1 Mysore City Corporation Mysore JnNURM

2 Jawaharlal Nehru National Urban Renewal Mission JNNURM PROGRESS REVIEW 15 th January 2009 Projects State : Karnataka City : Mysore

3 Jawaharlal Nehru National Urban Renewal Mission Abstract of Projects Status of projects submitted under JnNURM for Mysore City Sl. No. Status of ProjectsNo. of Works Amount Rs.in Crores Remarks 1Projects approved by GoI 91120.72 2Projects Pending at GoI9610.50 Total181731.22 KUWS & DB MUDAKSCBKSRTCMCCTourismHeritage Sl.Status of Projects No. of Works Amount Rs. in Crores No. of Works Amount Rs. in Crores No. of Works Amount Rs. in Crores No. of Works Amount Rs. in Crores No. of Works Amount Rs. in Crores No. of Wor ks Amount Rs. in Crores No. of Works Amount Rs. in Crores 1.1. Projects approved by GoI 2303.361219.032136.2185.253376.88 2 Projects pending at GoI 1392.582109.7339.72265.6012.90 Total 3695.943328.732136.2185.256416.60265.60122.90

4 Jawaharlal Nehru National Urban Renewal Mission Projects Approved by GoI Sl. No. Name of the Project Appr cost Rs. in Crores Implementing Agency Status Sector: Water Supply 1.Remodeling of Water Supply distribution network, automation of system and providing integrated management system for Mysore city 194.54KUWS & DB 2Augmentation of bulk water supply from river Kabini. 108.82KUWS & DBProcess for acquiring 30 acres of land is initiated. Tender document are being prepared. WORK FLOW CHART :

5 Jawaharlal Nehru National Urban Renewal Mission Project Approved by GoI Sl. No. Name of the Project Appr cost Rs. in Crores Implementing Agency Status Sector: BSUP 3.Rehabilitation of 20 selected slums of Mysore City.(2788 houses) 17 selected slum rehabilitation 3 slums development works. Project Cost : Rs. 67.58(In Crores) 45.27KSCB In Phase-I, 1188 houses have been entrusted to Mysore Nirmithi Kendra at a cost of Rs.1.80 Lakhs per dwelling unit and 1170 houses have been entrusted to different empanelled contractors as approved in the SLEC meeting held on 25-10-08. Balance 430 houses decision to construct houses or to provide infrastructure to be decided The following works have been started. a. Mandakally - 480 Houses b. Roopanagar & Bogadi - 144 Houses c. Metagally - 276 Houses d. Hanchya Sathgally Block 1 - 180 Houses e. Hanchya Sathgally Block 2 - 186 Houses Total 1266 Houses 4.Rehabilitation of 46 selected slums of Mysore city(2500 Houses) 90.93KSCB As per the SLEC meeting held on 25- 10-08,Tenders were finalized and the following pacakges were approved. a)Package II – 396 Houses b)Package III - 348 Houses c)Package VII – Providng Infrastructure to 5 slums. Out of 1244 houses, tenders have been called for 1000 houses on 20/12/08 for which land is awaited from Revenue department

6 Jawaharlal Nehru National Urban Renewal Mission Project Approved by GoI Sl. No. Name of the Project Appr cost Rs. in Crores Implementing Agency Status Sector: Transportation 5.Infrastructure Development of Transport System in Mysore Tendered Cost:Rs. 108.90 crores Work awarded on: 25.8.08 Contract period: 18 months excluding monsoon period (3 months) 85.25KSRTCWork Commenced at 1. Kuvempunagar. 2. RS Naidunagar. 3. Sathagalli. 4. Moffosil Bus Station. 5.Yelwala. 6.CBS. Works yet to commence at 1.Chamundi Hills. An amount of Rs. 1005 lakhs has been spent as against the target of Rs 979 lakhs till the end of December 2008. Sector: Solid Waste Management 6.Development of an integrated Municipal Solid Waste Management (MSW) plant for the city of Mysore 28.98MCCThe Project has been cleared in CSMC meeting held on 19/12/08. Action is taken to Commence IEC activity. Tender documents are being finalised. Sector: Drainage 7Remodeling of storm water drain in Mysore (104.67km) 347.28MCCThe Project has been cleared in CSMC meeting held on 19/12/08. Privatization of valleys is in progress.

7 Jawaharlal Nehru National Urban Renewal Mission Project Approved by GoI Sl. No. Name of the Project Appr cost Rs. in Crores Implementing Agency Status Sector: Roads 8.Upgrading 2 lane outer ring road to 6 lane along with service road from Mysore- Bangalore road to Mysore-Nanjungud road (0 to 25 km-western side ) and upgrading 4 laned outer ring road to 6 lane along with service road from Mysore-Bangalore road to Mysore-Bannur road (0 to 7.49 km – Eastern side) 219.03MUDA Approved by GOI on 15.02.08 in CSMC meeting. Central and State Govt,.share of Rs. 49.28 crores released vide Govt. order No. UDD 44 CSS 2007 dated 25-3-2008. Tender has been floated on 27-3-2008. Only one agency is qualified in Technical Bid and hence rejected by govt.,Retender is called for four packages on 17-09-2008. The same Notification has been Questioned in the Honourable High Court Vide W.P No: 13270 of 2008. The Honorable High Court has passed an interim order stating that all further proceedings pursuant to the Notification dated 17- 09.2008 will be subject to further order of this court. Further process on Notification is in Progress. Last date for receipt of bids 05/01/09 Sector: Others 9.Project Implementation Unit0.62MCC Public Health Engineer, Information Technology Officer and Human Resource Development officer have reported. Tender has been called for the remaining posts. Total 1120.72

8 Jawaharlal Nehru National Urban Renewal Mission Projects Pending at GoI Sl. No. Name of the Project Appr cost Rs. in Crores Implementing Agency Status Sector: Preservation of Water Bodies 1Conservation on Natural lakes in Mysore- Packages 1 (4No. of Lakes) 6.63MCCDPR submitted to GoI for approval. Central Water Commission to scrutiny the DPR. 2Conservation on Natural lakes in Mysore- Package 2 (4 No. of Lakes) 6.46MCCDPR submitted to GoI for approval. Central Water Commission to scrutiny the DPR. Sector: Others 3Setting up of new Modern Abattoirs26.63MCCThe GOI has been requested to consider this project as an activity under SWM as it is not possible to consider under NABARD as MCC is an Urban area. The matter is under examination of GOI

9 Jawaharlal Nehru National Urban Renewal Mission Projects Pending at GoI Sl. No. Name of the Project Appr cost Rs. in Crores Implementing Agency Status Sector: Roads 4Construction of balance length of the outer ring road with a 6 lane road along with service road from Bannur road to Nanjungud road (Ch. 7.49km to 16.635km) 90.70MUDAFinal notification for land acquisition completed. Resubmitted to GOI for re-consideration. Sector: Heritage and Urban Renewal 5Development of Tourist Infrastructure In Mysore- Pakage1 development of Chamundi Hill 13.78Tourism Department DPR submitted to GOI. Awaiting approval from GoI. Sector: Heritage and Urban Renewal 6Development of 35 acres Heritage park in front of Lalith Mahal palace in K.C. Layout, Mysore 19.00MUDADiscussed in CSMC meeting on 15.02.08 to be reconsidered after getting comments from heritage experts. Expert committee to be formed by GoI.

10 Jawaharlal Nehru National Urban Renewal Mission Projects Pending at GoI Sl. No. Name of the Project Appr cost Rs. in Crores Implementing Agency Status 7Conservation of Heritage Buildings.2.90HeritageDPR submitted to GOI. Awaiting approval from GoI. 8Development of Heritage Core51.82Tourist Department Awaiting approval from GoI. Sector: Sewerage 9Remodeling of the UGD network in old areas of the city and development of sewage treatment plant ( STP ) for the uncovered areas 392.58KUWS&DBDPR submitted to GOI. Awaiting approval from GoI. Total610.50 REFORMS

11 Jawaharlal Nehru National Urban Renewal Mission Projects in the pipeline for submission Sl. No. Name of the Project Appr cost Rs. in Crores Implementing Agency Status Sector : BRTS/Roads/other urban transport 1Restructuring of intermediate ring road and construction of subways in Mysore (27.49km of road and 2 No. of Subways) 20.00MCCNegotiation underway with 2 nd lowest bidder, M/s. CES, Bangalore. 2.Extension of 4 Railway under bridges (RUB’s) from 2 lane to 6 lane across outer ring road (western side) at ch. 1.15km, 1.95, 3.57km and 20.54km (On deposit basis to railways) 29.92MUDARailway department to submit estimate. DPR under preparation. Sector : Heritage & Urban Renewal 3.Improvement of Urban forestry in Mysore (53 No. of Parks totaling to 103.04 acres) 19.00MCCSubmitted DPR to KUIDFC for placing before SLEC and was refused. Request has been made to KUIDFC vide letter No. MCC/SE/JnNURM/147/08- 09 dated 01.10.08 to reconsider the project. 4.Providing Infrastructure facilities to heritage buildings and circles of Mysore 20.00Heritage Department DPR preparation under progress HUDCO are the consultants.

12 Jawaharlal Nehru National Urban Renewal Mission Projects in the pipeline for submission Sl. No. Name of the Project Appr cost Rs. in Crores Implementing Agency Status Sector: Water Supply 5.Strengthening of existing Hongalli II & III Stage WSS 47.50KUWS & DBDPR to be submitted to KUIDFC 6.Augmentation of 50 MLD from III Phase Melapura. 29.50KUWS & DBDPR finalised. MCC passes resolution. DPR to be submitted to KUIDFC from KWB. 7Development of ZOO Infrastructure23.00TourismDPR to be submitted to KUIDFC Total188.92