Presentation is loading. Please wait.

Presentation is loading. Please wait.

Characteristics of projects in EU research programmes

Similar presentations


Presentation on theme: "Characteristics of projects in EU research programmes"— Presentation transcript:

1 Characteristics of projects in EU research programmes
Kai Tullius DG Information Society and Media Unit E2 04/01/2006

2 Outline of Presentation
Project Selection Process Contract overview Overview of reporting & financing Reporting Review Costs / Receipts Payment Audit certificates Amendments Collective Responsibility Conclusions

3 Project Selection Process
Procedure Call for proposals Submission Evaluation by external experts Hearing for IPs Negotiation

4 Contract Overview Contract – between whom?
Between EC and co-ordinator (the legal representative of the consortium) All contractors must accede within time limit specified in contract (30 days) from the date of the signature More than before, the co-ordinator is the legal link between the EC and the consortium 04/01/2006

5 Contract Overview Consortium agreement in place, EC contract takes precedence in case of conflicts Should cover issues: Decision-making process and dispute settling IPR Payment modalities between partners Global Risk Management

6 Adjusted pre-financing Adjusted pre-financing Initial pre-financing
Contract Overview Months Payment & Reporting Schedule (IP) Reporting Accepted costs Reporting Detailed work plan Accepted costs Adjusted pre-financing Reporting Accepted costs Detailed work plan Adjusted pre-financing Detailed work plan Initial pre-financing

7 Reporting 45 days after end of each reporting period
Annual Activity Report Annual Management Report Report on the distribution between contractors of the Community financial contribution Any additional report defined in Annexes Updated Implementation Plan (IP only) Financial Statements (Form C) and Audit Certificates (if applicable) Final period: all + Final Activity Report covering the full duration Final management report covering the full duration. Any additional report defined in annexes. Report on the final financial distribution (60 days after receiving it)

8 Annual Review Review is a contractual requirement to be carried out after each reporting period - successful outcome required for payment Review is based on: Reports and Deliverables (technical objectives timely achieved with adequate quality?) Resources deployed appropriate? Annual Management Report proposal for update to Implementation Plan (IP)

9 Costs / Receipts Cost basis FC/FCF/AC Direct/indirect Costs
AC participants cannot charge costs of permanent staff (except for management) Direct/indirect Costs Eligible/ineligible eligible = economic and necessary No reckless expenditure no sub-contracting unless specified in Technical Annex, except for minor tasks (services, brochures, audit certificates) ineligible costs include bank interest, losses etc. in general, follow your internal rules and practices must be auditable -> document carefully Receipts have to be declared

10 Payment Pre-financing max. 80% of estimated cost of first 18 months
Next payment within 45 days of approval of annual activity reports Payment for a period normally combined with pre-financing for next period Usual provisions concerning suspension of payment terms due to missing/incomplete information etc. Receipts reduce grant and must be declared in cost claims.

11 Audit Certificates Audit certificates (depending on contract)
Free to chose auditor (no need for tendering…) Independent, external auditor, qualified to national regulations – exception: “Competent public officer” for public bodies Certify that costs incurred during period meet the conditions required by the contract, should expressly state amounts verified make early contract with your external auditor establish with him how to submit cost claims/certificates 45 days after end of period - continuous assessment process? Payments supported by audit certificates are final except in case of fraud, over-charging etc. Cost of audit certificates is an eligible cost (if economic!)

12 Amendments Amendments: no tacit approval
To be submitted by registered mail by an AUTHORISED signatory of the COORDINATOR with all supporting documents Request must adhere strictly to template (amendment guidelines on Cordis) May include 1 or many modifications Binary processing: everything acceptable or everything rejected

13 Collective Responsibility
1. Technical Collective Responsibility Each contractor obliged to take all necessary measures to attain the objectives of the project and to carry out the work incumbent on the defaulting contractor 2. Financial Collective Responsibility Should either the contract or participation of a contractor be terminated and any contractor does not honour the reimbursement of the amount due by that contractor, the Consortium is responsible to reimburse that amount to the Commission Amount to be recovered to be allocated between the remaining contractors in accordance with their pro rata share in the project

14 Conclusion you must deliver!! FP6 very different to FP5!
Increased responsibility for consortium all aspects - management, budget, technical work…... Expenditure/accounting according to your own, normal rules and practices no more permission requests - but you may have to justify your actions/expenditure later! Bigger projects, greater opportunity, greater risk Greater visibility and higher expectations Expect more scrutiny from tax-payer and politicians More than ever, need strong management in all areas, clear focus, effective implementation! you must deliver!!

15 Conclusion New financial regulations require strict compliance with contract and deadlines EC must also demonstrate that it has implemented contracts correctly and ensure proper use of public money especially important for annual activity reports, cost claims, audit certificates avoid delays with review and approval of programme of work/amendment for following period


Download ppt "Characteristics of projects in EU research programmes"

Similar presentations


Ads by Google