License Renewal at Paks NPP Project Technical Tasks Project Technical Tasks Sándor RÁTKAI, LR project technical head, PAKS NPP Telephone: 75/508576, fax:

Similar presentations


Presentation on theme: "License Renewal at Paks NPP Project Technical Tasks Project Technical Tasks Sándor RÁTKAI, LR project technical head, PAKS NPP Telephone: 75/508576, fax:"— Presentation transcript:

1 License Renewal at Paks NPP Project Technical Tasks Project Technical Tasks Sándor RÁTKAI, LR project technical head, PAKS NPP Telephone: 75/508576, fax: 75/507036 E-mail address: ratkai@npp.hu 1 st Hungarian-Ukrainian Joint Conference on „Safety-Reliability and Risk of Engineering Plants and Components” Miskolc, Bay Z. Institute; 11 th April, 2006.

2 Why can we speak about LR?  World tendency  Feasible in the sense of safety and technical aspects  Good business  Decision of the owner  Society support  Political support  Existing regulation

3 Why to extend the operational lifetime? Hungarian electricity supply - present situation and perspectives –Environmental aspects: Kyoto obligations – it is possible only if nuclear is considered –Security of supply – considering available sources and reliable markets to control the import dependence –Competitiveness of the economy – reliable and cheap electric energy is required

4 Hungarian electricity production Today: Well balanced system, the Kyoto targets could be met Diversity of the system ensured according to sources technologies import market 10% system capacity reserve exists Total domestic consumption 2004: 41 118 GWh Total domestic production 2004: 33 708 GWh

5 Needs for new capacities peak demand Construction of 6000 MW capacity is needed between 2005 and 2020 (to replace the old capacities and cover the increasing needs).

6 Domestic market - 2004 Largest, cheapest domestic producer! Source: www.eh.gov.hu Renewable production in 2004: 884 GWh state support: 16.495 MFt 5,95 Ft/kWh

7 Regulation

8 Activities for the sake of LR -- LTO Environmental Licensing 1. Feasibility study 2. Technical tasks 3. LR „program” making 4. Authority review 5. Demonstration of commitment 2008. 2011. 2012. IMPLEMENTATION 1. Operation due to LAR 2. Reconstruction, upgrading 2000. Nuclear Licensing (Making of LR application report) 6. License application document 7. Authority revew NEW Issue of the license Project Plan 1.TLAAs 2. Ageing Project Plan 1.TLAAs 2. Ageing 2010. 2009. 1. unit 2002. 12 1 2

9 REVIEW OF THE PROJECT TASKS

10 Integrated Plant Assessment (Review of the AMP)

11 SCOPEING + SCREENING of LR 1. Separately managed components: Reactor pressure vessel Reactor cover Reactor inner components Pressurizer Steam generator Main circulation pump Main gate valve …………. 2. Review units and commodity groups: Safety class Type of component Working medium Type of Material SC 1Housing of valves Primary waterAustenic SC 2 Housing of pumps (boric acid) Ferrite SC 3 Piping Duna water …. 4T, which Vessels Steam failure Heat exchangers …. threatens Acid/alkali safety …. Screening: Long lived, passive Scoping: Safety Class 1-3

12 Review includes: assessment of the SSCs aged status in context with assessment of effectiveness of existing AMP Review is extended also to plant programmes in general, i.e. ISI, T, maintenance practice (ASME BPVC sections XI,V) Items not included into the scope of LTO are covered by PLiM Action items: improvement or new programmes if needed Review the condition of the equipments Integrated Plant Assessment

13 Review and assessment of the AMP To demonstrate for the extended operational lifetime that: –The safety and ageing analysis remain valid and could be projected to the end of intended operational lifetime; –The effects of ageing on the intended function(s) will be adequately managed; –There is a procedure to deal with unexpected ageing mechanisms that can surface later in the years. In many cases, the plants existing ageing management programmes can be credited as acceptable programmes for LTO. For the remaining cases, either the plants existing programme can be augmented to satisfy the attributes listed above or new programmes should be initiated.

14 TLAA Review

15 Time Limited Ageing Analysis TLAA are defined as those licensee calculations and analyses (qualifications) that satisfy the following: –Involve systems, structures, and components within the scope of license renewal; –Consider the effects of ageing; –Involve time-limited assumptions defined by the current operating term, for example, 30 years; –Were determined to be relevant in making a safety determination; –Involve conclusions or provide the basis for conclusions related to the capability of the system, structure, and component to perform its intended functions; and –Are contained or incorporated by reference in the current licensing basis (in the FSAR).

16 PROJECT TASKS--TLAAs PROJECT TASKS-- TLAAs 1. Embrittlement of Reactor Pressure Vessel PTS p-T curves (normal operation & pressure test) 2.Strength + Fatigue calculations /check of the design/ benchmark tasks (tank, piping, flange)* load catalog strength calculations fatigue calculations (ASME BPVC 2001.) thermal stratification 3. Stability of indications (crack growth ) 4. Extension of Environmental Qualifications (I&C) 5. Other TLAAs cranes (review of operational limits) ----- preparation of the list Remark: * Also for PTS

17 OTHER PROJECT TASKS 1.Civil Structures Examination of soil stability (preparation of soil model--sinking); Examination of SC 2 structures due to high temperature ( check of >70 °C environments); penetration, examination of machine foundation, liners; 2.Introduction of Maintenance Rule Guidelines for establishment of monitoring of maintenance goals (deterministic and risk based) (all of specialty); Benchmark (High pressure safety injunction system); 3.Configuration management programs (Programs for reconstruction short, medium, long terms) 4.I & C program modification 5.Making of Final Environmental Usage Report

18 PROJECT ORGANIZATION PROJECT MANAGEMENT Project administration Power Uprating LR In-house team team PROJECT TEAM PROJECT PLANNING, SCHEDULING, CO-ORDINATION, CONTRACTING, DOCUMENTATION, QA RELATED ACTIVITIES: HUMAN PROGRAM, PUBLIC RELATIONS Project Supervisory Board FSAR upgrading Scientific committees: Reactor, Mechanical Eq., Civil structures, ISI, Water chemistry

19 Thanks for your attention!

20 PTS analyses 1.HAEA guideline (Analyses of RPV due to PTS events, No.: 3.17); 2.Scope of PTS transients (10 -5 /év); 3.Termo hydraulic analyses (transient pressure, temperature); 4.Calculation of neutron fluent at RPV; 5.Calculation of allowable T k (critical transient temperature) value (fracture mechanics); 6.Evaluation RPV embrittlement; 7.Determination of the lifetime of RPV; 8.Determination of technical and administrative measures for 50 (60) years of RPV lifetime; 9.Summary of PTS results for FSAR; 10.Summary (PR document); Deadline: End of 2007

21 Scope of the calculations Scope: Safety Category 1&2 systems 1. Equipments in the main coolant system (Class 1): Reactor + reactor internals Pressurizer & MCP & MIV Steam Generator Main coolant piping 1.Class 2 systems: Piping Heat Exchangers Pumps Tanks Valves

22 Main Passive/Active VVER 440/213 Components VVER 440/213 Components REACTOR/P pressure vessel CR drive/A CR drive housing/P Steam Generator/P MCP shaft/A MCP pump/A MCP housing/P MGV shaft./A MGV motor/A MGV housing/P PRESSURIZER/P Primary piping/P heater patron /P Cable/P

23 Tasks: 1. Strengths calculations (& embrittlement) (ASME I, III, XI); 2. Review of overpressure protection ; 3. Fatigue calculations (50+10 years, power up rating: 108%, thermal stratifications); 4. Determination of fatigue monitoring places and parameters; 5. Summary document for FSAR Deadline: Mid of 2007. Check of the design against ASME BPVC code requirements for selected SSCs

24 Political support On 21 th November, 2005 the Hungarian Parliament has approved a resolution (votes with 339 Yes, 4 No, 8 Abstention): 1)To initiate activities of preparing for establishment of radioactive waste repository for low and medium level of radioactive waste, 2)Extension of the operational life time of PAKS NPP The resolution reads as follows: “Under Act CXVI of 1996 on Atomic Energy, Article 7, Section (2) the Parliament approves, preliminarily and in principle to initiate activities of preparing for the establishment of a radioactive waste repository for low and medium level waste in the administrative area of Bátaapáti, in the region of Bátaapáti (Üveghuta), in a territory which was previously qualified suitable from geological point of view. The Parliament takes note of the information on the extension of the operational life-time of Paks Nuclear Power Plant, as a solution necessary for the long-time and safe provision of the country with electric energy.”