Gantt Charts. Scenario One Selling a new product Tasks:  Determine new product features (5 days)  Produce Prototype (10 days)  Design Graphics (8 days)

Similar presentations


Presentation on theme: "Gantt Charts. Scenario One Selling a new product Tasks:  Determine new product features (5 days)  Produce Prototype (10 days)  Design Graphics (8 days)"— Presentation transcript:

1 Gantt Charts

2 Scenario One Selling a new product Tasks:  Determine new product features (5 days)  Produce Prototype (10 days)  Design Graphics (8 days)  Perform Sales Calls (20 days)  Design Marketing Campaign (3 days)  Acquire Prototype Materials (11 days)  Conduct Marketing (30 days)

3 Scenario Two  The Recruitment Process  Agree job and person specification (1 day)  Prepare advertisement (2 days)  Receive enquiries and send further information (10 days)  Agree composition of interview panel (2 days)  Evaluate applications and prepare shortlist (3 days)  Conduct interviews (1 day)  Send offer letter to successful candidate (1 day)  Personnel manager to define job grade (5 days)  Publish advertisement on website (1 day)  Closing date for applications (1 day)  Book interview room (1 day)  Invite shortlisted applicants for interview (1 day)  Confirm selection decision ( 1day)

4 Scenario Three  Writing an article  Use Internet resources (0.5 days)  Evaluate what you find (1 day)  Create article (1 day)  Find audio and visual resources (1 day)  Reference finds in standard format (0.5 days)  Identify topic (0.5 days)  Consult library for books (0.5 days)  Find periodical articles (2 days)  Find background material (2 days)

5 Scenario Four  Building a house  Connect electricity (3 days)  Hire portable toilet (2 days)  Fencing and signs (5 days)  Connect water supply (4 days)  Locate and inspect building site (2 days)  Excavate over site (4 days)  Set out string lines (1 day)  Clear and level site (3 days)  Excavate footings (4 days)

6 Scenario Five  Introduction of a new computer room  Work out rooms expected use (1 day)  Create and test master image (0.5 days)  Install new computers etc. (0.5 days)  Install cabling and plugs (2 days)  Empty room (0.5 days)  Order furniture, fittings and computer equipment (0.5 days)  Test whole system (1 day)  Design room layout (0.5 days)  Install furniture and fittings (2 days)