required for Windsor Revenue Costs –Rail or bus based facility:£1m per annum Revenue Generation -Parking income: increase by raising tariffs and generating demand OPERATING DEFICIT: £275K (PER ANNUM) Experience of Park & Ride facilities elsewhere is that direct positive financial returns are rare and Break Even is often the best case. Subsidies are common. Significant non-cashable benefits are realised

10 Finance – Business Case Increase revenue streams / Reduce capital outlay Capital –Approach SEERA (via DfT Major Scheme Bid) to increase funding –Secure financial commitment from Olympic Delivery Agency –Secure private investment –Generate capital receipts from RBWM assets Revenue –Aggressive parking strategy –Reprovide town centre long-stay parking at Park & Ride –Review long-stay tariffs / discounts for residents –Open up new markets (eg. Crossrail) Increase revenue streams / Reduce capital outlay Capital –Approach SEERA (via DfT Major Scheme Bid) to increase funding –Secure financial commitment from Olympic Delivery Agency –Secure private investment –Generate capital receipts from RBWM assets Revenue –Aggressive parking strategy –Reprovide town centre long-stay parking at Park & Ride –Review long-stay tariffs / discounts for residents –Open up new markets (eg. Crossrail)

11 Planning / Land Planning Strategy –Significant Planning Constraints exist –Overall policy to support park and ride ….Success will rest upon the ability to demonstrate that park and ride is the most sustainable option and the overall benefits of development outweigh the harm to the site… Land -Appropriate site must be secured -Lammas rights to be resolved Planning Strategy –Significant Planning Constraints exist –Overall policy to support park and ride ….Success will rest upon the ability to demonstrate that park and ride is the most sustainable option and the overall benefits of development outweigh the harm to the site… Land -Appropriate site must be secured -Lammas rights to be resolved

12 2012 Olympics / Regional Agenda London 2012 Olympic venue – Dorney Lake (rowing, kayak, canoe) Sustainable Games – Park & Ride at Windsor identified in Transport Plan Discussions ongoing with Olympic Development Agency Regional Agenda For example; Crossrail London 2012 Olympic venue – Dorney Lake (rowing, kayak, canoe) Sustainable Games – Park & Ride at Windsor identified in Transport Plan Discussions ongoing with Olympic Development Agency Regional Agenda For example; Crossrail

13 Stakeholder Engagement Local communities Local businesses / Chambers of Trade Network Rail Transport Operators Highways Agency Environment Agency Landowners Olympic Development Agency Neighbouring Authorities SEERA / DfT Local communities Local businesses / Chambers of Trade Network Rail Transport Operators Highways Agency Environment Agency Landowners Olympic Development Agency Neighbouring Authorities SEERA / DfT

14 Potential Project Programme Feasibility / Business Case: April 2007 – March 2009 Planning Application: April 2007 – March 2009 Statutory Approvals: July 2007 – June 2010 Design / Procurement Process: April 2009 – September 2010 Construction: October 2010 – March 2012 Acceptance / Operation: April – June 2012 2012 Olympics: July – August 2012 Park & Ride Legacy: September 2012 onwards Feasibility / Business Case: April 2007 – March 2009 Planning Application: April 2007 – March 2009 Statutory Approvals: July 2007 – June 2010 Design / Procurement Process: April 2009 – September 2010 Construction: October 2010 – March 2012 Acceptance / Operation: April – June 2012 2012 Olympics: July – August 2012 Park & Ride Legacy: September 2012 onwards

15 Options for Way Forward Are there parking issues in Windsor to be addressed ??? Is Park & Ride the best solution ??? –If no, how will increasing demand / pressures be managed –If yes Is the currently preferred site at Southfield the best solution Is rail a pre-requisite of the project Is a cost neutral business case essential Is the link to Eton / Eton Wick essential Are there parking issues in Windsor to be addressed ??? Is Park & Ride the best solution ??? –If no, how will increasing demand / pressures be managed –If yes Is the currently preferred site at Southfield the best solution Is rail a pre-requisite of the project Is a cost neutral business case essential Is the link to Eton / Eton Wick essential


Download ppt "Windsor Park & Ride (Overview & Scrutiny Panel – 29 th October 2007)"

Similar presentations


Ads by Google