Download presentation
Presentation is loading. Please wait.
Published byCornelia Stafford Modified over 8 years ago
1
Beam Interlock System MPP Internal ReviewB. Puccio17-18 th June 2010
2
CERN Bruno PUCCIO (TE/MPE) Machine Protection Panel - Internal review - 17-18 th June 2010 2 Current Status ● Stable system ♦ Intensively used (~1000 emergency dumps since Nov.09) ♦ Get confidence thanks to Operational tests (see next slide) ♦ No false dump ♦ High availability, except for: ■ VME-bus controller board failures (same problem with BI crates) BE/CO is aware of this issue. A solution/cure is expected… ■ few failures with redundant PSU installed in CIBU Thanks to redundancy, never lead to a beam operation disruption. ■ 3 failures with redundant PSU of the VME crate Always a primary side fault, together with a permanent short => open the circuit breaker. Unfortunately, only one UPS “reglette” is installed in each BIC’s racks; in other words: our redundancy is useless! No immediate solution. Waiting for feedback from BE/CO & Elcotron…
3
CERN Bruno PUCCIO (TE/MPE) Machine Protection Panel - Internal review - 17-18 th June 2010 3 Radiation issues? ● Controllers are installed in: CCR, SR3, SR7, UA (23,27,43,47,63,67,83,87), UJ33, TZ76, US15, USC55 and UJ56 ♦ UJ56 case: a move to USC55 is already scheduled (shutdown 2012?) (re-commissioning has to performed) ♦ Other cases: still waiting for R2E inputs (a move to the surface is technically possible; simply a question of cost..) ● CIBUs are always installed in the User Systems’ racks. The most critical cases are UJ14, UJ16, RRs,… ♦ If User System equipment is moved, CIBU will be obviously moved. ♦ Irradiation tests performed: the CIBU is most likely less sensitive than the host Equipment. ♦ Thanks to redundancy, SEU will not compromise safety but obviously could provoke a beam dump.
4
CERN Bruno PUCCIO (TE/MPE) Machine Protection Panel - Internal review - 17-18 th June 2010 4 Operational Tests Pre-Operation checks (launched by Beam Sequencer) configuration verification and integrity check During Operation (DiaMon application) fault diagnosis and monitoring Post-Operation checks (included in PM ) response analysis
5
CERN Bruno PUCCIO (TE/MPE) Machine Protection Panel - Internal review - 17-18 th June 2010 5 In order to avoid blind failure, the User_Permit signal changes must be regularly checked Automated Tests Automated Test of CIBU connections (1/2) Connections could be tested from end-to end recovered “good as new” But only from the input connectors... BIS design allows 100% Online test coverage:
6
CERN Bruno PUCCIO (TE/MPE) Machine Protection Panel - Internal review - 17-18 th June 2010 6 Automated Test of CIBU connections (2/2) ● Already available with only: ♦ BLM and BTV systems ♦ PIC, WIC and FMCM ● Required for: ♦ Collimation (Environmental parameters) ♦ Collimation (Motor positions) ♦ Vacuum ♦ Experiments (detector parts) ♦ Experimental Magnets … ● FESA property (for VME based system) and PVSS framework (for PLC based system) are both available MI team is willing to help but it’s up to the User System team to implement the functionality and write the code.
7
CERN Bruno PUCCIO (TE/MPE) Machine Protection Panel - Internal review - 17-18 th June 2010 7 Safe Beam Flag and Unmasking.... As an additional safety level, what about the “removal” of the masks? YES FALSE It has been foreseen to force the Safe Beam Flag to FALSE before the ramp… (could be implemented without difficulty)
8
CERN Bruno PUCCIO (TE/MPE) Machine Protection Panel - Internal review - 17-18 th June 2010 8 ● Stable HW system despite few availability issues: Summary Not related to BIC boards; under investigation with help of BE/CO. ● Monitoring and Test SW in operation: - Pre-Operational checks recently integrated in LHC Beam Sequencer - Post-Operational checks are included in PM analysis - BIS Java application and Diamon application both give on-line diagnosis - C IBU Automated tests increase the level of confidence: To be done by the User System team Partially implemented; need MPP recommendation for (re)activating the “process” Waiting for a decision... ● Radiation issues? will be only related to machine availability move of BIC in UJ56 already scheduled; for the other locations: we will follow R2E advices ● Masks removed before the ramp?
9
CERN Bruno PUCCIO (TE/MPE) Machine Protection Panel - Internal review - 17-18 th June 2010 Bruno PUCCIO 9 Machine Protection Panel - Internal review - 17-18 th June 2010 CERN Fin Thank you for your attention
10
CERN Bruno PUCCIO (TE/MPE) Machine Protection Panel - Internal review - 17-18 th June 2010 10 Spare slides
11
CERN Bruno PUCCIO (TE/MPE) Machine Protection Panel - Internal review - 17-18 th June 2010 11 Key element of PM analysis Thanks to the different gathered History Buffers: - Identification of the beam dump source - Reconstruction to the sequence of events that has led to the beam dump
12
CERN Bruno PUCCIO (TE/MPE) Machine Protection Panel - Internal review - 17-18 th June 2010 12 CIBU Test Layout 12 PVSS framework (supplied by EN/ICE) Simplified layout
Similar presentations
© 2024 SlidePlayer.com Inc.
All rights reserved.