Port of Long Beach 76 Foot Main Channel Dredging Project Doug Thiessen, Port of Long Beach (POLB),Al Moro, Chief Harbor Engineer, POLB Emily Ueda, Program.

Similar presentations


Presentation on theme: "Port of Long Beach 76 Foot Main Channel Dredging Project Doug Thiessen, Port of Long Beach (POLB),Al Moro, Chief Harbor Engineer, POLB Emily Ueda, Program."— Presentation transcript:

1 Port of Long Beach 76 Foot Main Channel Dredging Project Doug Thiessen, Port of Long Beach (POLB),Al Moro, Chief Harbor Engineer, POLB Emily Ueda, Program Manager, POLB, Janna Watanabe, Environmental Specialist, POLB Jim Fields, U.S. Army Corps of Engineers, Alan Alcorn, Moffatt & Nichol Todd Graham, KPFF, Steve Cappellino, Anchor QEA

2

3 Project Goal Improve navigation and environmental safety – Economical sediment remediation (IR Site 7) Deepen and widen turning Basin and Main Channel Create Port property for commerce

4 Project Sites

5 Disposal Site: Pier G North Slip

6 Pier G North Slip Fill

7 Pier G Fill

8 Catalina Express Terminal Maintenance Dredging

9 Target Dredge Depths Area A = 4’+2’ OD Area C (west) = 4’+2” OD Area C (east) = 2’+2’ OD Final Removal Volume Area A = 147,000 CY Area C (west) = 221,000 CY Area C (east) = 134,000 CY Total = 502,000 CY IR Site 7 West Basin Dredge Areas IR Site 7 West Basin Dredge Areas

10 Clamshell Dredge at IR Site -7

11 IR Site -7 Material in Dump Scow

12 IR Site -7 Material at Pier G Fill

13 Phase 2 – Dredging Turning Basin PIER G 3500’ WEIGHTED HDPE PIPE 4000’ WEIGHTED HDPE PIPE 1000’ STEEL PIPE 2000’ WEIGHTED HDPE PIPE 1400’ FLOATING STEEL PIPE 80’ STEELPIPE SCHEDULE: 4/6/2011 – 4/26/2011 (21 DAYS – 24/7) EQUIPMENT: H.R. MORRIS (CUTTER HEAD) DREDGE POWER: ELECTRIC (from Pier T) DREDGE QUANTITY: 430,000 CY DISPOSE METHOD: PUMP (24” PIPE) PRODUCTION: 17,000 PER DAY

14 Dike Construction

15 HR Morris Cutterhead

16 Channel Dredging

17 Turning Basin Dredging

18 Hydraulic Discharge within Fill

19 Emergent Fill at Pier G

20 Surcharge Material Originally planned to use Western Anchorage sand mine Revised to include rolling surcharge using Port supplied crushed miscellaneous base (CMB) 2/3 of CMB left on-site for use in developing site Excess material used for other Port project (Middle Harbor)

21 Construction Costs Engineer’s Cost Estimate : $44M Area Cost Fill Area (Wall, Dike, dredging) $15.7 Million Catalina Express Terminal $0.8 Million IR Site 7 $11.5 Million Turning Basin and Channel (50/50 Fed Funded project) $9.6 Million Miscellaneous Items $2.2 Million Total Bid Amount: $39.8 Million Army Corps of Engineers cost share amount: $4.8 Million

22 http://www.polb.com Questions