Alternative Sediment Remediation Authorities to CERCLA: Elizabeth River Demonstration Robert Engler (rengler@moffattnichol.com) Moffatt & Nichol), Vicksburg,rengler@moffattnichol.com) Mississippi, (USA) Eric Smith (esmith@moffattnochol.com), Baltimore,esmith@moffattnochol.com), Maryland, (USA)
2
Alternative Sediment Remediation Permitting Authorities Full and Continuing Coordination with Federal, State, Local permitting and Review Agencies and the Elizabeth River Project at the Outset of Project. Full Commercial Navigation Requirements Must Be Maintained. Pre-operational Assessment o Clean Water Act – CWA (USACE Guidance/Review o VA DEQ, DCR, VIMS, DGIF, MRC Guidance/Review Dredging o USACE, Section 10, Rivers and Harbors Act (R&HA), Clean Water Act 404(b)1 Guidance, Manuals o VA DEQ CWA, Water Quality Certification o VA DCR Oversight o VIMS Review
3
Dredge Material Rehandling/Treatment/Disposal o VA Authorized Land Fill Rules; Land Farming/Solidification and stabilization o TSCA – VA Rules Capping/Wetlands Restoration, Oyster Habitat o USACE, Section 10 R&HA, CWA 404(b)1 Guidance, Manuals o VA DEQ, CWA – Water Quality Certification o VA – DCR, DGIF, MRC Oversight o VIMS Review Source Control/Air Quality o VA Regulations USEPA Guidance and Oversight as Appropriate Under CWA Threatened and Endangered Species Coordination – VA DNR, USNMFS, USF&WS Essential Fish Habitat – VA DNR, USWMFS, USF&WS
4
Landscape Approach Forested Upland Wetlands Restoration Oyster Reef Creation Sediment Cleanup
5
Republic ERM CLEANUP GOALS
6
Remediation Methods Natural Recovery Removal of Sediments (Dredging) Isolation and Containment of Sediments (Capping) Combination of Above
7
Dredged Material Management 1.Mechanical Dredging 2.Transport to Weanack Plantation (or other site) 3.Landfarming 4.Dewatering/Stabilization to Landfill (e.g. Charles City County) 5.Placement at Other Approved Upland Site
8
Cap Engineering Development Chemical Isolation Modeling Follow US EPA Design Guidance Isolation of Contaminants to ERM or Less 100-Year Plus Design Life Cap Stability Assessment Tidal and Storm Currents Ship Induced Currents Propwash
9
Cap Requirements Cap thicknesses for erosion protection and chemical isolation Focus for health benchmarks
10
Isolation Cap Modeling Used two models (both in EPA guidance) RECOVERY (v 4.3) model for design Lampert & Reible model (LRM) for confirmation and additional tests RECOVERY USACE developed and validated model, 20 years of use with continual updating Numerical, time-varying, mass balance LRM Analytical, steady-state, mass balance
11
Cap Isolation Conclusion/Recommendation 12 inch sand cap is protective given the expected low groundwater upwelling rates The 12 inch protective cap on top of isolation adds extra protection
12
Cap Stability Assessment Tidal and Storm Currents Hydrodynamic Model of Tides and Storm Surge Ship-Induced Currents Numerical Model of Passing Ship Propwash Analytical Calculation of Prop Scour from Tugs
13
Hydrodynamic Model Domain MIKE FM Model Increased Resolution in Project Area 25-YEAR HURRICANE VALIDATED
14
Passing Vessel Model Model DELPASS developed by Pinkster Marine Hydrodynamics Panel model based on 3-d potential flow Panels represent river bathymetry and vessel Output 3 time-dependent velocity components on grid points of the river bottom Grid points match MIKE3 model resolution
15
Alternative 1 Dredge + Cap Dredge 2’ Cap 2’ 2’ Sand Cap / Wetlands Dredge 2’ w/ Armored Cap Dredge to El -39’ w/ Armored Cap Armored Cap Dredge 2’ Cap 2’ 2’ Sand Cap Armored Cap Dredge to El -42 ’ Dredge Volume 172,460 cy