North-East Northamptonshire Project Highlight Report No. 2 Period October 15 th to October 31 st 2014 Thursday October 30 th 2014.

Similar presentations


Presentation on theme: "North-East Northamptonshire Project Highlight Report No. 2 Period October 15 th to October 31 st 2014 Thursday October 30 th 2014."— Presentation transcript:

1 North-East Northamptonshire Project Highlight Report No. 2 Period October 15 th to October 31 st 2014 Thursday October 30 th 2014

2 North-East Northamptonshire A. Buildings Workstream (i)Kings Cliffe - Design meeting with school, (October 17 th ) - Feasibility report completed. - Governors and school have signed-off feasibility report, (October 24 th ) - Site plan for new school in place - School layout now plan completed - Site surveys commissioned. (ii) Polebrook - Feasibility study and outline proposals now completed - Scheme is for new classroom and corridor link - Refurbish ICT room to form library / group room - Refurbish area for staff room - Presented to Head and school have signed-off the proposals - Alternative layout suggested by school has been developed and is cost neutral - Scope for interim arrangements for September 2015 in development - Interim works to be undertaken as school’s based project - Site surveys commissioned

3 North-East Northamptonshire A.Buildings Workstream (iii) Trinity Aldwincle - Feasibility study and outline proposals now completed - Presented to Head and school have signed-off the proposals - Scheme involves construction of four new classrooms and an expansion to the hall - Existing space to be refurbished and used as a library - Scope for interim arrangements for September 2015 in development - Interim works to be commissioned as school based project - Site surveys commissioned (iv) Thrapston - Works are predominantly refurbishment of existing school - No significant new build of classrooms required - Works will include covered play area and additional toilets - Scope and feasibility to be finalised and agreed with school

4 North-East Northamptonshire A.Buildings Workstream (v)Titchmarsh - Feasibility study and outline proposals now completed - Presented to Head and school have signed-off the proposals - Scheme consists of two new classrooms, break out space and WC’s - Increase in staff room size - Modify existing entrance to the school - Proposal for school to use existing spare capacity in the school - Meeting with Head on October 17 th to discuss potential to utilise school hall as a learning space as part of interim arrangements for September 2015 (vi) Nassington - Feasibility study and outline proposals now completed - Presented to Head and school have signed-off the proposals - Scheme consists of new classroom, staff room and corridor - Refurbish existing staff room and head’s office to form new classroom - Convert ICT room to create general classroom - Refurbish existing space to form library, group area and head’s office - Alternate layout presented by school considered and rejected due to loss of playground space - Scope for interim arrangements for September 2015 in development - Interim works to be commissioned as school based project

5 North-East Northamptonshire A.Buildings Workstream (vii) Oundle - Proposal is for primary school to move into the middle school buildings - Extensive refurbishment of the existing building to address condition - Works to be funded by capital receipt from the sale of part of the site - Internal survey of school now arranged for October Half-Term week (viii) Glapthorn - Scheme for an additional classroom - In dialogue with school on proposals - Concerns over use and suitability of the house on school land - Conversion of the house may generate change of use issues from a planning perspective - Scheme to be re-worked around new build rather than using school house (ix) Warmington - Feasibility study and outline proposals now completed - Scheme for new classroom and Head’s Office - Refurbish existing spaces to form group room, lobby and office - Presented to Head and school have signed-off the proposals - Scope for interim arrangements for September 2015 in development - Interim works to be commissioned as a school based project

6 North-East Northamptonshire A.Buildings Workstream (x) Prince William School - Further design work undertaken on Science Block - Architects producing outline plans for Science Block - Alternative proposals for extending Coach Park discussed at length with school - Requirement will be for an additional four coach bays by September 2015 - Proposals for extended staff car park also in development with school - Intention is to provide permanent solution for parking rather than implement an interim solution if practicable - School requirements for interim works for ICT suite have now been identified - Engagement with school on Dining Area, Music and Performance Space has now taken place, (October 29 th ) - Architects to draw up layout and plans for Dining Area, Music and Performance Spaces - Site Survey commissioned at school for half-term week - Internal NCC business case for use of Government Commerce Framework has been established - Proposal for an Open Day for providers to be set up at the school for November 10 th 2014 - Early engagement with highways required to ensure deadlines are met for planning - Data audit and initial analysis undertaken for change in traffic flows ahead of engagement with highways - Requirements for interim accommodation determined Six Double Classroom units plus an additional open space (equivalent to double classroom unit circa 120m 2 )

7 North-East Northamptonshire A.Buildings Workstream Planned Outcomes for Next Period to November 14 th 2014 (i)Project Level Risk and Issue Logs to be formalised (ii)Proposals and Feasibility Studiesfor Glapthorn, Oundle and Thrapston to be completed (iii)Surveys of existing school sites to be completed and outcomes collated (iv)Formal specification of requirements for interim accommodation to be completed for Prince William School (v)Commencement of procurement of temporary accommodation for Prince William School (vi)Coach Park, ICT suite and Dining Hall Interim works to be fully scoped and designed for Prince William School (vii)Science Block layout drawings to be completed (viii)Music, Performance and Dining Spaces to be formally specified and layouts produced (ix)All interim works for September 2015 to be scoped and defined for each school in North-East Northants programme (x) Funding for interim works to be determined and allocated to individual schools


Download ppt "North-East Northamptonshire Project Highlight Report No. 2 Period October 15 th to October 31 st 2014 Thursday October 30 th 2014."