Slide 1UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE UCSB 4-Hybrid Thermal Test System Status 17 June Sam Burke UCSB HEP Group.

Similar presentations


Presentation on theme: "Slide 1UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE UCSB 4-Hybrid Thermal Test System Status 17 June Sam Burke UCSB HEP Group."— Presentation transcript:

1 Slide 1UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE UCSB 4-Hybrid Thermal Test System Status 17 June Sam Burke UCSB HEP Group

2 Slide 2UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE Progress Input/Output Schematics Completed à Sensor I/O (4ea Hybrid Temps, Humidity, Peltier over temp) à Analog I/O (Peltier power, air flow, water flow) à Digital I/O (pulser, water, hi air, low air) Breakout board 19” panel layout Hybrid Temperature and Humidity Sensor Cable Assembly work

3 Slide 3UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE Progress Digital Temperature Sensor Measurements à Read out Dallas digital address à Measure Dallas Temperature against reference –Dallas Readout = 23.12 deg C +-0.5 deg C –Sensirion reference = 23.20 deg C +-0.9 deg C Flow Control Panel layout

4 Slide 4UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE Progress NIM Crate Received à NIM / TTL / NIM Module à Dual Pulse Generator à Logic (OR, AND) Module Flow Sensors Received

5 Slide 5UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE Future Plans Fabricate Digital I/O Breakout Board Fabricate Analog I/O Breakout Board Fabricate Sensor Interface Board Fabricate and test all 4 Hybrid Temperature Sensors

6 Slide 6UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE Future Plans Measure Relative Humidity with System à Measure analog voltage and check calibration à Verify correct LabView Sub VI (ie subroutine) Build Power Transformer board Reverse engineer Coolie Box relay board


Download ppt "Slide 1UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE UCSB 4-Hybrid Thermal Test System Status 17 June Sam Burke UCSB HEP Group."