Presentation is loading. Please wait.

Presentation is loading. Please wait.

Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis.

Similar presentations


Presentation on theme: "Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis."— Presentation transcript:

1 Lincoln Public School- Lincoln, MA

2 Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis Building Analysis Space Usage Summary Educational Philosophy Summary Next Steps

3 Lincoln Public Schools 3 March 8, 2011 Meeting #2 Consultants Nitsch Engineering, Inc. Sandra Brock, PE, LEED AP - Civil Engineer Foley Buhl Roberts & Associates, Inc Jonathan Buhl, PE - Structural Engineer Garcia.Galuska.DeSousa Consulting Engineers Inc. Carlos DeSousa, PE – Electrical Engineer Dominick Puniello, PE, LEED AP – Mechanical Engineer Christopher Garcia, PE – Plumbing/ Fire Protection Engineer

4 Lincoln Public Schools 4 March 8, 2011 Meeting #2 Groundwork o Review existing conditions information o Prepare schedule and work plan Meeting # 1Goals, Values and Visioning ObjectivesFollow-up o Review schedule and process o Discuss goals, values o Discuss upcoming Visioning sessions o Site walk thru with Engineers and Facilities Coordinator o Conduct Visioning Sessions o Conduct User Group meetings Meeting # 2 Site Analysis, Existing Conditions, Building Usage and Philosophy ObjectivesFollow-up 2/08/11 3/08/11 o Prepare contract o Obtain and review all available/ pertinent documents o Review Educational Philosophy o Review site analysis, existing conditions and space usage o Prepare goals and values from four visioning sessions o Prepare Initial Space Summary o Develop evaluation criteria for preliminary alternatives Meeting # 3 Goals, Values and Initial Space Summary ObjectivesFollow-up 3/22/11 o Submit initial space summary to MSBA for review o Develop Preliminary Alternative Concepts Meeting # 4 & 5 Preliminary Alternative Concepts ObjectivesFollow-up 4/05/11; 4/12/11 o Review and Approve Preliminary Alternative Concepts o Approve Preliminary Design Program Submission o Complete Preliminary Design Program Submittal for MSBA o Meet with MSBA o Develop Proposed Alternatives & Preliminary Evaluation Meeting # 6 Preliminary Evaluation of Proposed Alternatives ObjectivesFollow-up 4/26/11 o Review Preliminary Evaluation of Proposed Alternatives o Submit Preliminary Alternatives to MSBA for review o Meet with MSBA o Develop Selected Alternatives and evaluate Meeting # 7 Finalize Preliminary Alternatives ObjectivesFollow-up 5/10/11 o Review and Approve Preliminary Alternative(s) o Develop Final Evaluation of Alternatives & Preferred Solution Meeting # 8 Final Evaluation of Alternatives ObjectivesFollow-up o Review Final Evaluation of Alternatives & Confirm Preferred Solution o Prepare Preferred Schematic Report 5/24/11 * Lincoln School Feasibility Study Work Plan Meeting # 9 Preferred Schematic Report ObjectivesFollow-up o Review and Approve Preferred Schematic Report o Submit Preferred Schematic Report to MSBA o MSBA Facilities Assessment Subcommittee and BOD Vote 6/07/11 o Review goals and values o Review and Approve Initial Space Summary o Establish Alternative Evaluation Criteria

5 Lincoln Public Schools 5 March 8, 2011 Meeting #2 Project Update Analysis of Existing Conditions and Reports - Civil/Landscape - Architectural - MEP/FP - Structural - Food Service - Hazardous Materials Educational Program/Philosophy Meeting with LPS Administration School, Multi-Board and Community Visioning Meetings Initial User Group Programming Meetings (3 Days)

6 Lincoln Public Schools 6 March 8, 2011 Meeting #2 N Site Analysis - Natural Features WetlandsWetlands WetlandsWetlands WetlandsWetlands FIELD HOUSE BROOKS SCHOOL LINK SMITH SCHOOL Warm Summer Breezes Cold Winter Winds Solar Orientation Winds Tree Line/Wooded Areas Stream Wetlands 50 Foot Buffer 100 Foot Buffer JUNE 21 AM JUNE 21 PM DEC 21 AM MARCH 21 AM MARCH 21 PM DEC 21 PM LINCOLN ROAD BALLFIELD ROAD HARTWEL L PODS

7 Lincoln Public Schools 7 March 8, 2011 Meeting #2 Site Analysis - Built Environment N Vehicular Traffic Athletic Fields Playgrounds Community Spaces - Interior - Exterior - External program Views Neighbors Septic Emergency Drive Main Entrances Parking Property Line Conservation Land LINCOLN ROAD HARTWEL L PODS Play SMITH SCHOOL LINK BROOKS SCHOOL FIELD HOUSE * * * * * *

8 Lincoln Public Schools 8 March 8, 2011 Meeting #2 Site Analysis - Site Circulation N Parking -Remote from controlled entrances Buses - 3 Drop- off locations Inadequate parking at main entrances Inadequate parking for community use Congestion at Smith drop-off LINCOLN ROAD HARTWEL L PODS SMITH SCHOOL LINK BROOKS SCHOOL FIELD HOUSE 1 2 3

9 Lincoln Public Schools 9 March 8, 2011 Meeting #2 Site Analysis - General Site/Civil/Fields View Across PlayfieldsView at Smith Lot Exit Site Issues Storm drainage appears insufficient; ponding observed along paved edges Downspouts discharge directly onto ground Parking lot to east of Reed half underwater occasionally Driveways, parking lots, sidewalks and curbs in fair to poor condition Handicap accessibility does not meet MAAB code Water table is high, causing seasonal wet conditions at fields

10 Lincoln Public Schools 10 March 8, 2011 Meeting #2 Permitting Issues - Wetlands Wetlands Protection Act (310 CMR 10.00) – The site falls within an environmentally sensitive area and a Notice of Intent is required, the wetland resource areas include: Riverfront – Critical to have the limit of Riverfront determined, this has a direct impact on project Bordering Vegetated Wetlands Bank Land Underwater Lincoln Wetlands Protection Bylaw - includes 50-foot “no disturb area” Natural Heritage & Endangered Species – the site does not fall within Priority or Estimated Habitat and does not contain a certified vernal pool per MASSGIS Flood Plain – the majority of the site is not located within a 100-year floodplain. There is a 100-year floodplain associated with Stony Brook but is generally confined to Stony Brook channel. Limit of Riverfront Area? Wetland Map From Lincoln GIS

11 Lincoln Public Schools 11 March 8, 2011 Meeting #2 Permitting Issues Zoning - Zone – R-1, Single Family Residential – the zoning for schools vary greatly depending on the Town’s regulations and their interpretation of the Dover Amendment. The Dover Amendment exempts schools from certain requirements of a Zoning Bylaws and Ordinances. It is critical to have a full understanding of the Towns interpretation of the Dover Amendment and the requirements and extent of review. Surface Water Supply Protection – site falls within water supply protection zone – Zone II, this will impact the drainage design. USEPA NPDES – disturbances over one acre require a submission of a Notice of Intent (NOI) that includes the stormwater pollution prevention plan to the EPA prior to beginning construction. This permit is signed by the operators of the construction site – the Owner and the Contractor Sanitary Sewer – There is a functioning existing 14,000 gallon per day Title 5 Septic System (1994) on site. Recommend the existing site be maintained. The function, size, and status of the existing Septic System will need to be confirmed with the Board of Health.

12 Lincoln Public Schools 12 March 8, 2011 Meeting #2 Existing Septic Information 3 septic fields Main leach field under the soccer field (13,792 gpd) – 1994 designed for 14,000 gpd –not a pressure dosing system - works on a siphon Hartwell School leach field (2,880 gpd) – 1969 no design flows available Codman Pool leach field (2,500 gpd) – 1984 no design flows available Total of 19,172 gallons per day based on Title 5 Board of Health could require installation a wastewater treatment plant to come into compliance with Title 5 and Groundwater Discharge permit It appears that the septic leach fields were functioning in 2000 and that the nitrogen loading was below the 10 mg/l required The 2000 GZA report also indicated that the actually flows based on water meter readings was approximately 2,800 gpd (15% of design/Title 5) in 2000 The GZA report indicated that monitoring wells were installed to monitor the water table water quality. Permitting Issues - Septic

13 Lincoln Public Schools 13 March 8, 2011 Meeting #2 Building Analysis – Existing Building Conditions Leaching Gutters Staining Exterior Envelope Walls Translucent panels in Smith Gym provide natural light Gutters damaged, corroded and leaking Soffit water damage and staining Exterior wall staining Translucent Panels

14 Lincoln Public Schools 14 March 8, 2011 Meeting #2 Building Analysis – Existing Building Conditions Exterior Staining Poor Sun ControlInsulated Glass Clerestories Exterior Envelope Windows Limited and ineffective solar control Majority of windows insulated Staining at exterior window units Clerestory shades and windows difficult to operate

15 Lincoln Public Schools 15 March 8, 2011 Meeting #2 Building Analysis – Existing Building Conditions Heat LossIce Dams Roof Leaks Exterior Envelope Roof Melted snow pattern indicates heat loss in roof Ice damming along north elevation Roof leaks throughout the school Skylights leak at interior Roof access from one location at flat roofs. Pitched roofs accessed from ladders All Membrane seams repaired in 2010 Skylight

16 Lincoln Public Schools 16 March 8, 2011 Meeting #2 Building Analysis – Existing Building Conditions Walk-off Mats Accessibility Lack of VestibulesExterior Doors Exterior Envelope Doors No vestibule at most main entrances Many exterior doors Main entrances are accessible Lack of effective entry mats

17 Lincoln Public Schools 17 March 8, 2011 Meeting #2 Building Analysis – Existing Building Conditions Ceiling Tiles Furnishings and Storage Retro-fitted Spaces Classrooms and Corridors Smith School Proper furnishings lead to improved acoustics and air quality Storage lacking within classrooms Water Damaged ceilings Mechanically and acoustically ill equiped occupied space Poor exhaust/ventilation in classrooms (Temperatures have reached 90’s in first grade classrooms) Equipment in Corridors

18 Lincoln Public Schools 18 March 8, 2011 Meeting #2 Building Analysis – Existing Building Conditions Skylights Asbestos Containing Materials Classrooms and Corridors Brooks School Ceiling tiles tested positive for asbestos VCT in Classroom is telegraphing and cracking at slab joint Skylights in classrooms are not equipped with light control Storage lacking in classrooms Ceilings have water damage Wall surfaces below 36” require frequent maintenance Missing or falling ceiling tiles Poor exhaust and ventilation in classrooms Storage Floor Tile

19 Lincoln Public Schools 19 March 8, 2011 Meeting #2 Building Analysis – Existing Building Conditions Raised CurbsRenovated Locker Rooms No Natural LightDivider Curtain Reed Gym/ Fieldhouse 1971 Addition No natural light Not connected to school Half of gym used as cafeteria Divider curtain has no acoustic separation Small kitchen located in previous storage space Kitchen storage/receiving remote from kitchen Insufficient adult shower and locker facilities Noisy HVAC Used by community nights and weekends.

20 Lincoln Public Schools 20 March 8, 2011 Meeting #2 Building Analysis – Existing Building Conditions Auditorium Seating Stage Backstage Return Air Grilles Brooks Auditorium Capacity: 330 Accessible seating distribution; replacement parts not available Curtains and lighting supported by chains, difficult to adjust Operation and acoustics performance lacking at partition

21 Lincoln Public Schools 21 March 8, 2011 Meeting #2 Building Analysis – Existing Building Conditions Stadium Seating Operable Partition Acoustical Treatment Exit Access Brooks Lecture Hall Capacity: 226 Space described as “gloomy” “bad acoustics”, and “difficult to use”. Perceived as “unsafe” Simultaneous use with auditorium - acoustics

22 Lincoln Public Schools 22 March 8, 2011 Meeting #2 Building Analysis – Existing Building Conditions Story RoomLibrary Entrance Reading Room Library/Link Large space by today’s standards Circulation desk serves as a functional work space Main entrance houses printers and copiers Inadequate lighting Noisy HVAC Story Room: - used frequently - poor ventilation - acoustic issues - tiered seating issues Circulation Desk

23 Lincoln Public Schools 23 March 8, 2011 Meeting #2 Building Analysis – Existing Building Conditions StageStorage Motorized Partition Smith School Gymnasium Gym separated by motorized partition, used frequently Acoustics need improvement Stage is useful but safety hazard No backstage; wings currently used as kitchen storage Dead spots in floor Parent pickup in gym causes floor damage Inadequate office Acoustical Treatment

24 Lincoln Public Schools 24 March 8, 2011 Meeting #2 Building Analysis – Code Issues Faculty Bathroom Toilet Stalls Stage Exit Doors Accessibility Stage not accessible Bathroom clearances and hardware Classroom exterior doors Raised curbs into locker room shower stalls Narrow circulation in bathrooms Noise levels: mechanical acoustic separation

25 Lincoln Public Schools 25 March 8, 2011 Meeting #2 Building Analysis – Foodservice Serving Area in Pantry Kitchen View Through Serving Aisle Pre-K through 4 Serving Pantry Kitchen Congested Aisle Cluttered Dish Washing Area Extremely congested space Electric oven used to cook limited range of items Inadequate aisle spacing Kitchen items stored outside kitchen, between kitchen servery and stage Some equipment could be reused in renovation Inadequate space for servery, food prep, cooking, and storage Crabtree McGrath, Consulting Partners, Inc.: Preliminary Report, dated 3-23-2011

26 Lincoln Public Schools 26 March 8, 2011 Meeting #2 Building Analysis – Foodservice Addition off gym used as table, trash can, salad bar, and paper storage Deliveries travel across gym floor to reach kitchen Crabtree McGrath, Consulting Partners, Inc.: Preliminary Report, dated 3-23-2011 View Through Galley Style KitchenGas Fired Range Field House Kitchen Storage/Receiving Addition Storage Addition Behind GymStorage Addition Interior Field House Kitchen Congested room, difficult to maintain proper separation of function Inefficient gas range, not allowed by Mass CHPS Equipment worn and end of life, Some could be reused in renovation

27 Lincoln Public Schools 27 March 8, 2011 Meeting #2 Building Analysis – Structural One-story Wood or steel framed roofs Concrete slab on grade Conventional spread footings Masonry veneer exterior with CMU or Steel stud backup Structure is in satisfactory condition – no evidence of failure or distress (Horizontal splitting/ checking in timber beams is normal, not a concern) Roofs designed for snow loads of 30 psf to 40 psf. Current code flat roof design snow load in Lincoln is 42.4 psf, plus drifting snow (as applicable). Pre-1994 buildings do not have clearly defined lateral load resisting systems Boiler Rooms and utility tunnels in Smith School experience seasonal flooding FBRA Consultants: Preliminary Report, dated March 8, 2011 Snow Drift Conditions at Smith Flooding in Boiler Room Roof Beam Checking Snow Drifting Conditions at Brooks

28 Lincoln Public Schools 28 March 8, 2011 Meeting #2 Click to edit the outline text format Second Outline Level  Third Outline Level Fourth Outline Level  Fifth Outline Level  Sixth Outline Level  Seventh Outline Level  Eighth Outline Level  Ninth Outline LevelClick to edit Master text styles  Second level  Third level  Fourth level  Fifth level Existing electrical equipment has reached life expectancy and requires replacement. The Link electrical service is in good condition. Original panels in the mechanical spaces are severely corroded and have live bussing. Click to edit Master text styles Second level Third level Fourth level Fifth level Click to edit Master text styles Second level Third level Fourth level Fifth level Main Service Switch at Brooks Building Main Service Switch at Link Electric Panels at Field House Corroded Electrical Panels at Brooks Building Boiler Room Building Analysis – Electrical: Distribution System

29 Lincoln Public Schools 29 March 8, 2011 Meeting #2 Click to edit the outline text format Second Outline Level  Third Outline Level Fourth Outline Level  Fifth Outline Level  Sixth Outline Level  Seventh Outline Level  Eighth Outline Level  Ninth Outline LevelClick to edit Master text styles  Second level  Third level  Fourth level  Fifth level Receptacles are adequate but not optimal. Lack of outlets in Media Center. Click to edit Master text styles Second level Third level Fourth level Fifth level Click to edit Master text styles Second level Third level Fourth level Fifth level G4000 Wiremold with Data & Power at Classrooms Lack of Media Center Receptacles at Computer Tables Building Analysis – Electrical: Branch Circuits

30 Lincoln Public Schools 30 March 8, 2011 Meeting #2 Click to edit the outline text format Second Outline Level  Third Outline Level Fourth Outline Level  Fifth Outline Level  Sixth Outline Level  Seventh Outline Level  Eighth Outline Level  Ninth Outline LevelClick to edit Master text styles  Second level  Third level  Fourth level  Fifth level Interior Lighting System - The lighting system has had lamps and ballasts changed to energy saving type. New lighting systems will control glare and have better controls such as daylight dimming. The Link lighting has glare control presently. Click to edit Master text styles Second level Third level Fourth level Fifth level Click to edit Master text styles Second level Third level Fourth level Fifth level Library/Media Center LightingAuditorium Housing Lighting Typical Wraparound Classroom Lighting Typical Linear Classroom Lighting at Link Building Analysis – Electrical: Lighting System

31 Lincoln Public Schools 31 March 8, 2011 Meeting #2 Click to edit the outline text format Second Outline Level  Third Outline Level Fourth Outline Level  Fifth Outline Level  Sixth Outline Level  Seventh Outline Level  Eighth Outline Level  Ninth Outline LevelClick to edit Master text styles  Second level  Third level  Fourth level  Fifth level New code requires 2 hour rating of feeders and Equipment location. Emergency lighting is through battery units. Click to edit Master text styles Second level Third level Fourth level Fifth level Emergency GeneratorTypical Emergency Battery Head Building Analysis – Electrical: Emergency Lighting

32 Lincoln Public Schools 32 March 8, 2011 Meeting #2 Click to edit the outline text format Second Outline Level  Third Outline Level Fourth Outline Level  Fifth Outline Level  Sixth Outline Level  Seventh Outline Level  Eighth Outline Level  Ninth Outline LevelClick to edit Master text styles  Second level  Third level  Fourth level  Fifth level System is up to code but is problematic. Panel is in “trouble”. Click to edit Master text styles Second level Third level Fourth level Fifth level Main Fire Alarm PanelTypical Heat Detector Building Analysis – Electrical: Fire Alarm System

33 Lincoln Public Schools 33 March 8, 2011 Meeting #2 Click to edit the outline text format Second Outline Level  Third Outline Level Fourth Outline Level  Fifth Outline Level  Sixth Outline Level  Seventh Outline Level  Eighth Outline Level  Ninth Outline LevelClick to edit Master text styles  Second level  Third level  Fourth level  Fifth level Headend room is in good condition but not to current standards. New Avaya telephone system in good condition. Existing clock system needs to be replaced. Click to edit Master text styles Second level Third level Fourth level Fifth level MDF RackTelephone System Classroom Telephone Handset with Clock/Speaker Building Analysis – Data/Telephone/Clock System

34 Lincoln Public Schools 34 March 8, 2011 Meeting #2 Click to edit the outline text format Second Outline Level  Third Outline Level Fourth Outline Level  Fifth Outline Level  Sixth Outline Level  Seventh Outline Level  Eighth Outline Level  Ninth Outline LevelClick to edit Master text styles  Second level  Third level  Fourth level  Fifth level Click to edit Master text styles Second level Third level Fourth level Fifth level Click to edit Master text styles Second level Third level Fourth level Fifth level Firetube BoilerCast Iron Sectional Boiler The hot water heating plants should be upgraded in both buildings. The existing hot water boilers, pumps, accessories and associated wing and controls should be removed. A new high efficiency plant with all new boilers, pumps with VFDs, piping, breeching, combustion venting, accessories, power wiring and control would provide energy savings and long service life. Building Analysis – Mechanical: Boiler Plant

35 Lincoln Public Schools 35 March 8, 2011 Meeting #2 Click to edit the outline text format Second Outline Level  Third Outline Level Fourth Outline Level  Fifth Outline Level  Sixth Outline Level  Seventh Outline Level  Eighth Outline Level  Ninth Outline LevelClick to edit Master text styles  Second level  Third level  Fourth level  Fifth level The building pneumatic control system should be removed and replaced with a new direct digital control system and building energy management system. New DDC/BMS system offers improved energy savings and temperature control. Click to edit Master text styles Second level Third level Fourth level Fifth level Click to edit Master text styles Second level Third level Fourth level Fifth level ATC Compressor – Brooks Building ATC Control Panel – Brooks Building ATC Control Panel – Library Mechanical Room ATC Compressor – Library Mechanical Room Building Analysis – Mechanical: Automatic Temperature Control

36 Lincoln Public Schools 36 March 8, 2011 Meeting #2 Click to edit the outline text format Second Outline Level  Third Outline Level Fourth Outline Level  Fifth Outline Level  Sixth Outline Level  Seventh Outline Level  Eighth Outline Level  Ninth Outline LevelClick to edit Master text styles  Second level  Third level  Fourth level  Fifth level Auditorium – Ductwork located in Crawlspace Click to edit Master text styles Second level Third level Fourth level Fifth level Boy’s Locker room – Air Handling Unit The existing Locker room air handling units, ductwork and fin tube radiation should be replaced. The Auditorium and Lecture Hall air handling units should be replaced. The existing Field House heating and ventilation units and associated ductwork should be cleaned and refurbished at a minimum. Building Analysis – Mechanical: Air Handling Equipment

37 Lincoln Public Schools 37 March 8, 2011 Meeting #2 Click to edit the outline text format Second Outline Level  Third Outline Level Fourth Outline Level  Fifth Outline Level  Sixth Outline Level  Seventh Outline Level  Eighth Outline Level  Ninth Outline LevelClick to edit Master text styles  Second level  Third level  Fourth level  Fifth level Click to edit Master text styles Second level Third level Fourth level Fifth level Click to edit Master text styles Second level Third level Fourth level Fifth level Teachers Room – PTAC Unit (at window) Computer Server Room AC unit VAV Box Controls (Bypassed) Smith Building Classroom UV w/ DX cooling should be repaired (2 units) Smith building Teacher work and break room PTAC unit cooling should be repaired. Library Computer room VAV box installation and thermostat controls should be repaired. A new energy efficient computer room AC system should be installed to replace the existing split system unit. Building Analysis – Mechanical: Air Conditioning System Repairs

38 Lincoln Public Schools 38 March 8, 2011 Meeting #2 Click to edit the outline text format Second Outline Level  Third Outline Level Fourth Outline Level  Fifth Outline Level  Sixth Outline Level  Seventh Outline Level  Eighth Outline Level  Ninth Outline LevelClick to edit Master text styles  Second level  Third level  Fourth level  Fifth level Click to edit Master text styles Second level Third level Fourth level Fifth level Ceiling Recessed Unit Ventilator With Taped Grille Click to edit Master text styles Second level Third level Fourth level Fifth level Field House Lobby – Damaged Fin Tube Radiation Kitchen Hood - Brooks Building The existing Locker room air handling units, ductwork and fin tube radiation should be replaced. Damaged terminal heating equipment should be repaired or replaced. A new exhaust and make-up air system should be provided as part of any kitchen renovation project. Building Analysis – Mechanical: Miscellaneous

39 Lincoln Public Schools 39 March 8, 2011 Meeting #2 Click to edit the outline text format Second Outline Level  Third Outline Level Fourth Outline Level  Fifth Outline Level  Sixth Outline Level  Seventh Outline Level  Eighth Outline Level  Ninth Outline LevelClick to edit Master text styles  Second level  Third level  Fourth level  Fifth level Toilet Fixtures are in fair condition however do not meet current code for accessibility. New “high efficiency” plumbing fixtures are recommended. Science classroom/Tech Lab emergency fixtures do meet current code. Fixtures are supplied with cold water only. Emergency Fixtures are required to be supplied by tepid water. New fixtures are recommended. Floor Mounted Water Closet Wall Hung Water Closet Wall Hung Lavatories and Urinal Building Analysis – Plumbing: Fixtures

40 Lincoln Public Schools 40 March 8, 2011 Meeting #2 Click to edit the outline text format Second Outline Level  Third Outline Level Fourth Outline Level  Fifth Outline Level  Sixth Outline Level  Seventh Outline Level  Eighth Outline Level  Ninth Outline LevelClick to edit Master text styles  Second level  Third level  Fourth level  Fifth level Water service is 4” in size and adequate for renovations. Majority of distribution piping is original, several leaks have been repaired over time. Valves on the system show signs of corrosion. Science classrooms are supplied with domestic water. The system must be protected with backflow preventers to meet current code. Piping has reached its life expectancy. New piping systems are recommended. Building Analysis – Plumbing: Domestic Water System

41 Lincoln Public Schools 41 March 8, 2011 Meeting #2 Click to edit the outline text format Second Outline Level  Third Outline Level Fourth Outline Level  Fifth Outline Level  Sixth Outline Level  Seventh Outline Level  Eighth Outline Level  Ninth Outline LevelClick to edit Master text styles  Second level  Third level  Fourth level  Fifth level Brooks School/Field House are supplied by gas fired heater with 120 gallon storage tank (standard efficiency). Smith School is supplied by gas fired tank type heater (standard efficiency). Field House kitchen supplied by 120 gallon electric water heater. Field House Electric Water Heater Smith Water Heater Brooks Gas-Fired Water Heater Building Analysis – Plumbing: Hot Water System

42 Lincoln Public Schools 42 March 8, 2011 Meeting #2 Cast iron is used for sanitary and storm drainage. In general cast iron piping, above slab, can be reused in a major renovation where adequately sized. Video investigation of below slab piping is recommended. Science classroom piping system discharges to the on-site septic system. Majority of piping is cast iron. Traps and tailpieces of sinks are polypropylene. Building Analysis – Plumbing: Drainage System

43 Lincoln Public Schools 43 March 8, 2011 Meeting #2 Natural gas is supplied to each building. Exterior gas meters are located at the Field House, Smith Building and Brooks Building. Natural gas is provided in the science classrooms. Classrooms are equipped with manual emergency shutoff valves. Natural gas is provided for kitchen cooking equipment. Kitchen supply is equipped with an automatic shutoff valve. Brooks School Gas ServiceField House Gas Service Building Analysis – Plumbing: Gas System

44 Lincoln Public Schools 44 March 8, 2011 Meeting #2 Click to edit the outline text format Second Outline Level  Third Outline Level Fourth Outline Level  Fifth Outline Level  Sixth Outline Level  Seventh Outline Level  Eighth Outline Level  Ninth Outline LevelClick to edit Master text styles  Second level  Third level  Fourth level  Fifth level There are no automatic sprinkler systems in the buildings. In general, Massachusetts General Law M.G.L. c.148, s.26G requires that any existing building, including any additions or major alterations, which total more than 7,500 square feet in aggregate floor area must be sprinklered. Should the existing building undergo a major renovation the building will require an automatic sprinkler system to provide complete protection of all spaces. Building Analysis – Fire Protection

45 Lincoln Public Schools 45 March 8, 2011 Meeting #2 Building Analysis – Features and Deficiencies Positive Building Features  Existing gyms and auditorium  Library/Link in good condition  Views to surroundings  Campus feel  Well maintained Facility Deficiencies Include:  Sprawling facility  Roof leaks throughout schools  Hazardous materials reported  Inefficient and ineffective HVAC systems  Lack of control at main entrances  Site circulation  Lack of potable water  Lack of adequate teacher dining and private areas  Lack of adult bathrooms  Lack of adequate storage  Pest infestation  Inadequate kitchen and cafeteria spaces Educational Deficiencies Include:  Many classroom sizes below MSBA guidelines  Classrooms lack adequate ventilation  Closets used as programmed space, eg. SPED  Music program uses other designated classrooms  Current layout does not support team teaching  Current layout does not support teacher collaboration  Harsh or inadequate lighting. Code Deficiencies Include: Accessibility issues: Clearances, millwork, toilet rooms, door hardware, entrances exits, etc. Building is unsprinklered

46 Lincoln Public Schools 46 March 8, 2011 Meeting #2 Space Usage Summary 1948 1953 1955 1963 1970 1994 K GR 1 GR 2 GR 3 GR 4 & 5 GR 7 & 8 GR 6 SC MUS ART

47 Lincoln Public Schools 47 March 8, 2011 Meeting #2 Lincoln Public Schools Mission “ The Lincoln Public Schools seeks to unite our communities in challenging and equipping our students to: Acquire essential knowledge Think critically and independently Exhibit academic excellence Appreciate and respect diversity Demonstrate creativity Value reflection Work hard and play fair.”

48 Lincoln Public Schools 48 March 8, 2011 Meeting #2 Educational Philosophy Summary Two Schools within a School: The philosophy and curriculum are articulated and aligned as a K-8 program, however, operationally the scheduling, structure and administration are separate between the elementary and middle schools. Relational teaching bound by a community of learners: Communities are formed by the classroom, the grade, the school and the families. Enrollment Projection: 600 students confirmed. Preferred Class Size: 18 (K); 20 (1st); 21 (2nd-3rd); 22 (4th- 5th); 24 (6th-8th). Grade transition is seamless within and between buildings. Scheduling of Space: One teacher per classroom. Classrooms are clustered by grades. Specialized spaces support grade group clusters. A high level of intervention, support and collaboration within classrooms reduces special education needs. Physical structure should promote collaboration. Transition from “curriculum silos” to “project based learning” opportunities. The school is a green community interlaced with the greater community.

49 Lincoln Public Schools 49 March 8, 2011 Meeting #2 A Shared View “For a Pre-K-8 education, [the students] are together in the circle… This is community.”

50 Lincoln Public Schools 50 March 8, 2011 Meeting #2 Next Steps SBC Meeting #3, March 22, 2011 Discuss Goals and Values Review and Approve Initial Space Summary Review Alternative Evaluation Criteria

51 Thank You


Download ppt "Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis."

Similar presentations


Ads by Google