1 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 8PU Drawer Installation and Configuration 1:00 TEXTFlexible Crew  Sessions required as needed (after new hardware arrives on station). HRF2-DRWR-CONFIG

2 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 8PU Drawer Reconfiguration :30  Sessions required as needed (before new hardware arrives on station). HRF2-DRWR-RECONFIG TEXTFlexible Crew

3 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 Drawer Audit :30 TEXTFlexible Crew  Sessions required as needed. HRF2-DRWR-AUIDT

4 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 Drawer Holder Installation :25 TEXTFlexible Crew  Sessions required as needed (after new hardware arrives on station). HRF2-DRWR-HLDR INSTL

5 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 Hardware Consolidation 1:00  Sessions required as needed (before new hardware arrives on station). HRF2-HW-CONSOLID TEXTFlexible Crew

6 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 Light Bulb Replacement :20 TEXTFlexible Crew  Sessions required as needed (due to hardware anomaly, applicable increment OCR). HRF2-BULB-RPLC

7 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 PC Data Downlink :30 OR 1:00 OR 1:30 OR 2:00 OR 2:30 OR 3:00 OR 3:30 OR 4:00 OR 4:30 OR 5:00 (duration is dependent on amount of excepted data) Commanding Unattended  Sessions required as needed, assume once per increment (mid-increment).  For HRF2-PC-D/L xH CMD, x can be 0.5, 1.0, 1.5, 2.0, 2.5, 3.0, 3.5, 4.0, 4.5, or 5.0. HRF2-PC-D/L xH CMD HRF2-RACK/PC-TRACK :30 ESA-HRF2-DEACT (ESA) ESA-HRF2-ACT (ESA) 1:00 HRF2-RACK-PWRUP CMDHRF2-RACK-PWRDN CMD

8 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 HRF2-PC-D/L 1.5H CMD HRF2-PC2-DVD PREPHRF2-PC2-DVD CNCLD HRF2-PC2-DVD LOAD PC 2 DVD Load Installation :101:30 1:15 Crew Commanding Unattended  Sessions required as needed (after new software arrives on station). :10 HRF2-RACK/PC-TRACK :30 ESA-HRF2-DEACT (ESA) ESA-HRF2-ACT (ESA) 1:00 HRF2-RACK-PWRUP CMD HRF2-RACK-PWRDN CMD

9 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 PC 2 Setup Crew Commanding Unattended  Sessions required as needed. HRF2-PC2-SETUP HRF2-RACK/PC-TRACK :30 ESA-HRF2-DEACT (ESA) ESA-HRF2-ACT (ESA) 1:00 HRF2-RACK-PWRUP CMDHRF2-RACK-PWRDN CMD :10

10 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 :30 PC 2 Swap > 2:30 :15 Crew Commanding Unattended  Sessions required as needed (due to hardware anomaly, applicable increment OCR). HRF2-PC-D/L 0.5H CMD HRF2-PC2-SWAP HRF2-LAPTOP-RTRV HRF2-RACK/PC-TRACK :30 ESA-HRF2-DEACT (ESA) ESA-HRF2-ACT (ESA) 1:00 HRF2-RACK-PWRUP CMD HRF2-RACK-PWRDN CMD :30

11 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 1:30 HRF2-CATLOG-RTRV CMD  Sessions required as needed (after new software arrives on station). 1:00 PRO-PLMDM FILE-CMD (can be the day before) Commanding Unattended HRF2-RACK/PC-TRACK :30 ESA-HRF2-DEACT (ESA) ESA-HRF2-ACT (ESA) 1:00 HRF2-RACK-PWRUP CMDHRF2-RACK-PWRDN CMD RIC Card Catalog Retrieval Using Bootloader

12 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 :50 HRF2-RIC-LOAD ENDHRF2-RIC-LOAD PREP HRF2-RIC-SW LOAD RIC Software Load Installation :45:15 Crew Commanding Unattended  Sessions required as needed (after new software arrives on station). HRF2-RIC-COL VIDEO COMMS-VCA2-DLM NASA (ESA) HRF2-RACK/PC-TRACK :30 ESA-HRF2-DEACT (ESA) ESA-HRF2-ACT (ESA) 1:00 HRF2-RACK-PWRUP CMDHRF2-RACK-PWRDN CMD HRF2-RIC-COL VIDEO

13 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 1:00 HRF2-RIC-UPDATE CMD RIC Software Load Installation Using Bootloader  Sessions required as needed (after new software arrives on station). 1:00 PRO-PLMDM FILE-CMD (can be the day before) Commanding Unattended HRF2-RACK/PC-TRACK :30 ESA-HRF2-DEACT (ESA) ESA-HRF2-ACT (ESA) 1:00 HRF2-RACK-PWRUP CMDHRF2-RACK-PWRDN CMD

14 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 RIC Subnet Mask Change  Sessions required as needed. HRF2-SUBNET-COL VID HRF2-PC-D/L 1.0H CMD HRF2-SUBNET-MASK CHG COMMS-VCA2-DLM NASA (ESA) PRO-PLMDM FILE-CMD Crew Commanding Unattended HRF2-PLMDM-FILE CMD :30:45 :30 HRF2-PC-D/L 0.5H CMD HRF2-RACK/PC-TRACK :30 ESA-HRF2-DEACT (ESA) ESA-HRF2-ACT (ESA) 1:00 HRF2-RACK-PWRUP CMD HRF2-RACK-PWRDN CMD 1:00

15 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 Stowage Audit and Trash HRF2-STW-AUDIT/TRASH 3:00 TEXTFlexible Crew  Sessions required as needed (before new hardware arrives on station).

16 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 TEXTFlexible Supply Kit Inventory and Resupply HRF2-SUPPLY-INVNTRY 1:00 ~3 weeks HRF2-SUPPLY-RESUPPLY 1:30 Crew  Sessions required as needed, assume twice per increment.  Inventory occurs approximately 3 weeks before resupply, resupply occurs after resupply kit arrives on station.  Request that no blood collection occurs between inventory and resupply so the inventory counts remain accurate.

17 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 Change#RevisionIncDateCrew Roll-up* (hrs) PTP (hrs) Notes EO10-PPO-10- 036 Baseline27/2812/8/10--- EO10-PPO-11- 015 Baseline27/28 & Subs 4/1/11Nominal: 3.42 Reserve: 0.00 Inc 27/28 Working PTP 11/1/10 Nominal: 3.42 Reserve: 0.00 Ops: HRF Rack 2 Maintenance (periodic). Nominal: - HRF Rack 2 GDS and Portable PFS Gauge Photography (0.17 hrs/session): 1 session. - HRF Rack 2 PC DVD/RIC Software Load Installation (1.58 hrs/session): 1 session. - HRF Rack 2 Supply Kit Inventory and Resupply (1.67 hrs/session): 2 sessions. Reserve: - N/A EO10-PPO-11- 021 Revision A29/30 & Subs 6/23/11Nominal: 7.00 Reserve: 0.00 Inc 29/30 Working PTP 4/22/11 Nominal: 6.50 Reserve: 0.00 Ops: HRF Rack 2 Maintenance (periodic). Nominal: - HRF Rack 2 GDS and Portable PFS Gauge Photography (0.17 hrs/session): 1 session (near end of increment). - HRF Rack 2 PC DVD/RIC Software Load Installation (1.67 hrs/session): 1 session (double booked, also planned in previous increment). - HRF Rack 2 GDS Tank Changeout (0.50 hrs/session): 1 session (2 tanks after HTV3 docking). - HRF Rack 2 PFS PAM Health Check (1.33 hrs/session): 1 session. - HRF Rack 2 Supply Kit Inventory and Resupply (1.67 hrs/session): 2 sessions. Reserve: - N/A PPO Change Log *Crew Roll-up is not maintained real-time.

18 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 Change#RevisionIncDateCrew Roll-up* (hrs) PTP (hrs) Notes EO10-PPO-11- 036 Revision B29/30 & Subs 12/8/11Nominal: 1.25 Reserve: 0.00 Inc 29/30 Working PTP 10/15/11 Nominal: 3.00 Reserve: 3.00 Ops: - HRF Rack 2 Maintenance (periodic). Nominal: - HRF Rack 2 PFS PAM ORU Replacement (1.25 hrs/session): 1 session (after 45P, 29S docking, before next experiment use of PFS). Reserve: - N/A EO10-PPO-11- 037 Revision C31/32 & Subs 12/8/11Nominal: 5.92 Reserve: 0.00 Inc 31/32 Working PTP 10/31/11 Nominal: 5.50 Reserve: 0.00 Ops: - HRF Rack 2 Maintenance (periodic). Nominal: - HRF Rack 2 GDS and Portable PFS Gauge Photography (0.17 hrs/session): 1 session (near end of increment). - HRF Rack 2 GDS Tank Changeout (0.25 hrs/session): 2 sessions (1 tank after ATV3 docking, 1 tank after HTV3 docking). - HRF Rack 2 PC DVD Load Installation (0.58 hrs/session): 1 session (after SpX-1 docking). - HRF Rack 2 RIC Software Installation (1.25 hrs/session): 1 session (after SpX-1 docking). - HRF Rack 2 PFS DMU File Update (0.08 hrs/session): 1 session (after SpX-1 docking). - HRF Rack 2 Supply Kit Inventory and Resupply (1.67 hrs/session): 2 sessions (first inventory mid Apr 2012, resupply early May 2012; second inventory late Aug 2012, resupply mid Aug 2012). Reserve: - N/A PPO Change Log *Crew Roll-up is not maintained real-time.

19 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 Change#RevisionIncDateCrew Roll-up* (hrs) PTP (hrs) Notes EO10-PPO-12- 011 Revision D33/34 & Subs 6/28/12Nominal: 6.00 Reserve: 0.00 Inc 33/34 Working PTP 5/11/12 Nominal: 4.33 Reserve: 0.00 Ops: - HRF Rack 2 Maintenance (periodic). Nominal: - HRF Rack 2 GDS and Portable PFS Gauge Photography (0.17 hrs/session): 1 session (near end of increment). - HRF Rack 2 PC DVD Load Installation (0.58 hrs/session): 1 session (after SpX-1 docking; double booked, also planned in previous increment). - HRF Rack 2 RIC Software Installation (1.25 hrs/session): 1 session (after SpX-1 docking; double booked, also planned in previous increment). - HRF Rack 2 PuFF Calibration Syringe Maintenance (0.33 hrs/session): 1 session (NLT 2/13/13). - HRF Rack 2 PFS Relief Valve Checkout (0.25 hrs/session): 1 session (before 1/3/13). - HRF Rack 2 PFS DMU File Update (0.08 hrs/session): 1 session (after HTV3 docking; double booked, also planned in previous increment). - HRF Rack 2 Supply Kit Inventory and Resupply (1.67 hrs/session): 2 sessions (first inventory late Nov 2012, resupply mid Dec 2012; second inventory mid Feb 2013, resupply early Mar 2013). Reserve: - N/A EO10-PPO-12- 036 Revision E35/36 & Subs 12/19/12Nominal: 3.67 Reserve: 0.00 Inc 35/36 Working PTP 10/24/12 Nominal: 4.08 Reserve: 0.00 Ops: - HRF Rack 2 Maintenance (periodic). Nominal: - HRF Rack 2 GDS and Portable PFS Gauge Photography (0.17 hrs/session): 1 session (near end of increment). - HRF Rack 2 PFS DMU File Update (0.17 hrs/session): 1 session (before BP Reg use of PFS). - HRF Rack 2 Supply Kit Inventory and Resupply (1.67 hrs/session): 2 sessions (first inventory May 2013, resupply within 8 weeks after; second inventory end of July 2013, resupply Aug 2013). Reserve: - N/A PPO Change Log *Crew Roll-up is not maintained real-time.

20 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 Change#RevisionIncDateCrew Roll-up* (hrs) PTP (hrs) Notes EO10-PPO-13- 020 Revision F37/38 & Subs 6/13/13Nominal: 3.67 Reserve: 1.50 Inc 37/38 Working PTP 4/29/13 Nominal: 3.91 Reserve: 1.42 Ops: - HRF Rack 2 Maintenance (periodic). Nominal: - HRF Rack 2 PC DVD Load Installation (0.33 hrs/session): 1 session (after SpX-3 docking). - HRF Rack 2 PC Data Downlink (0.00 hrs/session): 1 session (mid-increment). - HRF Rack 2 Supply Kit Inventory and Resupply (1.67 hrs/session): 2 sessions (first resupply after 53P docking, before Wakata’s FD60 Biochem/Repo blood collection, inventory at least 3 weeks before, not far after Wakata’s FD30 Biochem/Repo blood collection; second resupply after 54P docking, before Hopkins’ R-14 ProK/Biochem/Repo or Wakata's FD120 blood collection, whichever ends up first, inventory at least 3 weeks before). Reserve: - HRF Rack 2 GDS and PPFS Gauge Photography (0.17 hrs/session): 1 session (near end of increment). - HRF Rack 2 RIC Software Load Installation (1.33 hrs/session): 1 session (after SpX-3 docking). EO10-PPO-13- 042 Revision G39/40 & Subs 12/12/13Nominal: 5.42 Reserve: 0.00 Inc 39/40 Working PTP 10/21/13 Nominal: 5.42 Reserve: 0.00 Ops: - HRF Rack 2 Maintenance (periodic). - PFS Maintenance (periodic). Nominal: - HRF Rack 2 PC Data Downlink (0.00 hrs/session): 1 session (mid-increment). - HRF Rack 2 Supply Kit Inventory and Resupply (2.50 hrs/session): 2 sessions (first resupply after 38S docking, inventory ~3 weeks before; second resupply after ATV5 docking, inventory ~3 weeks before). - PFS GDS and PPFS Gauge Photography (0.17 hrs/session): 1 session (near end of increment). Refer to the PFS PPO to schedule the session. - PFS Relief Valve Checkout (0.25 hrs/session): 1 session (NLT 4/26/14). Refer to the PFS PPO to schedule the session. Reserve: - N/A PPO Change Log *Crew Roll-up is not maintained real-time.

21 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 Change#RevisionIncDateCrew Roll-up* (hrs) PTP (hrs) Notes hopsall001224Revision H39/40 & Subs 7/23/14--Decreased time for HRF Rack 2 RIC Software Load Installation session from 80 mins to 60 mins to reflect new crew time update. hopsall001231Revision I39/40 & Subs 7/30/14--Added PC D/L 0.5H commanding activity to HRF Rack 2 RIC Software Load Installation session in order to allow for verification commanding after RIC load is completed. EO10-PPO-14- 039 Revision J39/40 & Subs 8/18/14--Added PPO document number to reflect new EO10 OPR Configuration Control Plan for PPOs. parcall000039Revision K41/42 & Subs 9/15/14Nominal: 6.00 Reserve: 0.00 Inc 41/42 Working PTP 8/6/14 Nominal: 6.17 Reserve: 0.00 Ops: - HRF Rack 2 Maintenance (periodic). - PFS Maintenance (periodic). Nominal: - HRF Rack 2 PC Data Downlink 5.0H (0.00 hrs/session): 1 session (mid-increment). - HRF Rack 2 PC DVD Load Installation (0.33 hrs/session): 1 session (after SpX-5 docking). - HRF Rack 2 Supply Kit Inventory and Resupply (2.50 hrs/session): 2 sessions (first resupply after Orb-3 docking, inventory ~3 weeks before; second resupply after Orb-4 docking, inventory ~3 weeks before). - PFS DMU Update (0.25 hrs/session): 1 session (after Orb-4 docking, before Drain Brain use of PFS). Refer to the PFS PPO to schedule the session. - PFS GDS and PPFS Gauge Photography (0.17 hrs/session): 1 session (near end of increment). Refer to the PFS PPO to schedule the session. - PFS PuFF Calibration Syringe Maintenance (0.33 hrs/session): 1 session (before 1/29/15). Refer to the PFS PPO to schedule the session. Reserve: - N/A EO10-PPO-14- 073 Revision L41/42 & Subs 10/21/14--Combined COMMS VCA downlink and monitor ESA activities for HRF Rack 2 RIC Software Load Installation session to reflect new requirement to use one commanding activity (instead of two) for downlink and monitor based on IEPT email from ESA planner. hopsall001265Revision M41/42 & Subs 11/21/14--Created activities to reflect new requirement to perform HRF Rack 2 RIC Subnet Mask Change to facilitate communication between HRF PC3 and HRF Racks. PPO Change Log *Crew Roll-up is not maintained real-time.

22 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 Change#RevisionIncDateCrew Roll-up* (hrs) PTP (hrs) Notes hopsall001272Revision N41/42 & Subs 12/9/14--Added HRF2 PL MDM commanding activity for HRF Rack 2 RIC Subnet Mask Change session to reflect new direction based on previous OCR to identify when PL MDM commanding is required to ensure no file commanding to/from the PL MDM is occuring at the same time. Increased duration of subnet mask change activity from 30 mins to 45 mins to reflect new crew time based on procedure update to add corrective steps for comm ports in procedure to match what is seen on-orbit. hopsall001278Revision O41/42 & Subs 1/5/15--Created activity to reflect new requirement to perform HRF Rack 2 Light Bulb Replacement due to bulb burning out. hopsall001285Revision P41/42 & Subs 2/11/15 --Increased duration of PC DVD load activity from 1 hr to 1 hr 30 mins, PC downlink commanding activity from 1 hr to 1 hr 30 mins to reflect new unattended and commanding time update for HRF Rack 2 PC DVD Load Installation session. Created activity to reflect new requirement to perform HRF Rack 2 RIC Software Load Installation Using Bootloader. parcall000089Revision Q43/44 & Subs 3/24/15Nominal: 2.50 Reserve: 2.67 Inc 43/44 Working PTP 2/27/15 Nominal: 2.50 Reserve: 2.67 Ops: - HRF Rack 2 Maintenance (periodic). - PFS Maintenance (periodic). Nominal: - HRF Rack 2 PC Data Downlink 5.0H (0.00 hrs/session): 1 session (mid-increment). - HRF Rack 2 Supply Kit Inventory and Resupply (2.50 hrs/session): 1 session (resupply after Orb-4 docking, inventory ~3 weeks before). Reserve: - HRF Rack 2 Supply Kit Inventory and Resupply (2.50 hrs/session): 1 session (resupply after SpX-7 docking, inventory ~3 weeks before). - PFS GDS and PPFS Gauge Photography (0.17 hrs/session): 1 session (near end of increment). Refer to the PFS PPO to schedule the session. hopsall001339Revision R43/44 & Subs 6/9/15--Created activity to reflect new requirement to perform HRF Rack 2 PC 2 Setup to operate using Ethernet capability and rack power. PPO Change Log *Crew Roll-up is not maintained real-time.

23 EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 Change#RevisionIncDateCrew Roll-up* (hrs) PTP (hrs) Notes hopsall001353Revision S43/44 & Subs 7/15/15--Created activity to reflect new requirement to perform HRF Rack 2 RIC Card Catalog Retrieval Using Bootloader to retrieve card catalog information from the RIC per request from Express Rack team. parcall000159Revision T45/46 & Subs 9/25/15Nominal: 2.50 Reserve: 1.17 Inc 45/46 Working PTP 8/14/15 Nominal: 2.50 Reserve: 2.75 Ops: - HRF Rack 2 Maintenance (periodic). - PFS Maintenance (periodic). Nominal: - HRF Rack 2 Supply Kit Inventory and Resupply (2.50 hrs/session): 1 session (resupply after SpX-9 docking, inventory ~3 weeks before). - HRF Rack 2 PC Data Downlink 5.0H (0.00 hrs/session): 1 session (mid-increment). Reserve: - HRF Rack 2 8PU Drawer Configuration (1.00 hrs/session): 1 session (after SpX-8 docking). - PFS GDS and Portable PFS Gauge Photography (0.17 hrs/session): 1 session (near end of increment). Refer to the PFS PPO to schedule the session. PPO Change Log *Crew Roll-up is not maintained real-time.