Presentation is loading. Please wait.

Presentation is loading. Please wait.

AFREPREN/FWD Cogen Centre Training Workshop on Cogeneration in Africa

Similar presentations


Presentation on theme: "AFREPREN/FWD Cogen Centre Training Workshop on Cogeneration in Africa"— Presentation transcript:

1 How Utilities Can Benefit from Cogeneration Hippo Valley Estates Case Study
AFREPREN/FWD Cogen Centre Training Workshop on Cogeneration in Africa 10-11 January 2009, Sotik, Kenya

2 CONTENTS OF PRESENTATION Cogeneration at Hippo Valley Estates Perfomance of Chiredzi distribution network Technical benefits of embedded cogeneration Economic benefits of embedded cogeneration

3 Context of Case Study Case study undertaken under “Cogeneration in Zimbabwe: a utility perspective” by Bothwell Batidzirai Worked for the electricity utlity ZESA as customer services engineer for 3 years Portfolio included agroindustries, farmers and rural communities Specific functions included monitoring quality of supply, energy services and customer liaison

4 Cogeneration at Hippo Valley Estates (HVE) Key operational parameters
Sugar cane milling period: months Annual tonnage of crushed cane: 2.3 million tonnes Boiler characteristics: 6 boilers total rating of bars and 400oC Turbo Alternators 46 MW but fully function estimated 30 MW 3 boilers have capacities of 40 tonnes/hr 1 boiler has capacity of 100 tonnes/hr 2 boilers have capacities of 68 tonnes/hr

5 Cogeneration of electricity and process heat
at Hippo Valley Estates (HVE) Average HVE estate demand is about 14.5MW Up to 11MW excess capacity can be exported the grid (30 GWh – 66GWh p.a.) Power Purchase Agreement with ZESA concluded in 2001 to export excess power Improvement of Chiredzi network wrt quality of supply, reliability and reduction of losses

6 Technical benefits - reliability
Demand in Chiredzi area is 25 MVA Up to 11MW available for export to local grid via L1 substation HVE feeding L1 in an island mode configuration

7 Location of power plants and
Chiredzi area Power production centres distant from Chiredzi area Long distance transmission of power transmission losses and voltage regulation problems Need for boosting supplies in Chiredzi area

8 Chiredzi distribution network
CHISUMBANJE FDR. MKWASINE FDR. RENCO 2 FDR. RENCO 1 FDR. CHIREDZI 2 FDR. CHIREDZI 1 FDR. 33kV BUSBAR 132 kV BUSBAR N/O 132 kV LINE FROM MIDDLE SABI PROPOSED 11/33kV INTERCONNECTOR SUBSTATION FROM HVE POWER STATION 11kV 33kV CHIREDZI (L1) 15MVA, 33/11KV SUBSTATION HIPPO VALLEY PUMPS (L16) 5MVA, 33/11KV SUBSTATION 2.4MVAr CAPACITOR BANK AT BUFFALO RANGE CHIREDZI EAST (L18) 10MVA, 33/11KV SUBSTATION CHIREDZI RIVER PUMPS SUBSTATIONS 1 & 2, 33/0.38Kv, TOTAL INSTALLED CAPACITY 1.5MVA MKWASINE 132 KV SUBSTATION 132 kV LINE FROM TRIANGLE 2 long feeders tied in ring network Chiredzi town feeders carry 33% of parent s/s load short and long feeders gives voltage regulation problems

9 Chiredzi network performance analysis
Load flow analysis Substation voltage with different loading conditions Quality of supply Maintenance of voltage, frequency within statutory limits Voltage and Load profile analysis Reliability assessment Provision of uninterrupted service

10 Impact of Cogen on Voltage Stability:
Load flow analysis Substation Light load without cogen Peak load without cogen Light load with cogen Peak load with cogen Chiredzi Town T1 32.7 29.5 34.6 33.6 T2 Chiredzi East 32.5 29.0 33.7 31.6 Hippo Valley 32.6 29.3 34.9 33.8 HVE Pumps 34.7 33.5 Statutory limits: Voltage: ±10% Range ~ 29.7kV to 36.3 (33kV nominal)

11 Load profile for Chiredzi Town (L1)
Impact of HVE demand

12 Technical benefits – quality of supply
Cogen stabilizes voltage hence improves quality of power supply With cogen the utilitiy does not have to resort to On Load Tap Changing to regulate voltage which can lead to system instability With cogen the utility can avoid using line drop compensation which is not effective with long and short feeders from one substation Because cogen improves voltage control, it: Allows increased line loading Allows extension of line length

13 Technical benefits - reliability
Cogen ensures: Improvement in reliability of supply from local substation If national grid collapses, local network not affected and total black out of Chiredzi is avoided

14 Economic benefits Avoided Investment Costs New generation capacity
26MW coal thermal costs – USD 31.2 million Hydro costs – USD 52 million Network reinforcement Uprating feeders to carry higher loads Substation uprating: Uprating MVA 33/11kV ss costs ~USD 1 million Constructing 330/132 kV ss – USD 8.3 million Avoided Imports Interconnectors costly – 330kV costs ~ USD 480,000/km construction cost & USD 9,600/km maintenance pa HVE can save USD 1.32 million pa imports

15 Economic benefits Costs Of Meeting Peak Demand
Savings of up to USD 3.5 million for peak demand dispatch Reduces cost Of Outages And Unmet Demand Reduction In Losses load flow shows peak power losses reduced from 16.1% (2,963 kW absolute) without cogeneration to 8.3 % (1,061 kW absolute) with cogeneration Voltage Control leads to reduced liability claims

16 Lessons for Cogen Project Developers
Similar technical and economic benefits can be demonstrated in other African countries Cogen for Africa Project can assist in analyzing and quantifying these benefits and presenting them to utilities and policy makers THANK YOU


Download ppt "AFREPREN/FWD Cogen Centre Training Workshop on Cogeneration in Africa"

Similar presentations


Ads by Google