MOBILE DISTRICT DREDGING PROGRAM MOBILE DISTRICT DREDGING PROGRAM NAD/SAD REGIONAL DREDGING MEETING/WEDA NAD/SAD REGIONAL DREDGING MEETING/WEDA US Army.

Similar presentations


Presentation on theme: "MOBILE DISTRICT DREDGING PROGRAM MOBILE DISTRICT DREDGING PROGRAM NAD/SAD REGIONAL DREDGING MEETING/WEDA NAD/SAD REGIONAL DREDGING MEETING/WEDA US Army."— Presentation transcript:

1 MOBILE DISTRICT DREDGING PROGRAM MOBILE DISTRICT DREDGING PROGRAM NAD/SAD REGIONAL DREDGING MEETING/WEDA NAD/SAD REGIONAL DREDGING MEETING/WEDA US Army Corps of Engineers Mobile District US Army Corps of Engineers Mobile District

2

3

4 Type of Work: Beach Nourishment Length: 1 Mile Quantity: 500 Kcy Distance to Borrow Area: 20 Miles Type of Equipment: Hopper Small Business Set Aside: No Schedule: Mid FY08 Type of Work: Beach Nourishment Length: 1 Mile Quantity: 500 Kcy Distance to Borrow Area: 20 Miles Type of Equipment: Hopper Small Business Set Aside: No Schedule: Mid FY08 Panama City Beach

5

6 Mobile Harbor Extension Mobile Harbor Extension 2100/1200 Type of Work: New Work Depth: 45’ Width: 500’ Length: 3300’ Quantity: 300 Kcy Type of Material: Sand/Clay Placement Area: Ocean D/A Distance to Placement Area: 40 Miles Type of Equipment: Bucket/Hopper Set Aside: Yes Schedule: Bid Opening January 2008

7

8 Type of Work: New Work Depth: 36’ Width: Widen from 220 to 300’ Length: 20+ Miles Quantity: 5.4 Mcy Type of Material: Hard Sand and Clay Placement Area: New Ocean D/A Distance to Placement Area: 30 Miles Type of Equipment: Bucket/Hopper Small Business Set Aside: No Last Dredged: 2007 Schedule: Bid Opening April 2008 Type of Work: New Work Depth: 36’ Width: Widen from 220 to 300’ Length: 20+ Miles Quantity: 5.4 Mcy Type of Material: Hard Sand and Clay Placement Area: New Ocean D/A Distance to Placement Area: 30 Miles Type of Equipment: Bucket/Hopper Small Business Set Aside: No Last Dredged: 2007 Schedule: Bid Opening April 2008 Gulfport Harbor Widening Gulfport Harbor Widening

9

10 Type of Work: New Work Depth: Deepen Upper Sound from 38’ to 42’ Width: Bar Channel widen from 350 to 550’ Length: 11 Miles Quantity: 8 Mcy Type of Material: Sands and Clay Placement Area: Ocean D/A Distance to Placement Area: 20 miles Type of Equipment: Bucket/hopper Small Business Set Aside: No Schedule: Bid Opening – June 2008 Type of Work: New Work Depth: Deepen Upper Sound from 38’ to 42’ Width: Bar Channel widen from 350 to 550’ Length: 11 Miles Quantity: 8 Mcy Type of Material: Sands and Clay Placement Area: Ocean D/A Distance to Placement Area: 20 miles Type of Equipment: Bucket/hopper Small Business Set Aside: No Schedule: Bid Opening – June 2008 Pascagoula Harbor Deepening Pascagoula Harbor Deepening

11

12 Figure 1. Project Location Hancock County Streams – Hancock County Marina

13 Hancock County Streams Cowan Bayou Cowan Bayou

14 Gautier Streams – 5 channels

15 Bayou Caddy Marsh Restoration Project Containment Structure New Marsh Bayou Caddy Figure 3. Rendering of proposed plan for Bayou Caddy by Ron Dawkins Bayou Caddy Containment

16

17

18 Type of Work: Beach Nourishment Length: 1 Mile Quantity: 500 Kcy Distance to Borrow Area: 20 Miles Type of Equipment: Hopper Small Business Set Aside: No Schedule: Mid FY09 Type of Work: Beach Nourishment Length: 1 Mile Quantity: 500 Kcy Distance to Borrow Area: 20 Miles Type of Equipment: Hopper Small Business Set Aside: No Schedule: Mid FY09 Panama CityBeach Carillon/Pinnacle Port Panama CityBeach Carillon/Pinnacle Port Carillon/Pinnacle Port

19 Type of Work: Maintenance Depth: 44’ Width: 500’ - 800’ Length: 5 Miles Quantity: 4.5 - 8.0 Mcy Type of Material: Silts and Sands Placement Area: Ocean D/A, Beach and Littoral Zone Distance to Placement Area: Varies Type of Equipment: Hopper/Pipeline Small Business Set Aside: No Last Dredged: 1990 Schedule: January 2009 Type of Work: Maintenance Depth: 44’ Width: 500’ - 800’ Length: 5 Miles Quantity: 4.5 - 8.0 Mcy Type of Material: Silts and Sands Placement Area: Ocean D/A, Beach and Littoral Zone Distance to Placement Area: Varies Type of Equipment: Hopper/Pipeline Small Business Set Aside: No Last Dredged: 1990 Schedule: January 2009 Pensacola Navy Channel Pensacola Navy Channel

20 Mobile Harbor Turning Basin Mobile Harbor Turning Basin Type of Work: New Work Depth: 45’ Quantity: 3.2 Mcy Type of Material: Sand, Silt and Clay Placement Area: Upland/Gaillard Distance to Placement Area: 13 Miles Type of Equipment: Bucket /Pipeline Small Business Set Aside: No Schedule: mid – FY09 Type of Work: New Work Depth: 45’ Quantity: 3.2 Mcy Type of Material: Sand, Silt and Clay Placement Area: Upland/Gaillard Distance to Placement Area: 13 Miles Type of Equipment: Bucket /Pipeline Small Business Set Aside: No Schedule: mid – FY09 Mobile Harbor Extension

21 Gulf of Mexico Walton County, Florida Walton County Post-Ivan 2004 May 2003 Dune Lakes Walton County, Florida - Beaches Type of Work: Beach Renourishment Quantity: 2 Mcy Length: 26 Miles Type of Equipment: Hopper/Pipeline Small Business Set Aside: No Schedule: Late FY 09


Download ppt "MOBILE DISTRICT DREDGING PROGRAM MOBILE DISTRICT DREDGING PROGRAM NAD/SAD REGIONAL DREDGING MEETING/WEDA NAD/SAD REGIONAL DREDGING MEETING/WEDA US Army."