BSBPMG503A Manage Project Time 6.2 Sequence Activities Adapted from PMBOK 4 th Edition InitiationPlanning ExecutionClose Monitor Control The process of.

Similar presentations


Presentation on theme: "BSBPMG503A Manage Project Time 6.2 Sequence Activities Adapted from PMBOK 4 th Edition InitiationPlanning ExecutionClose Monitor Control The process of."— Presentation transcript:

1 BSBPMG503A Manage Project Time 6.2 Sequence Activities Adapted from PMBOK 4 th Edition InitiationPlanning ExecutionClose Monitor Control The process of identifying and documenting relationships between the project activities Every activity, except the first and last, must be connected to at least one predecessor and one successor Milestones are generally connected to predecessor and successor activities with some exceptions, particularly when the milestone denotes an external dependency or a major event that is outside of the project Simplified by using project management software Occurs during Planning

2 BSBPMG503A Manage Project Time 6.2 Sequence Activities Adapted from PMBOK 4 th Edition Inputs to Sequence Activities Activity List and Attributes Milestone List Project Scope Statement Work Breakdown Structure Learning from past projects Tools and techniques to Sequence Activities Lead & Lag Times (advanced technique) Schedule Templates Precedence Diagramming Dependency Determination

3 BSBPMG503A Manage Project Time Precedence Diagramming Method This is one of the key techniques used to sequence activities in projects It has become an industry standard and underpins project management software that produces both GANTT and PERT charts Defines 4 types of logical relationships between activities 1.Finish-to-start (FS) 2.Finish-to-finish (FF) 3.Start-to-start (SS) 4.Start-to-finish (SF) Adapted from PMBOK 4 th Edition InitiationPlanning ExecutionClose Monitor Control

4 BSBPMG503A Manage Project Time Application of Interdependencies Rule of Thumb Application Finish to Start95% Start to Start2.5% Finish to Finish2.5% Start to FinishNot applicable Many finish to start relationships are used in sequencing activities Start to start and finish to finish are sometimes used to assist with planning

5 BSBPMG503A Manage Project Time Finish-to-Start Relationships The initiation of the successor activity depends on the completion of the predecessor activity Translated this means…the start of the second activity is dependent on the completion of the first activity In a GANTT chart this is depicted as an arrow from the end of the first activity pointing to the start of the second activity Most common type of logical relationship between activities, sometimes this is a mandatory dependency, but often it is a preference for planning purposes Adapted from PMBOK 4 th Edition Activity 1 Activity 2 Finish-to-start

6 BSBPMG503A Manage Project Time Finish-to-Finish Relationships Adapted from PMBOK 4 th Edition The completion of the successor activity depends on the completion of the predecessor activity Translated this means…the completion of the second activity is dependent on the completion of the first activity It does not necessarily mean that both activities need to finish at the same time In a GANTT chart this is depicted as an arrow from the end of the first activity pointing to the end of the second activity Activity 1 Activity 2 Finish-to-finish

7 BSBPMG503A Manage Project Time Start-to-Start Relationships The initiation of the successor activity depends on the initiation of the predecessor activity Translated this means…the first activity must start before the second activity can start Many people incorrectly assume that the activities need to start at the same time In a GANTT chart this is depicted as an arrow from the start of the first activity pointing to the start of the second activity Adapted from PMBOK 4 th Edition Activity 1 Activity 2 Start-to-start

8 BSBPMG503A Manage Project Time Start-to-Finish Relationships The completion of the successor activity depends on the initiation of the predecessor activity Translated this means…the second activity can’t finish until the first activity starts Very RARE and not available in some project management software, can normally be replanned as a finish to start relationship In a GANTT chart this is depicted as an arrow from the start of the first activity pointing to the end of the second activity Adapted from PMBOK 4 th Edition Activity 1 Activity 2 Start-to-finish

9 BSBPMG503A Manage Project Time Example Relationships Finish-to-startFinish-to-finish This means Activity A must finish before Activity B can finish. Assume you’re cooking dinner and you want the turkey to finish cooking before the potatoes. Activity A is “Cook turkey” Activity B is “Cook potatoes” The finish-to-finish relationship says that the turkey must finish cooking (activity A) before the potatoes finish cooking (activity B). This relationship is based on the end times. They can each start whenever they need to, as long as they finish in this order. This means that Activity B cannot start until Activity A has completed. This is by far the most common relationship between multiple activities. Activity A is “Create the Project Charter” Activity B is “Obtain Project Charter approval from the Project Sponsor” This finish-to-start relationship would say that we must create the Project Charter before we obtain Project Charter approval from the Project Sponsor This means Activity A must start before Activity B can start. Assume that you are having your walls painted in one room and wallpaper is being hung in another room. You want to minimize the total disruption by having both activities happen at the same time. Activity A is “Paint the walls” Activity B is “Hang the wallpaper” The wallpaper hangers may be ready to go (activity B). However, the start-to-start relationship says that they cannot start until the painting starts (activity A). This relationship is based on the activity start times. The end times of each activity are not related and, in fact, one activity could end at a much later time than the other. Let’s assume that you want to fertilize your garden, but the plants must all be wet when the fertilizer is applied. Activity A is to “fertilize the garden.” Activity B is to “water the garden” The start-to-finish relationship says we need to start watering the garden (activity B) first to get the plants wet. This activity must continue until the fertilizing starts (activity A). This will ensure the plants remain wet until the fertilizer is ready to be applied. Note that you can start watering at any time and you can finish fertilizing at any time. The relationship only ties the start of activity A to the completion of activity B. Start-to-startStart-to-finish

10 BSBPMG503A Manage Project Time Types of Dependencies Mandatory Contractually required or inherent in the nature of the work Often involve physical limitations Discretionary Based on preferences and knowledge of best practice Can be reviewed if fast tracking of project schedules is required External A relationship between project activities and activities outside of the project and outside of the project team’s control Often regulatory Adapted from PMBOK 4 th Edition InitiationPlanning ExecutionClose Monitor Control

11 BSBPMG503A Manage Project Time 6.2 Sequence Activities Adapted from PMBOK 4 th Edition InitiationPlanning ExecutionClose Monitor Control Outputs of this process include – Draft Project Schedule – Most Common –High level project schedule with phases, deliverables, activities and interdependencies Project Network Diagrams –High level PERT chart excluding time estimates, shows interdependencies between all activities Project Document Updates –Changes to Activity Lists and Attributes –Changes to the Risk Register –Changes to the Work Breakdown Structure –Changes to Project Scope via Change Requests


Download ppt "BSBPMG503A Manage Project Time 6.2 Sequence Activities Adapted from PMBOK 4 th Edition InitiationPlanning ExecutionClose Monitor Control The process of."