Presentation is loading. Please wait.

Presentation is loading. Please wait.

Slide 1L3 Testing Meeting March 7, 2003UCSB Status-Anthony Affolder UCSB Testing Status Anthony Affolder (for the UCSB module testing group) Current testing.

Similar presentations


Presentation on theme: "Slide 1L3 Testing Meeting March 7, 2003UCSB Status-Anthony Affolder UCSB Testing Status Anthony Affolder (for the UCSB module testing group) Current testing."— Presentation transcript:

1 Slide 1L3 Testing Meeting March 7, 2003UCSB Status-Anthony Affolder UCSB Testing Status Anthony Affolder (for the UCSB module testing group) Current testing infrastructure Test results Module test equipment needs Software Needs Current testing through-put

2 Slide 2L3 Testing Meeting March 7, 2003UCSB Status-Anthony Affolder Testing Facilities Readiness Clean room adjacent to production area à Room layout finished à Currently in high bay with intentionally same layout –Missing only hybrid thermal cycling test à Clean room will be finished in April Storage cabinet with dry air flow in place for testing phase Long term module storage cabinets under construction at KSU

3 Slide 3L3 Testing Meeting March 7, 2003UCSB Status-Anthony Affolder UCSB Recent Infrastructure Projects Hybrid holding plates à Matches hybrid thermal cycling test stand à Can bond and test with low noise in same holder Burn-in low voltage distribution crate à LED indicators and fuse protection Crowbar à HV protection circuit à 12 each for FNAL/UCSB Module cold plate à Attaches to current module holder Hybrid clamshell Module clamshell

4 Slide 4L3 Testing Meeting March 7, 2003UCSB Status-Anthony Affolder Hybrid Visual Inspection Once FNAL indicated lift off problem, closely visually inspected our 5 hybrids à Found 1 wire bond lift off à Bonds have redundancy so no failure seen –Removed broken bond to eliminate chance of short à Will closely monitor for lift off/ wire breaks throughout production process

5 Slide 5L3 Testing Meeting March 7, 2003UCSB Status-Anthony Affolder Current UCSB ARC Setup 3 ARC Controller + 5 new ARC FE + 1 old ARC FE 1 Hybrid testing (2 Hybrid clamshells) 2 Module testing (Module clamshell) à 2 LED systems à DEPP HV supply –Missing hybrid-to-utri adapters to fully use capacity Hybrid Clamshell Module Clamshell DEPP LED Controller ARC Controller ARC crate

6 Slide 6L3 Testing Meeting March 7, 2003UCSB Status-Anthony Affolder ARC Hybrid Test Results (1) 5 hybrids tested on arrival à All good, but fail current requirement given in the Procedures for Module Testing à Pedestal test reproducible, but noise measured very sensitive to digitization effects –Measured noise varying the pedestal by changing VPSP value –Digitization effects cause variations larger than ±20% Hybrid noise requirements should be changed à N i within 50% of average à 0.3 < N i < 1.5 –Removes chance of chips with uniformly low/high noise from passing requirements See hep.ucsb.edu/cms/cmsUCSB.html for more complete description

7 Slide 7L3 Testing Meeting March 7, 2003UCSB Status-Anthony Affolder ARC Hybrid Test Results (2) 4 hybrids have had APV bonded to pitch adapters à All channels are good Hybrid clamshells enable testing without large pickup effects at chip edges à Hybrid isolated with base plate and lid grounded à Same requirements can be made for hybrids with or w/o PA bonded

8 Slide 8L3 Testing Meeting March 7, 2003UCSB Status-Anthony Affolder ARC Gain Measurements (1) Multi-point gain added to ARCS 6.0 beta software à Thanks to the Aachen group Tests are very quick and have advantages over pulse shape measurements à More uniform à More stable à Gain linearities à Gain variations Strongly suggest that test be added to all M800 production. Will be included TOB testing  Make requirements on gain slope, offset and fit  2

9 Slide 9L3 Testing Meeting March 7, 2003UCSB Status-Anthony Affolder ARC Gain Measurements (2) 2 of 24 chips so far have no response with low injection values à Only occurs in peak mode inverter on Caused by initialization defaults in ARCS tests à VPSP set too low –Thanks to T. Franke and M. Raymond for help VPSP setting will be modified in new release à Removes all seen irregularities

10 Slide 10L3 Testing Meeting March 7, 2003UCSB Status-Anthony Affolder ARC Module Test Results (1) 1 Prototype Module Tested 1 Production Module Tested à Module testing in UCSB clamshell decreases common-mode noise to the point where location of opens become detectable by their noise levels –PA-sensor –Sensor-sensor à Pinholes act as if saturated à High current channels can have higher noise (Bad IStrip à Slight noise increase on chip edges à Two neighboring channels have high noise only in peak inverter on Pinhole PA-sensor open Sensor-sensor open Bad CAC Bad Istrip Unknown Problem PEAK ON

11 Slide 11L3 Testing Meeting March 7, 2003UCSB Status-Anthony Affolder ARC Module Test Results (2) LED pinhole test à Bonded one inherent pinhole on purpose à Test acted as expected –120  A needed to unsaturate pre-amp  Not clear if maximum current (400  A) supplied sufficient to find “high current” pinholes Pinhole Unknown Problem PA-sensor open Sensor-sensor open PEAK ON

12 Slide 12L3 Testing Meeting March 7, 2003UCSB Status-Anthony Affolder ARC Module Test Results (3) Gain test à Pinhole clear by lack of gain à Opens clear by higher gain Pinhole Sensor-sensor open PA-sensor open Unknown Problem Bad CAC Bad Istrip PEAK ON

13 Slide 13L3 Testing Meeting March 7, 2003UCSB Status-Anthony Affolder ARC Test X-calibrations Minimal X-calibration has been performed à Same faulty channels found at FNAL/UCSB on prototype model à CERN FHIT/UCSB ARC test compared –Pedestals very similar –Noise is slightly higher than CERN FHIT measurement Not understood if it is FHIT/ARC difference, a software difference, an environmental difference, or a digitization effect Once model production begins, plan to exchange modules with FNAL for X-calibration

14 Slide 14L3 Testing Meeting March 7, 2003UCSB Status-Anthony Affolder ARCS Database No entries yet put into official database à Waiting for ARCS interface for database upload and database definition to stablize All testing results have been made available to silicon community on local website à hep.ucsb.edu/people/affolder/module_test_UCSB.html

15 Slide 15L3 Testing Meeting March 7, 2003UCSB Status-Anthony Affolder DAQ status 1 full DAQ stand available at UCSB à Planned only for Vienna box tests with modules Limited number of tests performed à See P. Gartung’s talk à Focus on bringing up hardware/software for Vienna box à Xdaq, LT, and Xrod software all compiled and run –Still working to understand controls/output No LED stand planned for DAQ No database work done as of yet

16 Slide 16L3 Testing Meeting March 7, 2003UCSB Status-Anthony Affolder Vienna Box Status Vienna Box recently arrived at UCSB à No modification necessary to use with TOB module carrier plates à Full compliment of plates currently in machine shop à LV distribution ready à Just received HV controllers (both the A128HS and A1303) –Integrating as fast as possible à Demonstrated each slot works with hybrids à Thermal cycled box between –25 to 30° C with chiller à Need hardware to test more than one channel at a time –See P. Gartung’s talk for more details

17 Slide 17L3 Testing Meeting March 7, 2003UCSB Status-Anthony Affolder Current Hardware Needs ARC Needs à 1 DEPP à 1 LED system –Will be picked up this week Torino Interlock Box à In-route 3 Electrometers à 2 in-route Flat cable-Lemo adapter à Under construction at UCSB 13 hybrid-to-utri ver. D à 1 in-route –Used for both ARC module and burn-in test –Limiting factor in testing through-put Hybrid thermal cycling box à Lack hardware/software à Tests will be performed by A. Honma’s group for M800 à We are aiding in the manufacturing of test stand DAQ components à 8 VUTRI –10 in-route à 9 PAACB –6 in-route à 1 TPO –1 in-route à 1 CCU –1 in-route à 2 PAACB to TPO interface –Needed for backplane pulsing

18 Slide 18L3 Testing Meeting March 7, 2003UCSB Status-Anthony Affolder Current Testing Software Needs Hybrid Characterization à Database input Module Testing à IV scan, backplane pulsing test, database input Module Burn-in Rods à Beginning to assemble necessary infrastructure for rod assembly/ burn-in à Xrod and LT software package already compiled and running

19 Slide 19L3 Testing Meeting March 7, 2003UCSB Status-Anthony Affolder Current Estimated Testing Through-put Hybrid Arrival Testing à 24 hybrids per day à Matches peak production (+ contingency) à Requires dedicated tech Module Basic Test à 2 ARC LED stands but only 1 hybrid-to-utri version D à 12 modules per day à Requires dedicated tech Module Burn-in (Vienna Box) à See P. Gartung’s talk for details à Lack of hybrid-to-utri adapters limits testing through-put to 1 –While burn-in test underway, no module testing possible à Module characterization test will be done at beginning/end of test cycles ARC After Burn-in Test à Not clear how much ARC testing necessary after burn-in –Depends on grounding/pickup issues –LED is minimal test Time estimates do not include database entry. After finishing test equipment acquisition/integration, database will be first priority.


Download ppt "Slide 1L3 Testing Meeting March 7, 2003UCSB Status-Anthony Affolder UCSB Testing Status Anthony Affolder (for the UCSB module testing group) Current testing."

Similar presentations


Ads by Google