UPDATE – FEBRUARY 2012 Jail Expansion & Infrastructure Construction Project.

Similar presentations


Presentation on theme: "UPDATE – FEBRUARY 2012 Jail Expansion & Infrastructure Construction Project."— Presentation transcript:

1 UPDATE – FEBRUARY 2012 Jail Expansion & Infrastructure Construction Project

2 AB 900 Project History  March 2008 - The Board of Supervisors approved Resolution R-08-146 to submit a proposal through the Corrections Standards Authority Local Jail Construction Funding Program (AB 900) for the jail expansion project  May 2008 - San Joaquin County was conditionally awarded $80 million for the jail expansion project  January 2009 - Began design process with Architecture & Engineer and the Design Team 2

3 AB 900 Proposed Concept ItemSq FtConstruction Cost 1280 Beds - 11 units -per unit 186,164 16,924 $39,622,123 $3,602,011 Custody Administration Building -JCC included 46,604 990 $8,450,266 $1,221,500 Visitor Center5,882$1,936,426 Central Plant8,400$4,322,000 Secure Corridors8,268$2,314,220 Design Contingency-------$7,769,919 Escalation to MOC-------$2,832,252 Contractor OH/P GC-------$16,811,801 Total Construction Cost:255,318$84,059,008 Total Project Cost $115,330,739 3

4 AB 900 Proposal Deficiencies  The Jail Expansion footprint identified in the 2008 Jail Needs Assessment Update was conceptual and not a programmed site plan  Omitted Infrastructure  Site work  North Jail Administration Building  Square Footage of Housing Units based on Title 15 Minimum Standards  Inadequate to maintain the Direct Supervision Philosophy 4

5 Preliminary Housing Concepts Many housing unit concepts were reviewed to ensure operational design and space requirement needs were met within the project budget. 5

6 Preliminary Housing Concepts Many housing unit concepts were reviewed to ensure operational design and space requirement needs were met within the project budget. 5a

7 Preliminary Housing Concepts Many housing unit concepts were reviewed to ensure operational design and space requirement needs were met within the project budget. 5b

8 Preliminary Housing Concepts Many housing unit concepts were reviewed to ensure operational design and space requirement needs were met within the project budget. 5c

9 50% Design Development North Jail Facility Custody Annex Building Video Visitor Center 6

10 7

11 Queuing Area Waiting Area Visiting Area Staff Control Room Fire Riser Janitor Closet Elec. Room Public Restrooms Visiting Area Queuing Area Waiting Area Staff R/R Public R/R Low Voltage Room 8

12 Custody Annex Building 9

13 ` Men’s Locker Room (396) Vending Area Briefing Room Women’s Locker Room (204) IT Room Gun Lockers CERT/Canine Room A-V Room Electrical Room Mechanical Room Phone & Cable Entry JCC Janitor Mail Slots Gun Lockers 10

14 North Jail Admin Bldg Central Plant 10 Medium-Security Housing Units North Jail Facility

15 North Jail Administration Building Enclave Staging Rooms 1-10 Sgt Offices Storage Officer Work Area Staff Break Room Staff R/R Admin Work Station Search Rooms 1-6 Inmate R/R Refrigerated Food Storage Laundry Supplies Janitor 1 5 432 7 6 9 8 10 Admin Entrance Supply Entrance Corridor 1 2 3 6 5 4 12

16 Central Plant Boiler Room Chiller Room Central Plant Yard Low Voltage Elec. Room Electrical Room R/R Boiler Room Chiller Room Central Plant Yard Low Voltage Elec. Room Electrical Room R/R 13

17 Housing Units 14

18 15

19 16

20 17

21 18

22 Project Budget  State Funds $80,000,000 ($80 million conditional award in Lease Revenue Bonds)  County Set-Aside $25,000,000  AB 900 Hard Match ($21,046,603)  AB 900 Ineligible Costs ($3,953,397) (Furniture Fixtures & Equipment, Off-Site Improvements, Plan Check & Permit Fees)  In-Kind Match (Transition Planning, Needs Assessment, Site Acquisition) $10,556,602 Total Project Cost $115,556,602 $2.1 million was borrowed from the Jail Expansion Project county set-aside to meet the Fiscal Year 2011/2012 Budget. 19

23 Probable Construction Cost September 2011 ItemSq FtCost Housing Building to include: -1,280 Beds (10 units) -North Jail Admin Bldg -Central Plant 283,429$63,312,604 Custody Annex Building15,518$5,983,032 Video Visitor Center5,861$2,526,245 Site Work563,567$5,874,359 Design Contingency (5%)-------$3,884,812 Escalation (3%)-------$2,447,432 Total Construction Cost:868,375$84,028,483 Total Project Cost $115,556,602 20

24 IMPACT ON THE SAN JOAQUIN COUNTY JAIL AB 109 Public Safety Realignment Act 10/01/11 – 01/31/12 A total of (731) AB 109 inmates have been processed through the San Joaquin County Jail 21

25 AB 109 Impact on San Joaquin County Jail  AB 109 inmate population as of January 31, 2012:  286 inmates in custody  5 inmates on electronic monitoring  263 inmates released  128 of the inmates released have returned to custody with new cases  65 – Parole  36 – Probation Violations  4 – Narcotics Charges  7 – Property Crimes  3 – Weapons  2 – Violence  11 – Other 22

26 AB 109 Impact on San Joaquin County Jail  AB 109 inmates with new sentences = 112  Average length of stay is 3 years  Split time of 3 years in custody with 1 year of community supervision  Longest AB 109 Sentences  8 years (4 years in custody/4 years supervised release)  7 years straight time 23

27 AB 109 Impact on San Joaquin County Jail  AB 109 Parole Violation Holds in custody = 210  79 in jail for parole violation only  131 in jail for parole violation with a new charge/sentence  Probable Cause Hearings completed = 497  Pending Probable Cause Hearings =11  Revocation Hearings = 10 24

28 New Commitments Parole Violators MonthState Projection Actual Received Difference Oct-11 32 0 Nov-11 3530-5 Dec-11 2028+8 Jan-12 2030+10 AB 109 Impact on San Joaquin County Jail MonthState Projection Actual Received Difference Oct-11 5167+162 Nov-11 6169+163 Dec-11 3172+169 Jan-12 8190+182 25

29 Next Steps  Board of Supervisors to Schedule Discussion on Funding Mechanism Should the Board of Supervisors Direct Construction these Steps would Follow:  Enter State Public Works Board Process  Develop County/State Agreements for Jail Expansion Project  Due Diligence  Submittal of 30% Schematic & 50% Design Development Documents  100% Construction Documents (March 2012)  Procurement  Construction  Hiring  Occupancy  Facility Test/Shakedown/Staff Training  Move-In 26

30 Occupancy Plan  Housing units will be opened based on the projected 6.233% annual increase in inmate population (Combination of a 4.48% increase trend in San Joaquin County’s inmate population, and a 1.753% increase resulting from AB109 realignment)  Year 1 open (2) housing units  Year 2 open (1) additional housing unit  Year 3 open (1) additional housing unit  Year 4 no housing unit projected to open  Year 5 open (1) additional housing unit  Year 6 open (1) additional housing unit  Year 7 open (2) additional housing unit  Year 8 open (1) additional housing unit  Year 9 open (1) additional housing unit 27

31 Jail Expansion Staffing (Additional Staffing per Fiscal Year) Sheriff’s Office Budget Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 #of Pods Opened2344568910 Correctional Staff9517 2216151615 0 Records Division14341121221 Central Services7000030000 Info Services1000000000 Annual Staffing Increase: 117202123172017 1 The staffing requirements correlate with the projected 6.233% increase in inmate population. 4.48% -increase trend in San Joaquin County’s inmate population 1.753% -increase resulting from AB109 realignment 6.233% 28

32 10 Year Sheriff’s Office Staffing and Operational Cost Projection YearSheriff’s Office Budget Operational Costs Annual Increase Total 1 $13,149,318$3,048,934$16,198,252 2 $15,978,884$3,928,135$3,708,767$19,907,019 3 $18,977,608$4,925,095$3,995,684$23,902,703 4 $22,804,500$5,889,429$4,791,226$28,693,929 5 $25,827,143$6,987,588$4,120,802$32,814,731 6 $29,235,183$8,291,805$4,712,257$37,526,988 7 $32,655,354$9,589,932$4,718,298$42,245,286 8 $36,211,679$11,166,957$5,133,350$47,378,636 9 $39,984,111$12,713,192$5,318,667$52,697,303 10 $41,533,430$13,707,173$2,543,300$55,240,603 Inflation Factor of 3.65% (Based on the Consumer Price Index 1980-2010) 29

33 Questions? 30


Download ppt "UPDATE – FEBRUARY 2012 Jail Expansion & Infrastructure Construction Project."