2
N EXISTING FACILITIES BUILDING “A” -Principal’s Office -Workroom -(9) 3 RD Grade Classrooms - (4) 4 TH Grade Classrooms -Life Skills Classroom -Title I (intervention and parent resource) “A” BUILDING “B” -(6) 4 TH Grade Classrooms -PTO Large Classroom “B” -Resource Room -(2) WINGs Rooms -Music Classroom -Counselor’s Office -Nurse’s Office -Storage -District Copier Repairman BUILDING “C” “C” -Library -Computer Classroom -Teacher Workroom -Tile I (Intervention Computer Lab) BUILDING “D” “D”
3
N EXISTING FACILITIES BUILDING “E” -Cafeteria -Art Classroom -Special Education Classroom “A” “B” “C” “D” “E” BUILDING “F” -Assistant Principal’s Office -(10) 5 th Grade Classrooms -Hearing Impaired Classroom “F” BUILDING “G” -Gymnasium (Not In Use) “G” OTHER BUILDINGS #1 District Bus Shop #2 District Bus Shop #3 District Maintenance Shop #4 PE Classroom #5 Not On Site #6 Filed House #7 Filed House #8 Football Field #9 Pavilion & Amphitheater #10 Pavilion 123 4 5 67 9 10 8 Car Drop Off Car Drop Off Loop Bus Drop Off Loop Bus Drop Off
4
N PHASE I NEW CAFETERIA Reduce/Re-rout Car Drop Off Loop “A” “B” “C” “D” “E” “F” “G” 123 4 5 67 9 10 8 Car Drop Off Car Drop Off Loop Bus Drop Off Loop Bus Drop Off Remove existing canopy between Building “D” and “E” Build New Cafeteria Car Drop Off Loop -Seating for 250 students -590 currently enrolled -Possible Stage -Food Equipment by Owner -Furniture by Owner -Building must be Sprinklered -Approximate size 6,500 sq ft
5
-Reception -Principal’s Office -Assistant Principal’s Office -Counselor’s Office -Library -Computer Lab PTO Meeting Area -Workroom -Teachers’ Workroom -(2) Small Classrooms Special Ed. Hearing Impaired -Storage and Vault -Furniture by Owner -Building must be Sprinklered -Approximate size 14,868 sqft N PHASE II NEW ADMIN. BUILDING Remove #9 Pavilion and Amphitheater “A” “B” “C” “D” “E” “F” “G” 123 4 5 67 9 10 8 Car Drop Off Bus Drop Off Loop Bus Drop Off Build New Admin Building Car Drop Off Loop
6
Renovation of Building “A” -Adapt/Reuse Principal’s Office Workroom -Create Three (3) Classrooms Total of 18 Classroom Renovation of Building “B” -Adapt/Reuse PTO Large Classroom -Create Two (2) Classrooms Total of 8 Classrooms Renovation of Building “D” -Adapt/Reuse Library Computer Classroom Teacher Workroom -Create Art Classroom Five (5) Classrooms Total of 7 Classrooms N PHASE III RENOVATIONS “A” “B” “C” “D” “E” “F” “G” 123 4 5 67 10 8 Car Drop Off Bus Drop Off Loop Bus Drop Off Car Drop Off Loop
7
Demolish Building “E” Demolish Building “F” Demolish Building “G” N PHASE IV DEMOLITION “A” “B” “C” “D” “E” “F” “G” 123 4 5 67 10 8 Car Drop Off Bus Drop Off Loop Bus Drop Off Car Drop Off Loop
8
Bus Drop Off Loop Bus Drop Off Car Drop Off Car Drop Off Loop Bus Drop Off New Bus Drop Off Loop Car Drop Off New Car Drop Off Loop Relocate Bus Parking Relocate Car Drop Off & Bus Drop Off Build New Wing -(8) Classrooms -Multi-Purpose Room Stage/Gym/P.E. -Conference Room Office -Storage Room -Staff Restroom -Restroom Facilities -Furniture by Owner -Building must be Sprinklered -Approximate size 21,720 sqft N PHASE V NEW WING “A” “B” “C” “D” 123 4 5 67 10 8 Bus Parking
9
Bus Drop Off New Bus Drop Off Loop Car Drop Off New Car Drop Off Loop Build Classroom Wing -(12) Classrooms -Conference Room Office -Storage Room -Staff Restroom -Restroom Facilities -Furniture by Owner -Building must be Sprinklered -Approximate size 15,720 sqft N PHASE VI NEW CLASSROOM WING “A” “B” “C” “D” 123 4 5 67 10 8 Bus Parking
10
Bus Drop Off New Bus Drop Off Loop Car Drop Off New Car Drop Off Loop Demolish Building “C” Demolish Building “D” N PHASE VII DEMOLITION “A” “B” “C” “D” 123 4 5 67 10 8 Bus Parking
11
Bus Drop Off New Bus Drop Off Loop Car Drop Off New Car Drop Off Loop Build Classroom Wing -(12) Classrooms -Conference Room Office -Storage Room -Staff Restroom -Restroom Facilities -Furniture by Owner -Building must be Sprinklered -Approximate size 15,720 sqft N PHASE VIII NEW CLASSROOM WING “A” “B” 123 4 5 67 10 8 Bus Parking
12
Bus Drop Off New Bus Drop Off Loop Car Drop Off New Car Drop Off Loop Demolish Building “A” Demolish Building “B” Demolish #10 Pavilion N PHASE IX DEMOLITION “A” “B” 123 4 5 67 10 8 Bus Parking
13
Bus Drop Off New Bus Drop Off Loop Car Drop Off New Car Drop Off Loop Build Classroom Wing -(12) Classrooms -Conference Room Office -Storage Room -Staff Restroom -Restroom Facilities -Furniture by Owner -Building must be Sprinklered -Approximate size 15,720 sqft N PHASE X NEW CLASSROOM WING 123 4 5 67 8 Bus Parking
14
Bus Drop Off New Bus Drop Off Loop Car Drop Off New Car Drop Off Loop FOOTBALL FIELD PARKING LOT GYMNASIUM CLASSROOM ADDITION CAFETERIA DINING ADDITION PLAYGROUND N BEYOND PHASE X 123 4 5 67 8 Bus Parking Parking Lot