I-26 Safety Project. Project Corridor I-26 between I-95 and Summerville Number one and three ranked location for interstate safety improvements AADT =

Similar presentations


Presentation on theme: "I-26 Safety Project. Project Corridor I-26 between I-95 and Summerville Number one and three ranked location for interstate safety improvements AADT ="— Presentation transcript:

1 I-26 Safety Project

2 Project Corridor I-26 between I-95 and Summerville Number one and three ranked location for interstate safety improvements AADT = 32,433 Posted S/L = 70 mph Crash Stats: January 2007 through November 2011 Total Crashes = 1934 Total Fatalities = 44 Total Injuries = 709 50% Run off Road Crashes Post and Courier coined the phrase Corridor of Death in 2010 articles

3 Project Corridor

4 Project Corridor Safety Data Existing Median Width = 84 – 86 Existing Median Shoulder = 2 - 3 (paved) Distance from travel way to tree line = 25 Clear Zone Distance = 46 Berkeley Dorchester

5 Project Corridor Safety Data ** Vehicular speeds were estimated by investigating officer to be within posted speed limits.

6 Project Corridor Safety Data

7 0 I-77 US 601 I-95 FOUR HOLE SWAMP US 17 ALT US 21 US 301 CYPRESS SWAMP

8 I-26 Safety Alternatives Remove obstacles Provide clear zone clearing of median Median consists primarily of pines with light mixture of hardwoods environmental permit required Standard cable rail to be installed in center of median Initial cost estimate of $5M Would prepare median for future widening

9 I-26 Safety Alternatives Cable would be required for both directions of I-26 Initial cost estimate of $10M Considerable maintenance, repair and traffic impact concerns Shield Obstacles High tension cable rail only feasible option due to close distance of trees and existing shoulder slopes

10 Project Details Existing Conditions Total Length of project corridor – 29.6 Miles Total Length of Existing Guardrail along median– 2.2 Miles Median Length with no existing trees – 2.6 Miles Median Length with existing median cable rail – 0.9 Miles Median width occupied by trees – 36 feet maximum Wetlands within Project Limits – 4.2 Acres Overlap with Existing Projects Sheep Island Interchange I-26 Widening (Jedburg Road)

11 Preferred Alternative Details Alternative Feature Exclude median areas protected by existing guardrail Extension of existing steel beam guardrail in areas of steeper slopes 1.8 Miles of new steel beam guardrail Reduce tree impacts to only the trees necessary to allow for the installation of the guardrail Wetland impacts reduced from 4.2 to 1.9 acres SCDOT has received authorization from the Army Corps of Engineers based on these conditions

12 Preferred Alternative Details Alternative Considerations No glare shield provided Median width greater than 20 feet Can accommodate emergency crossovers and will bring up to standards with coordination with the local emergency agencies

13 Preferred Alternative Details Alternative Elements 23.0 miles of clearing, grubbing, dressing and grassing of the median ( 6 miles overlaps with the I-26 widening and Sheep Island Parkway Interchange) 24.7 miles of median cable rail 1.8 miles of new steel beam guardrail