Bryan Station Middle – Renovation Architect: Clotfelter-Samokar Architects General Contractor: Preston Construction Group Substantial Completion Date:August,

Similar presentations


Presentation on theme: "Bryan Station Middle – Renovation Architect: Clotfelter-Samokar Architects General Contractor: Preston Construction Group Substantial Completion Date:August,"— Presentation transcript:

1 Bryan Station Middle – Renovation Architect: Clotfelter-Samokar Architects General Contractor: Preston Construction Group Substantial Completion Date:August, 2010 Contract Sum:$10,769,400 Change Orders to Date (1):$8,667 Current Phase:1A (On Schedule) Estimated Completion:29% August 2009

2 Bryan Station Middle – Renovation Rendering of Final Façade August 2009

3 Bryan Station Middle – Renovation Work Completed in Last 30 Days: Cafeteria prepared for student use. Finishes and HVAC completed in this area. Corridors barricaded from construction areas and safe egress signs put in place. New sanitary sewer lines nearly complete. New kitchen and kitchen dock work progressing. Current Work Effort (August): Installing new HVAC rooftop equipment. Installing footers for new Music Suite addition at rear of building. Concentrate on library renovation for turnover to owner as soon as possible. Repair Wood gym floor. August 2009

4 Bryan Station Middle – Renovation Foundations for New Addition Earthwork Prep for New Addition August 2009 Concrete Poured at New DockCafé Prior to New Floor