FUNDED BY THE EUROPEAN COMMISSION S ustainable and C leaner Production in the Manufacturing I ndustries of Pak istan SCI-Pak Mar 2009- Feb 2012.

Similar presentations


Presentation on theme: "FUNDED BY THE EUROPEAN COMMISSION S ustainable and C leaner Production in the Manufacturing I ndustries of Pak istan SCI-Pak Mar 2009- Feb 2012."— Presentation transcript:

1 FUNDED BY THE EUROPEAN COMMISSION S ustainable and C leaner Production in the Manufacturing I ndustries of Pak istan SCI-Pak Mar 2009- Feb 2012

2  Lack in knowledge (energy wastages and energy saving potential)  Untrained and uneducated human resources  Old, inefficient, discarded machines  Lack in monitoring aptitude  Inefficient in resource consumption (water, chemicals, energy)  Improper maintenance and upkeep

3 Fuel (Natural Gas) Electricity Water Steam

4

5

6 More than 30% Reduction in Energy bills 70% 30%

7 Reuse of cooling water (compressor, pumps, therm oil heaters, chillers, singeing, jets, kiers) (Savings-Rs. 50,000-100,000/year) Payback 6 to 12 months

8 Minimize by increasing temperature

9 Fixed O2 Analyzer Portable Stack gas Analyzers Savings 5-10% boiler fuel savings (1% excess oxygen reduction in stack gas saves approximately 1% fuel)

10 1 ft 2 heating surface area = 3 kg steam/hr

11 Savings-Rs. 100,000/year-leak control Payback 2 months

12 Savings-Rs. 4,000-5,000/year-m Payback 6 months

13

14

15 RO plant for water treatment Water Softening Plant 1 mm thick scale in boiler increases 3 % fuel consumption

16 Recovery of heat from hot wastewater (Savings-Rs. 900,000-1,000,000/year) payback 6 months (Also De-scale properly)

17 Recovery of heat from exhaust gases of steam boiler, therm oil heaters, generators (Savings-Rs. 1,800,000-2,000,000/year) Payback 6 months

18 Every 22 °C reduction in stack gases will increase efficiency of heater by 1% Install Economizer to recover heat from thermal heater stack gases

19 Pay Back Less than one year

20 Pay back 6-8 months

21 Pay Back 7-10 months

22  Type, alignment, placement  Investment  Nominal for repairing  Rs. 5,000-20,000 for trap replacement  Savings  40,000-50,000 per year per steam trap  Pay back 3 months

23

24

25

26

27

28

29

30

31

32 Characteristics (FT, IB, TD) Condensate dischargeContinuous Intermittent Energy conservationExcellent Poor Corrosion resistantExcellent Resistance to wearsExcellent Poor Ability to vent airExcellentPoor Handling of startup air loadExcellentFairPoor Operation against back pressureExcellent Poor Performance against light loadExcellent Poor Response to slug of condensateImmediate Delayed Ability to purge systemFairExcellent Failure conditionCloseOpen Dirt handlingPoorExcellentPoor Handling to flash steamPoorFairPoor Resistance to hydraulic shocksPoorExcellent Resistance to freezing damage PoorGood Comparative Physical SizeLarge Small

33 Pay Back within one year

34 Countercurrent washing sequence (bleaching, mercerization, dyeing etc.) (Savings-Rs. 800,000-1,000,000/year-machine) Payback 1 months

35

36 Reuse of steam condensate as boiler feed water (Savings-Rs. 500,000-600,000/year) Payback 8 months

37 Replace T12(40W) Tube Lights with T8(36W) (electronic Chock) Pay Back 5 ~6 Months

38  Replace Class III Motors with Class I Motors Payback is 1 ~2 years

39 Leakage monitoring and control  Immediate Pay back Pressure Optimization Variable Speed Drive (VSD)  Pay back 1 year Use cool dry air at suction o 5 o C reduction in suction air temp-1% reduction in power Replacement of piston compressor with screw compressor Small diameter hose for cleaning