Presentation is loading. Please wait.

Presentation is loading. Please wait.

BOX PUSHING TECHNOLOGY

Similar presentations


Presentation on theme: "BOX PUSHING TECHNOLOGY"— Presentation transcript:

1 BOX PUSHING TECHNOLOGY
By - Akshit Rajan

2 Conventional method Open cut system Demerits Excavation Placing
Covering Demerits Increased time for execution Interruption in traffic Cost factor was high

3 NEED FOR THE ALTERNATIVE
Present day Intensity of Traffic, both Rail & Road due to the fast development, is very heavy it cannot the disturbed, for construction of under bridges or Canal Crossings, drainage etc by conventional i.e. open cut system. Box Pushing Technique is developed where in R.C.C. Boxes in segments are cast out side and pushed through the heavy embankments of Rail or Road by Jacking.

4 METHODOLOGY Excavation Casting of Thrust Bed
Fabrication of Front and Rear shield Box Casting and placing Pushing-shifting-pushing operation Miscellaneous works Precautions

5 Excavation and casting of Thrust Bed
Open excavation is carried out for construction of Thrust bed

6 Fabrication of Front Shield
It is fabricated for cutting action and to provide support , to prevent caving in of soil.

7 Fabrication of Rear Shield
It is provided by anchoring steel plates on the face of bottom slab of RCC box to suitably distribute the jacking load.

8 Box Casting And Pushing
The RCC Box is cast in segments of convenient lengths of Total pushing length. The Box section is designed as per IRS / IRC codes of practice for loading. Concrete grade normally kept as M- 35.  

9 Precautions Cutting edge of front shield is fabricated with adequate thickness of steel plate and the front edges of the steel plate are sharpened to facilitate penetration into the soil. To prevent caving of earth during excavation quantity of earth shall be removed to barest minimum duly following the slop of cutting edge. Guide channels to be provided in the thrust bed to guide the segments to ensure straight alignment The level of the boxes should be continuously checked. The Speed limit should be set to 20 km/h At the site of construction The work should be stopped when a train is passing over the work.

10 Photo Gallery

11

12

13 THANK YOU


Download ppt "BOX PUSHING TECHNOLOGY"

Similar presentations


Ads by Google