Presentation is loading. Please wait.

Presentation is loading. Please wait.

T RILLO A PPAREL C OMPANY R EVISED D ELIVERY P LAN Chatae M Falls Argosy University.

Similar presentations


Presentation on theme: "T RILLO A PPAREL C OMPANY R EVISED D ELIVERY P LAN Chatae M Falls Argosy University."— Presentation transcript:

1 T RILLO A PPAREL C OMPANY R EVISED D ELIVERY P LAN Chatae M Falls Argosy University

2 1 ST ISSUE Necessity of building permits helps in beginning work on the fresh space of the real building. Postpone building permits 2 weeks changes to 3 weeks

3 2 ND ISSUE Framing Needs to be finished before further building stages. Because of the delay only half the real crew is sent by the contractor. Actually15 days Presently 30 days Drywall Needs to be finished after completion of further building stages. Because of the delay only half the real crew is sent by the contractor. Actually15 days Presently 30 days

4 O PTION 1

5 O PTION 2

6 P ROPOSED S OLUTION Option 2 will be used. For staying at budget and being punctual requires certain variations when all the contractors would be coming for performing their work.

7 C ONCLUSION

8 R EFERENCES Kerzner, H. (2001). Strategic planning for project management using a project management maturity model. New York: John Wiley. Melton, T. (2008). Real project planning developing a project delivery strategy. Amsterdam: Butterworth-Heinemann.


Download ppt "T RILLO A PPAREL C OMPANY R EVISED D ELIVERY P LAN Chatae M Falls Argosy University."

Similar presentations


Ads by Google