Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU.

Similar presentations


Presentation on theme: "Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU."— Presentation transcript:

1 Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU funded Projects” Road Infrastructure Agency REPUBLIC OF BULGARIA MINISTRY OF REGIONAL DEVELOPMENT AND PUBLIC WORKS

2 European transport corridors 2

3 3 European transport corridors in Bulgaria

4 Road Junctions – 268 kmMotorways – 418 km I Class roads – 2975 km II Class roads – 4027 km Territory of Bulgaria: 110 900 km² Total length of national roads: 19 436 km Density of national roads: 0.18 km/km² 4

5 State budget; Pre-accession programmes PHARE and ISPA; Operational programmes Transport and Regional development 2007-2013(EU financing); State investment loans Sources of financing: 5

6 Operational Programme Transport 2007 – 2013 Total budget of 990 Million Euro for construction of 213 km motorways and 69 km I class roads, part of the TEN-T network. Road Infrastructure Agency is the only beneficiary on Priority Axis II “Development of road infrastructure along the major national and Pan- European transport axes”. 6

7 Projects in Operational Programme Transport 1. Trakia MW (from Sofia to Burgas) – 115 km – 350 Million Euro 2. Mariza MW (from BG to TR) – 67 km – 208 Million Euro 3. Struma MW (from BG to GR) – 132 km – 250 Million Euro 4. Kardshali – Podkova (from BG to GR) – 28 km – 32 Million Euro 5. Hemus MW (from Sofia to Varna) – 8.5 km – 32 Million Euro 6. Е-79, Vraza – Botevgrad (north of Sofia) – 31 km – 85 Million Euro 7.Е-79, Vidin – Montana (from RO to BG) – 20 km – 32 Million Euro 7 Σ 990 Million Euro

8 8 2 3 4 5 6 7 1 Projects on Operational Programme Transport 2007 - 2013

9 Sections of Trakiya MW in exploitation Projected sections of Trakiya MW 9 “Trakia” MW, Lot 2 Stara Zagora – Nova Zagora from km 210+100 to km 241+900 Length – 31.800 km The tender procedure for construction is completed. Signature of construction contract: 23 April 2010 Investment cost: 70.5 Million Euro. The tender procedure for supervision was announced on 22 February 2010. Signature of contract: expected in May 2010 End of construction: Summer 2012

10 “Trakia” MW, Lot 3 Nova Zagora – Yambol from km 241+900 to km 276+200 Length – 35.697 km Sections of Trakiya MW in exploitation Projected sections of Trakiya MW 10 Start of the tender procedure for construction: 26 February 2010. Signature of contract: expected in July 2010. Start of the tender procedure for supervision: 23 April 2010. Signature of contract: expected in July 2010 End of construction: Summer 2012 Tentative investment cost: 108 Million Euro

11 “Trakia”, Lot 4 Yambol - Karnobat from km 276+200 to km 325+280 Length – 49.080 km Sections of Trakiya MW in exploitation Projected sections of Trakiya MW 11 Start of the tender procedure for construction: 07 April 2010. Signature of contract: expected in August 2010. Start of the tender procedure for supervision: expected 14 May 2010. Signature of contract: expected in August 2010 End of construction: Autumn 2012 Tentative investment cost: 146 Million Euro

12 12 “Maritza” MW, Orizovo – Harmanli (connection Trakia MW – Turkish border) from km 5+000 to km 71 + 011 Length – 66,011 km Tender procedures for construction and supervision: Preparation of tender documentation is forthcoming. Start of tender procedures - second half of 2010 expected. Possible division of the project implementation – in 2 lots. Tentative investment cost: 209 Million Euro

13 Corridor No IV, Sofia to Greek border Lot 1 Dolna Dikania – Dupnitza from km 305+220 to km 322+000 Lot 2 Dupnitza-Blagoevrad from km 322+000 to km 356+000 Lot 4 Sandanski-Kulata from km 423+500 to km 438+500 Lot 3 will be constructed in the next programming period 2014-2020 Total length of Lot 1, Lot 2 and Lot 4: 65.78 km. Indicative cost: 250 Million Euro. Tender procedures for construction and supervision of Lot 1 and Lot 4: first half of 2011. Lot 2 – Tender procedure for design: forthcoming 13 Struma Motorway

14 „Hemus” Motorway Section : „Sofia Ring Road – “Yana” road junction” from km 0 to km 8+460. 1414 Start of the tender procedure for construction and supervision: expected in June 2011 Selection of Contractor and Consultant: expected in October 2011 Tentative investment cost: 32 Million Euro

15 Road I-5 Kardzhali – Podkova Corridor No IX, road to the Greek border The project includes rehabilitation of 8 km of the existing road and 24 km new construction from Kardzhali to Podkova. 1515 Start of the tender procedure for construction and supervision: expected in December 2010 Selection of Contractor and consultant: expected in April 2011 Tentative investment cost: 32 Million Euro

16 Operational Programme Regional Development 2007 - 2013 OPRD Phase 1, 302 km 14 Lots, ongoing tender procedures for construction and supervision. Expected beginning of the construction – July 2010.Budget – 110, 6 mil. Euro OPRD Phase 2, 311 km 15 Lots, tender documents are approved. Expected start of tender procedures –second half of 2010. Budget – 135,5 mil. Euro OPRD Phase 3 Indicative list of projects, ready to be included in the programme. 16

17 ІI. Road infrastructure projects for design 2010 – 2013 under Operational Programme Transport Construction 2014 – 2020 1717

18 Operational Programme Transport OPT – 2007-2013 PROGRAMME PERIOD OPT – 2014-2020 PROGRAMME PERIOD 18

19 Struma Motorway Lot 3 /Blagoevgrad - Sandanski/ Total length: 67.5 km 3 major sections: 3.1 - Blagoevgrad – Krupnik from km 356+000 to km 380+000 3.2 – Krupnik – Kresna (Kresna defile) from km 380+000 to km 400+600 3.3 - Kresna – Sandanski from km 400+600 to km 423+500 Preparation of Application form for funding the design of Lot 3 by Technical Assistance of Operational Programme "Transport“ is ongoing. Start of tender procedures for design – Autumn 2010. 1919

20 Trakia MW Lot 6 (Black Sea Motorway) The project is part of the Pan- European Transport Corridor No. VIII and connects the two biggest ports of the Republic of Bulgaria – Varna and Burgas Length:100 km Indicative cost: 350 Million Euro 20

21 Length: 50 km Indicative cost: 150 Million Euro “Sofia – Kalotina (border to Serbia)” MW 2121

22 Length: 85 km Indicative cost: 260 Million Euro “Sofia – Gyueshevo (border to Macedonia)” MW 22

23 “Shipka” Tunnel The total length is approx.: 3.2 km 23

24 Thank you for the attention! 24