TMB and RAT Status Report Endcap Muon OSU June 6, 2004 Martin von der Mey University of California, Los Angeles  Previous Status (OSU, April)

Similar presentations


Presentation on theme: "TMB and RAT Status Report Endcap Muon OSU June 6, 2004 Martin von der Mey University of California, Los Angeles  Previous Status (OSU, April)"— Presentation transcript:

1 TMB and RAT Status Report Endcap Muon meeting @ OSU June 6, 2004 Martin von der Mey University of California, Los Angeles  Previous Status (OSU, April)  Update  Future Plans

2 6/6/2004 CMS Endcap Muon meeting@CERN 2 TMB2004A and RAT2004A  Last meeting’s status:  TMB boards (32) were debugged.  RAT boards (32) were assembled, 1 debugged.  10 XC2V3000 mezzanine cards were produced for test beam.

3 6/6/2004 CMS Endcap Muon meeting@CERN 3 TMB/RAT Hardware Update (April-May)  All 32 RAT boards were debugged.  Full-crate tests at OSU and Rice have been pretty successful.  Possible small firmware bug in TMB fake muon sequence to MPC (32 frames OK, 256 not)  Full Virtex-II order (XC2V4000) placed, 100/540 chips received.  New TMB Virtex-II mezz. card layout (PNPI).  Currently reviewing mezzanine card bids for production and assembly.

4 6/6/2004 CMS Endcap Muon meeting@CERN 4 TMB/RAT Firmware Update (April-May)  RPC data readout simulated, debugged.  New RPC-related control and data registers.  Firmware updated for new FPGA pin-out.  Compiles without errors.  This fixes all previous problems.

5 6/6/2004 CMS Endcap Muon meeting@CERN 5 TMB/RAT Testing Update (April-May)  Successful tests at UC FAST site:  New TMB firmware.  New feed-through backplane.  RAT module ALCT interface (timing changes).  Debugging updates to PCC software.  4 TMBs currently in use at X5A.  Parts shipped for RPC tests:  Rear card cage (from Wiener) arrived.  Shipped backplane that connects to RAT.  Shipped RPC Link Board-to-RAT cables (5x2m and 4x8m variants).

6 6/6/2004 CMS Endcap Muon meeting@CERN 6 Future Plans I  TMB boards:  Ready to go into production pending successful beam test.  Mezzanine boards:  Components in hand except for Eproms.  Ready to go into pre-production pending successful beam test.  RAT modules can go right into production, but:  Need to see results with ALCTs and RPCs.  Need to test full pre-production backplane.  Need full crate mock-up (cable installation, strain relief, etc. issues).

7 6/6/2004 CMS Endcap Muon meeting@CERN 7 Future Plans II  RPC→Link Board→RAT→TMB testing:  Link-to-RAT initial tests can be done with or without RPC chamber (connectivity test, send beam xing bits).  Cosmic ray tests of RPC→Link→RAT nearly as interesting as beam test.  A few new RPC-related TMB registers (need small update to PCC software).


Download ppt "TMB and RAT Status Report Endcap Muon OSU June 6, 2004 Martin von der Mey University of California, Los Angeles  Previous Status (OSU, April)"