1 Torrance Unified School District Bond Measure Y Bond Measure Z Quarterly Construction Update September 30, 2009

2 Measure Y/Z Bond Management Team Program/Construction Management Torrance Unified School District Modernization ProjectsTwo New School FacilitiesFields & Modernization Projects

3 OVERVIEW Measure Z: Update on progress of new field construction Measure Y/Z: Progress reports for modernization projects at South High School, Magruder Middle School, and Walteria Elementary School Measure Y/Z: Progress reports for the new construction projects at Hull Middle School and Fern Elementary School

4 Measure Z Immediate Bond Money at Work

5 Sports Fields – North & West HS Where We Are: Field Construction Complete Closeout / Punchlist Completion Bleacher Design and Assessment in Progress Where We Are Going: Bleacher Replacement Late Spring / Summer 2010

6 SOUTH HS Where We Are Demolition is complete. Construction has started and is approximately 60% complete. Synthetic turf has begun and is schedule to be completed on July 28 th. Bleacher installation is scheduled to start Aug 3 rd and will be completed by Sept 11 th. Where We Are Going: Restroom upgrades will be scheduled for Jan – Feb 2010. Sports Fields – South & Torrance HS Where We Are: Field & Bleacher Construction Complete Closeout / Punchlist Completion Restroom Plans approved by DSA Where We Are Going: Restroom Renovations January/ February 2010

7 Measure Y/Z School Modernizations

8 Where We Are: Surveying Complete Geological Report Complete Construction Documents ⁻ Campus Visual Enhancements ⁻ Quad/Assembly Area Developed ⁻ Classroom Wing Development ⁻ Covered Walkways Designed Magruder Middle School

9 Where We Are Going: Community Meeting #2 – October 2009 Board Approval of Design DSA Submittal- Late October 2009 Final Cost Estimates Bidding - Late Spring Construction Begins - Summer 2010 Magruder Middle School

10 Where We Are: DISTRICT MASTER STANDARDS Master Standards 90% complete Prototype Classroom and Lab Design Complete CONSTRUCTION DOCUMENTS Final User Group Scope Meeting Resolution of Drainage Issues and Site Circulation Final Design of an Improved Learning Environment with new Finishes, Lighting, Millwork, Windows/Doors, Roofing, Mechanical, and Fire Alarm System South High School

11 Where We Are Going: September 2009 Test Classroom Flooring complete Master Standards complete October 2009 Community Meeting #1 50% Construction Documents Package for District Review November 2009 Board Approval of Design Construction Documents Complete Division of the State Architect Submission Summer 2010-Early 2012 Construction Start and Finish

12 Walteria Elementary School Where We Are DISTRICT STANDARDS MEETINGS Master Standards 90% Complete CONSTRUCTION DOCUMENTS Detailing an Enhanced Learning Environment via: ‐A New Campus Entry ‐Reconfiguration of the Admin. Interior ‐Relocation of existing and new Portable Classrooms ‐A new Classroom wing, Library, Kindergarten Quad ‐Covered Walkways ‐Site Amphitheater to solve Grading Issues

13 Walteria Elementary School Where We Are Going: September 2009 Detailing of Drawings, Finishes, Materials, Products, and Specifications October 2009 Community Meeting #2 District Review of 50% Construction Documents November 2009 Board Approval of Design Construction Documents Complete Division of the State Architect Submission Summer 2010 - Fall 2011 Construction Start and Finish

14 New Construction

15 Where We Are: DEMOLITION: Complete end of August OIL WELLS: Wells tested and no methane detected or methane remediation required SOLAR STUDY: Analysis of campus energy use begun Report due October SUBMISSIONS: 50% Construction Documents – early October Hull Middle School

16 Where We Are Going: Site Plan: ⁻ 28 Teaching Spaces ⁻ Multi-purpose Bldg. & Food Services ⁻ Media Center ⁻ Administration ⁻ Gym, (Alternate) Community Meeting #2 Late October 2009 Playfield: Separate Bid November 2009 Recap Torrance #4 Well Board Approval of Design DSA Submittal: Nov. 2009 Hull Middle School

17 Where We Are: No petro. or hydrocarbon lines in the street Interim housing plan complete Geotechnical report complete Site Committee meeting #4 held on September 15, 2009. 50% Construction Documents submission early October Fern Elementary School

18 Where We Are Going: Site Plan: ⁻ 15 New Classrooms ⁻ New Multi-purpose Building ⁻ New Food Services Community Meeting #2 – October 2009 Board Approval of Design DSA Submittal: November 2009

19 Questions And Closing Remarks Moving Forward