Www.emwd.org 1 EASTERN MUNICIPAL WATER DISTRICT Water Supply Strategic Plan Brian Jack Powell, P.E. Director of Planning June 17, 2015.

Similar presentations


Presentation on theme: "Www.emwd.org 1 EASTERN MUNICIPAL WATER DISTRICT Water Supply Strategic Plan Brian Jack Powell, P.E. Director of Planning June 17, 2015."— Presentation transcript:

1 www.emwd.org 1 EASTERN MUNICIPAL WATER DISTRICT Water Supply Strategic Plan Brian Jack Powell, P.E. Director of Planning June 17, 2015

2 www.emwd.org 2 Capital Plan The Water Supply Strategic Plan is a key element of the District’s Long-Term Capital Plan

3 www.emwd.org 3 Capital Plan New development is expanding beyond the reach of existing supplies Develop a plan for supply, reliability, and resiliency Incorporate the District’s water supply strategic priorities Include MWD’s Integrated Resources and Integrated Area Planning Results from the Water Supply Strategic Plan feed into the Master Plans and Capital Plan Mills Perris WFP Skinner Hemet WFP Desalters Ground water Moreno Valley

4 www.emwd.org 4 Water Supply Strategic Plan Conservatio n Planning Demand Projections MWD’s Planning Soboba Impacts The Plan incorporates key issues Updated Demand Projections Conservation planning MWD’s water supply planning Impacts from the Soboba Settlement Agreement

5 www.emwd.org 5 Water Supply Strategic Plan 2020 2030 2040 2050 Updated Demand Projections Latest land use planning from the various land planning agencies Current water use information and timing from Database of Proposed Projects (DOPP) Planning for permanent conservation Demand projections were moderated against economic projections

6 www.emwd.org 6 Water Supply Strategic Plan MWD’s Water Supply Planning MWD confirmed that a third treatment plant is not being considered The Skinner Treatment Plant has significant available capacity (400 MGD) The “Gap Pipe” (I-215 crossing) of the Perris Valley Pipeline could be completed within 3 to 5 years MWD is considering our request to share right-of-way and transmission capacity with EMWD A raw water connection for San Jacinto Valley recharge supplies was favorably considered by MWD

7 www.emwd.org 7 Water Supply Strategic Plan Soboba Settlement Agreement Impacts EMWD’s adjusted base production right is being adjusted downward annually to 7,303.4 AFY by 2019 The existing raw water pipeline and the EM-14 capacity limit supply available to Hemet Water Filtration Plan when MWD delivers 42 cfs to the recharge ponds

8 www.emwd.org 8 San Jacinto Valley Water Supplies

9 www.emwd.org 9 San Jacinto Valley Water Supplies Six Alternatives were evaluated for water supply using a combination of: Enhanced groundwater Hemet Water Filtration Plant expansion Treated imported from Skinner

10 www.emwd.org 10 San Jacinto Valley Water Supplies Recommended Approach: Enhanced groundwater o Requires new MWD raw water turnout, pipeline and recharge facilities Expand HWFP Supplement with Skinner

11 www.emwd.org 11 San Jacinto Valley Water Supplies Near-Term Facility Requirements: New MWD raw water turnout New EMWD raw water pipeline to HWFP Develop the Mountain Avenue West site into recharge facilities for the Enhanced Recharge and Recovery Program

12 www.emwd.org 12 San Jacinto Valley Water Supplies Ultimate Water Supplies for San Jacinto Valley: Maximum Day Demand 143 CFS Enhanced Groundwater 61 cfs HWFP 46 CFS Skinner 36 CFS Currently about 34 CFS

13 www.emwd.org 13 Districtwide Water Supplies

14 www.emwd.org 14 Districtwide Water Supplies Alternatives were evaluated for water supply using a combination of: Development of Mills contracted capacity (EM-12, EM-23 and EM-24) Total = 320 CFS Expansion of Skinner capacity Expansion of Perris WFP Redundancy and Reliability

15 www.emwd.org 15 Districtwide Water Supplies Recommended Approach: Expand treated water supplies from MWD: o Skinner New capacity (EM-11) and pumping station Conveyance pipelines phased in over time o Mills MWD to complete Gap Pipe on the Perris Valley Feeder EMWD to construct Western Way Pumping Station Conveyance pipelines phased in over time Expand Perris Water Filtration Plant if needed Mills Perris WFP Skinner Hemet WFP Desalters Ground water Moreno Valley

16 www.emwd.org 16 Districtwide Water Supplies Ultimate Districtwide Water Supplies: Maximum Day Demand 824 CFS Mills 320 cfs Skinner 330 CFS PWFP 37 CFS HWFP 46 CFS Desalters 19 CFS Groundwater 72 CFS Currently about 282 CFS

17 www.emwd.org 17 Next Steps

18 www.emwd.org 18 Water Supply Strategic Plan Capital Plan Coordination with Master Plan efforts MWD Coordination Raw Water Connection Skinner Connection PVP Gap Pipeline Conveyance Raw Water Connection and Pipeline Preliminary Design Recharge Mountain Avenue West Preliminary Design Next Steps Incorporate results into the Master Plans and Capital Plan Continue working closely with MWD Advance preliminary design of the connection and raw water pipeline in San Jacinto Advance preliminary design of the Mountain Avenue West Recharge Facilities – part of the Prop 84 grant application (Enhanced Recharge and Recovery Program)

19 www.emwd.org 19 Capital Plan Implementation Schedule

20 www.emwd.org 20 Contact Information EASTERN MUNICIPAL WATER DISTRICT www.emwd.org Brian Jack Powell, P.E. Director of Planning (951) 928-3777 ext. 4278 powellb@emwd.org