Presentation is loading. Please wait.

Presentation is loading. Please wait.

Operations and Supply Chain Management, 8th Edition

Similar presentations


Presentation on theme: "Operations and Supply Chain Management, 8th Edition"— Presentation transcript:

1 Operations and Supply Chain Management, 8th Edition
Chapter 15 Resource Planning Russell and Taylor Operations and Supply Chain Management, 8th Edition

2 Lecture Outline Material Requirements Planning (MRP) – Slide 4
Capacity Requirements Planning (CRP) – Slide 45 Enterprise Resource Planning (ERP) – Slide 58 Customer Relationship Management (CRM) – Slide 63 Supply Chain Management (SCM) – Slide 64 Product Lifecycle Management (PLM) – Slide 65 © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

3 Learning Objectives Discuss the differences between independent and dependent demand systems Describe the inputs and outputs to an MRP system, and execute the MRP process Determine resource capacity and load percent, and perform load leveling on capacitated resources Explain the hierarchical planning process for resources as a closed loop system, and discuss the assumptions on which this process is based Describe basic ERP systems and the scope of their implementations, including the connection to SCM, CRM and PLM Discuss the issues, advantages and drawbacks of the enterprise IT software systems that run today’s global businesses © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

4 Resource Planning for Manufacturing
© 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

5 Material Requirements Planning (MRP)
Computerized inventory control and production planning system When to use MRP? Dependent demand items Discrete demand items Complex products Job shop production Assemble-to-order environments © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

6 Demand Characteristics
Week 400 – 300 – 200 – 100 – No. of tables Continuous demand M T W Th F M T W Th F Discrete demand Independent demand 100 tables Dependent demand 100 x 1 = 100 tabletops 100 x 4 = 400 table legs © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

7 Material Requirements Planning
© 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

8 MRP Inputs and Outputs Inputs Outputs Master production schedule
Product structure file Item master file Outputs Planned order releases Work orders Purchase orders Rescheduling notices © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

9 Master Production Schedule
Drives MRP process with a schedule of finished products Quantities represent production not demand Quantities may consist of a combination of customer orders and demand forecasts Quantities represent what needs to be produced, not what can be produced Quantities represent end items that may or may not be finished products © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

10 Master Production Schedule
Cumulative lead time total length of time needed to manufacture a product Time fence Management-specified date within which no changes are allowed in the MPS © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

11 Product Structure Product structure file Bill of Material
contains computerized bill of material for every item produced Bill of Material list of all materials, parts and assemblies needed to make an item includes quantities, parent-component relationships & order quantities © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

12 Master Production Schedule
PERIOD MPS ITEM Pencil Case Clipboard Lapboard Lapdesk © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

13 Product Structures © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

14 Product Structure Tree
© 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

15 Product Structure © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

16 Multilevel Indented BOM
Clipboard ea 1 Clip Assembly ea 1 Top Clip ea 1 Bottom Clip ea 1 Pivot ea 1 Spring ea 1 Rivet ea 2 Press Board ea 1 LEVEL ITEM UNIT OF MEASURE QUANTITY © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

17 Specialized BOMs Phantom bills K-bills (kit numbers)
Transient subassemblies Never stocked Immediately consumed in next stage K-bills (kit numbers) Group small, loose parts under pseudo-item number Reduces paperwork, processing time, and file space © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

18 Specialized BOMs Modular bills
Plan production of products with many optional features Product assembled from major subassemblies and customer options Modular bill kept for each major subassembly Simplifies forecasting and planning X10 automobile example 3 x 8 x 3 x 8 x 4 = 2,304 configurations = 26 modular bills © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

19 Modular BOMs © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

20 Time-phased Bills An assembly chart shown against a time scale
© 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

21 Time-phased Bills Forward scheduling Backward scheduling
start at today‘s date and schedule forward to determine the earliest date the job can be finished. If each item takes one period to complete, the clipboards can be finished in three periods Backward scheduling start at the due date and schedule backwards to determine when to begin work. If an order for clipboards is due by period three, we should start production now © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

22 Item Master File DESCRIPTION INVENTORY POLICY
Item Pressboard Lead time 1 Item no Annual demand 5000 Item type Purch Holding cost 1 Product/sales class Comp Ordering/setup cost 50 Value class B Safety stock 0 Buyer/planner RSR Reorder point 39 Vendor/drawing EOQ 316 Phantom code N Minimum order qty 100 Unit price/cost 1.25 Maximum order qty 500 Pegging Y Multiple order qty 1 LLC 1 Policy code 3 © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

23 Item Master File PHYSICAL INVENTORY USAGE/SALES
On hand 150 YTD usage/sales 1100 Location W142 MTD usage/sales 75 On order 100 YTD receipts 1200 Allocated 75 MTD receipts 0 Cycle 3 Last receipt 8/25 Last count 9/5 Last issue 10/5 Difference -2 Cost acct Routing 00326 Engr 07142 PHYSICAL INVENTORY USAGE/SALES CODES © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

24 MRP Processes Exploding the bill of material Netting out the inventory
the process of subtracting on-hand quantities and scheduled receipts from gross requirements to produce net requirements Lot sizing determining the quantities in which items are usually made or purchased Time-phasing requirements © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

25 MRP Matrix © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

26 MRP Example Master Production Schedule 1 2 3 4 5
Clipboard Lapdesk Item Master File CLIPBOARD LAPDESK PRESSBOARD On hand On order 175 (Period 1) 0 0 (sch receipt) LLC 0 0 1 Lot size L4L Mult 50 Min 100 Lead time 1 1 1 Master Production Schedule © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

27 MRP Example © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

28 MRP - 1 ITEM: CLIPBOARD LLC: 0 PERIOD LOT SIZE: L4L LT: 1 1 2 3 4 5
Gross Requirements Scheduled Receipts 175 Projected on Hand 25 Net Requirements Planned Order Receipts Planned Order Releases © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

29 MRP - 2 (25 + 175) = 200 units available
ITEM: CLIPBOARD LLC: 0 PERIOD LOT SIZE: L4L LT: Gross Requirements Scheduled Receipts 175 Projected on Hand Net Requirements 0 Planned Order Receipts Planned Order Releases ( ) = 200 units available ( ) = 115 on hand at the end of Period 1 © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

30 MRP - 3 ITEM: CLIPBOARD LLC: 0 PERIOD LOT SIZE: L4L LT: Gross Requirements Scheduled Receipts 175 Projected on Hand Net Requirements 0 0 Planned Order Receipts Planned Order Releases 115 units available ( ) = 20 on hand at the end of Period 2 © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

31 MRP - 4 ITEM: CLIPBOARD LLC: 0 PERIOD LOT SIZE: L4L LT: Gross Requirements Scheduled Receipts 175 Projected on Hand Net Requirements Planned Order Receipts Planned Order Releases 100 20 units available ( ) = -100 — 100 additional Clipboards are required Order must be placed in Period 2 to be received in Period 3 © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

32 MRP - 5 ITEM: CLIPBOARD LLC: 0 PERIOD LOT SIZE: L4L LT: Gross Requirements Scheduled Receipts 175 Projected on Hand Net Requirements Planned Order Receipts Planned Order Releases Following the same logic Gross Requirements in Periods 4 and 5 develop Net Requirements, Planned Order Receipts, and Planned Order Releases © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

33 MRP - 6 ITEM: LAPDESK LLC: 0 PERIOD LOT SIZE: MULT 50 LT: 1 1 2 3 4 5
Gross Requirements Scheduled Receipts Projected on Hand 20 Net Requirements Planned Order Receipts Planned Order Releases © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

34 MRP - 7 ITEM: LAPDESK LLC: 0 PERIOD LOT SIZE: MULT 50 LT: Gross Requirements Scheduled Receipts Projected on Hand Net Requirements Planned Order Receipts Planned Order Releases Following the same logic, the Lapdesk MRP matrix is completed as shown © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

35 MRP - 8 ITEM: CLIPBOARD LLC: 0 PERIOD LOT SIZE: L4L LT: 1 1 2 3 4 5
ITEM: PRESSBOARD LLC: 0 PERIOD LOT SIZE: MIN 100 LT: Gross Requirements Scheduled Receipts Projected on Hand 150 Net Requirements Planned Order Receipts Planned Order Releases ITEM: CLIPBOARD LLC: 0 PERIOD LOT SIZE: L4L LT: Planned Order Releases ITEM: LAPDESK LLC: 0 PERIOD LOT SIZE: MULT 50 LT: Planned Order Releases © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

36 MRP – 9 x1 x1 x1 x2 x2 ITEM: CLIPBOARD LLC: 0 PERIOD
LOT SIZE: L4L LT: Planned Order Releases x1 x1 x1 ITEM: LAPDESK LLC: 0 PERIOD LOT SIZE: MULT 50 LT: Planned Order Releases x2 x2 ITEM: PRESSBOARD LLC: 0 PERIOD LOT SIZE: MIN 100 LT: Gross Requirements Scheduled Receipts Projected on Hand 150 Net Requirements Planned Order Receipts Planned Order Releases © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

37 MRP – 10 x1 x1 x1 x2 x2 ITEM: CLIPBOARD LLC: 0 PERIOD
LOT SIZE: L4L LT: Planned Order Releases x1 x1 x1 ITEM: LAPDESK LLC: 0 PERIOD LOT SIZE: MULT 50 LT: Planned Order Releases x2 x2 ITEM: PRESSBOARD LLC: 0 PERIOD LOT SIZE: MIN 100 LT: Gross Requirements Scheduled Receipts Projected on Hand Net Requirements Planned Order Receipts Planned Order Releases © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

38 MRP - 11 PERIOD ITEM 1 2 3 4 5 Clipboard 100 100 100 Lapdesk 50 50
Pressboard Planned Order Report © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

39 Lot Sizing in MRP Systems
Lot-for-lot ordering policy Fixed-size lot ordering policy Minimum order quantities Maximum order quantities Multiple order quantities Economic order quantity Periodic order quantity © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

40 Advanced Lot Sizing Rules: L4L
Total cost of L4L = (4 X $60) + (0 X $1) = $240 © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

41 Advanced Lot Sizing Rules: EOQ
minimum order quantity Total cost of EOQ = (2 X $60) + [( ) X $1)] = $220 © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

42 Advanced Lot Sizing Rules: POQ
periods worth of requirements Total cost of POQ = (2 X $60) + [( ) X $1] = $180 © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

43 Planned Order Report Item #2740 Date 9 - 25 - 05
On hand 100 Lead time 2 weeks On order 200 Lot size 200 Allocated 50 Safety stock 50 SCHEDULED PROJECTED DATE ORDER NO. GROSS REQS. RECEIPTS ON HAND ACTION 50 9-26 AL 9-30 AL 10-01 GR 10-08 SR Expedite SR 10-01 10-10 CO 10-15 GR 10-23 GR 10-27 GR Release PO 10-13 Key: AL = allocated WO = work order CO = customer order SR = scheduled receipt PO = purchase order GR = gross requirement © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

44 MRP Action Report ITEM DATE ORDER NO. QTY. ACTION Current date 9-25-08
# Expedite SR 10-01 # Move forward PO 10-07 # Move forward PO 10-05 # Move backward PO 10-25 # De-expedite SR 10-30 # Release PO 10-13 # Release WO 10-24 Current date © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

45 Capacity Requirements Planning (CRP)
Creates a load profile Identifies under-loads and over-loads Inputs Planned order releases Routing file Open orders file © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

46 CRP © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

47 Calculating Capacity Maximum capability to produce Rated Capacity
Theoretical output that could be attained if a process were operating at full speed without interruption, exceptions, or downtime Effective Capacity Takes into account the efficiency with which a particular product or customer can be processed and the utilization of the scheduled hours or work Effective Daily Capacity = (no. of machines or workers) x (hours per shift) x (no. of shifts) x (utilization) x ( efficiency) © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

48 Calculating Capacity Utilization Efficiency Load Load Percent
Percent of available time spent working Efficiency How well a machine or worker performs compared to a standard output level Load Standard hours of work assigned to a facility Load Percent Ratio of load to capacity Load Percent = x 100% load capacity © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

49 Load Profiles Graphical comparison of load versus capacity
Leveling underloaded conditions: Acquire more work Pull work ahead that is scheduled for later time periods Reduce normal capacity Load leveling Process of balancing underloads and overloads © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

50 Reducing Over-load Conditions
Eliminate unnecessary requirements Reroute jobs to alternative machines, workers, or work centers Split lots between two or more machines Increase normal capacity Subcontract Increase efficiency of the operation Push work back to later time periods Revise master schedule © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

51 Copy Courier Two high-speed copiers that can be operated by one operator. 2 shifts per day 8 hours/shift , 5 days/week. No breaks during the day 30 minutes for lunch or dinner Machine service time = 30 minutes at the beginning of each shift Machine efficiency = 90%. Capacity 2 copiers * 2 shifts * 8 hrs/day * 7/8 utilization * .90 efficiency = 1512 minutes/day © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

52 Copy Courier Job No. of Setup Time Run Time Copies (min) (min/unit) © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

53 Load Calculations Job Setup + Run x No. Copies Job Time (500 X 0.08) = (1000 X 0.10) = (5000 X 0.12) = (4500 X 0.14) = (2000 X 0.10) = , min © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

54 Loading Capacity 2 copiers * 2 shifts * 8 hrs/day * 7/8 utilization * .90 efficiency = 1512 minutes/day Load percent = /1512 = X 100% = 106.8% Overloaded by 6.8%. Extends working day by approximately 36 minutes Load percent = 99%. Increase efficiency to 97%. © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

55 Initial Load Profile © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

56 Adjusted Load Profile © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

57 Relaxing MRP Assumptions
Material is not always the most constraining resource Lead times can vary Not every transaction needs to be recorded Shop floor may require a more sophisticated scheduling system Scheduling in advance may not be appropriate for on-demand production. © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

58 Enterprise Resource Planning (ERP)
Software that organizes and manages a company’s business processes by sharing information across functional areas integrating business processes facilitating customer interaction providing benefit to global companies © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

59 Organizational Data Flows
© 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

60 ERP’s Central Database
© 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

61 Selected Enterprise Software Vendors
© 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

62 ERP Implementation Analyze business processes
Choose modules to implement Which processes have the biggest impact on customer relations? Which process would benefit the most from integration? Which processes should be standardized? Align level of sophistication Finalize delivery and access Link with external partners © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

63 Customer Relationship Management (CRM)
Software that Plans and executes business processes Involves customer interaction Changes focus from managing products to managing customers Analyzes point-of-sale data for patterns used to predict future behavior © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

64 Supply Chain Management
Software that plans and executes business processes related to supply chains Includes Supply chain planning Supply chain execution Supplier relationship management Distinctions between ERP and SCM are becoming increasingly blurred © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

65 Product Lifecycle Management (PLM)
Software that Incorporates new product design and development and product life cycle management Integrates customers and suppliers in the design process though the entire product life cycle © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

66 ERP and Software Systems
© 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

67 Connectivity Application programming interfaces (APIs)
give other programs well-defined ways of speaking to them Enterprise Application Integration (EAI) solutions EDI is being replaced by XML, business language of Internet Service-oriented architecture (SOA) collection of “services” that communicate with each other within software or between software © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e

68 Copyright 2014 John Wiley & Sons, Inc. All rights reserved
Copyright 2014 John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work beyond that permitted in section 117 of the 1976 United States Copyright Act without express permission of the copyright owner is unlawful. Request for further information should be addressed to the Permission Department, John Wiley & Sons, Inc. The purchaser may make back-up copies for his/her own use only and not for distribution or resale. The Publisher assumes no responsibility for errors, omissions, or damages caused by the use of these programs or from the use of the information herein. © 2014 John Wiley & Sons, Inc. - Russell and Taylor 8e


Download ppt "Operations and Supply Chain Management, 8th Edition"

Similar presentations


Ads by Google