Presentation is loading. Please wait.

Presentation is loading. Please wait.

Common Fibre Optic Infrastructure Strategies

Similar presentations


Presentation on theme: "Common Fibre Optic Infrastructure Strategies"— Presentation transcript:

1 Common Fibre Optic Infrastructure Strategies

2 LuxConnect is a private limited company setup in January 2007
The mission of LuxConnect To promote and facilitate high level ICT invests in Luxembourg Objectives Raising Luxembourg on International Internet “maps” “State of art” space available in Data Centres Interlinking countries Driver New economical pillar inside Luxembourg

3 DC 1.1 Bettembourg Space for racks: 3.000m2 In service since June 2009 6 MVA DC 1.2 Bettembourg Space for racks: 1.300m2 Active since February 2011 DC 2 Roost Space for racks: 4.800m2 Operational since April 2013 14 MVA DC 1.3 Bettembourg Space for racks: 5.480m2 Ready in July 2015 10 MVA

4 Luxembourg is connected to the German grid (Amprion) via two double HV lines
The Gas Network from Creos is interconnected to the German, French and Belgian Networks. Transport Network High Pressure (HP) : bar Distribution Network Medium Pressure(MP) : 0,1-1 bar Low Pressure(BP) : 0,01-0,1 bar High Voltage to High Voltage from 220 kV to 65 kV 5 stations High Voltage to Medium Voltage from 65 kV to 20 kV 48 stations over Luxembourg Medium Voltage to Low Voltage from 20 kV to 0,4 kV 2 428 stations

5 POWER GAS Total length of the grid 9.013,2 km Total consumption
4.887,9 GWh Border Exchanges (Import) 4.243,8 86,8 % Indigenous Production 644,1 13,2 % Number of transformers 220 kV à 65 kV 13 transformers 65 kV à 20 kV 84 20 kV à 400V 2428 Figures on POWER Network length 1.885,3 km BP/MP 1.473,3 km - HP 412 km Transported volume 13.338,5 GWh Peak Nm3/h Total capacity Total points supplied 41.140 customers Municipalities 45 municipalities Figures on GAS

6 ? Drivers Interconnecting as many as possible MV stations
No contiguous network-Hundred’s of segments Cost effective solution Accelerated rollout ? “Red” network realized – “Green” network projected Cost effective solution Accelerated rollout

7 - National fiber Network ( Dark fiber)
- > 850km of fiber optics - All kind of school and municipality buildings connected - Collective antenna sites connected - Nationwide interconnection of all Data Centers - Competitive development of dark fibre offer Actual Duct system: (only related to MV projects) 277 km of tubes 125/110mm Only segments 60 km of tubes 32mm installed (inside 125/110mm) 56 km of tubes 50mm along the Gas network 0 Stations MT/Gas interconnected via fibre optic

8 Overall beginning A B Projected link LuxConnect
MV MV A B MV Projected link LuxConnect Existing Segments from Creos MV Medium Voltage stations Projected Manholes

9 The solution 1/2 Creos implements in his segments a flatliner
in existing ducts, or in newer projects only a flatliner LuxConnect implements in his segments a flatliner 125/110mm Creos implements in the last mile sector a smaller flatliner 125/110mm

10 The solution 2/2 Creos implements only fibre optics in the
last mile sector LuxConnect is renting from Creos a third of their tubes ex. orange colored, implements their fibres optics Costs: 1m of tubes = 2m of 12 fibres optics LuxConnect implements manholes with their splice box Creos enters in the same manhole with his own splice box for being interconnected to the 12 fibres in the backbone on one hand and on the other hand managing his last mile

11 The result A B Backbone LuxConnect
MV MV A B MV Backbone LuxConnect 12 fibres optics due to renting used by Creos Remaining meters due to Creos from another part of the network Last mile of Creos MV Medium Voltage stations Manholes

12 The reality LuxConnect Backbone Creos Last Mile

13 Case study 1 Inside 5 years
Creos fully deploy a F.O. network Calculation base: 1500 MV stations and 1300 km F.O. Costs: Tubes 125/110: 1200km = 96 M€ (80€/m) Tubes 32mm: 1200 km = 6 M€ (5€/m) Manholes etc : 1.2M€ MV connection: Tubes 225km = 15.6 M€ (65€/m via particip.) Manholes etc = 4.5 M€ Fibre optics: Backbone: 1300km = 19.5 M€ (15€/m) MV level: 225km = M€ (15€/m) Housings, Connecters etc. = 2 M€ FTE: at least 3 suppl. au Comin and suppl. Work for Project Manager Total : = ~150 M€ (with « flatliner » – 8 M€) Inside 5 years ( for covering 3000 MV stations with 4500 km of F.O. around 500M€)

14 Case study 2 Total : = ~35 M€ Creos and Luxconnect :
Calculation base: 1500 MV station et 1300 km of F.O. Costs for Backbone: « flatliner » 550km = 16.5 M€ (30€/m) Right on 1300km of F.O. inside a 1500km network of Luxconnect MV connection (last mile): (only Creos) Tubes 225km = 15.6 M€ (65€/m via particip.) Fibre optics: Backbone: 1300km = 0 M€ Last mile MV: 225km = 0.9 M€ (4 €/m) Housings, Connecters etc. = 2 M€ FTE: 1 suppl. at Comin and less suppl. Work for Project Manager Total : = ~35 M€

15 Conclusion 5 years of invest in Backbone (Creos -> LuxConnect)
15 years of invest in last mile (MV to backbone, Creos) 1500 Creos MV stations interconnected - used backbone 1300km at LuxConnect - last mile 225km Faster rollout of the fiber network (LuxConnect) Less cost intensive (LuxConnect and Creos)

16 Communication Infrastructure
Management CEO Edouard Wangen (+352) Head of Department Guy Loos (+352) Head of Dispatching Carlo Bartocci (+352) 2624 – 8003 Communication Infrastructure Patrick Colling (+352) 2624 – 7746


Download ppt "Common Fibre Optic Infrastructure Strategies"

Similar presentations


Ads by Google